Decision Session - Executive Member for Transport - Expired approved this item on Wednesday 4 September 2013. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

That the Cabinet Member: (i) approved the overall scheme layout, including the changes and additional measures proposed within this report (i.e. as per Option 2 in paragraph 45, and as illustrated in Annexes A , C,D, E, F & G . (ii) Agreed in principal the Toucan Crossing and PROW diversion as illustrated at Annexes B & H but deferred a final decision to enable further investigative work. (iii) gave authorisation for all elements of the scheme to be implemented as soon as practically possible, which in some cases may need to be after associated Traffic Regulation Orders are put in place, (iv) gave authorisation for the advertisement of the necessary Traffic Regulation Orders relating to the following: · an extension to the existing 20mph School Safety Zone on Haxby Road, · An amendment to the speed limit on the roundabout junction of Haxby Road with the A1237 Outer Ring Road, along with authority to enact these Orders if no objections are received (any substantive objections to be considered at a future Officer in Consultation meeting). (v) gave authorisation for Officers to commence the necessary legal process for the proposed diversion of the existing Public Footpath, New Earswick No.1. Reason: To provide a safe and convenient route for pedestrians and cyclists between the villages of Haxby , Wigginton and New Earswick with the Clifton Moor leisure and retail park. In addition, the route will form the key part of a wider ‘Outer Orbital Route’ for cycling and walking from Poppleton to the University of York via Clifton Moor and Monks Cross. That the Cabinet Member: (i) approved the overall scheme layout, including the changes and additional measures proposed within this report (i.e. as per Option 2 in paragraph 45, and as illustrated in Annexes A , C,D, E, F & G . (ii) Agreed in principal the Toucan Crossing and PROW diversion as illustrated at Annexes B & H but deferred a final decision to enable further investigative work. (iii) gave authorisation for all elements of the scheme to be implemented as soon as practically possible, which in some cases may need to be after associated Traffic Regulation Orders are put in place, (iv) gave authorisation for the advertisement of the necessary Traffic Regulation Orders relating to the following: · an extension to the existing 20mph School Safety Zone on Haxby Road, · An amendment to the speed limit on the roundabout junction of Haxby Road with the A1237 Outer Ring Road, along with authority to enact these Orders if no objections are received (any substantive objections to be considered at a future Officer in Consultation meeting). (v) gave authorisation for Officers to commence the necessary legal process for the proposed diversion of the existing Public Footpath, New Earswick No.1. Reason: To provide a safe and convenient route for pedestrians and cyclists between the villages of Haxby , Wigginton and New Earswick with the Clifton Moor leisure and retail park. In addition, the route will form the key part of a wider ... view the full minutes text for item 14.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 21 pages

Decision Session – Cabinet Member for 4 September 2013 Transport, Planning & Sustainability

Haxby to Clifton Moor Cycle Route Proposals Summary 1. This report discusses feedback from consultation on proposals to create an off-road shared cycle and pedestrian route along the A1237 (Outer Ring Road) corridor between the Haxby Road roundabout and the B1363 (Wigginton Road) roundabout. The aim is to provide a safe and convenient route for pedestrians and cyclists between the villages of Haxby, Wigginton and New Earswick with the Clifton Moor leisure and retail park. In addition, the route will form the key part of a wider ‘Outer Orbital Route’ for cycling and walking from Poppleton to the University of York via Clifton Moor and Monks Cross. 2. This report also covers the outcome of more recent detailed design work and the latest cost estimates. In addition, the report seeks approval to advertise the necessary TROs and to commence implementation of the scheme proposals.

Background 3. The council is committed to improving the cycle network, which is one of the key measures to deliver the Council Plan priority to ‘Get York Moving’. As part of this, there has been a long term aspiration to establish this cycle route, and it was included as a flagship scheme within the council’s successful bid for Local Sustainable Transport Funding (LSTF) in 2011. Within the total grant allocation of £4.6 million, £700K was earmarked for this cycle route project.

4. During 2012/13 feasibility design work was carried to explore various options and determine how best the route could be achieved. An indicative plan of the preferred option is shown in Annex A, which highlights the various component parts of the overall scheme. These are described in more detail in the Proposals section of the report.

5. The cycle route proposals have been developed in light of potential further improvements to the Outer Ring Road. In the medium term this could include upgrades to the existing roundabouts on the Outer Ring Road (funding is being sought through the West Yorkshire Transport Fund for this) and in the longer term dualling remains an option (requiring substantially more funding). One or both of these options could involve additional approach lanes to the Haxby Road roundabout. These possibilities have therefore been considered in the context of these proposals, with a view to minimising any abortive work. A dualling option would have the most effect, the additional space that could be required would result in the removal of part of the ramp on the eastern side of the new bridge, and a new path would need to be constructed on an alternative alignment should the road be widened on the south side. However, it is considered that the current proposals would be the least affected by any changes to improve traffic capacity for the Haxby Road roundabout. 6. As part of this feasibility work more detailed cost estimates were developed for all the components of the scheme, including options for crossing the railway. This demonstrated that the initial allocation of £700k would be insufficient to achieve an acceptable solution. The cost of the preferred option was estimated to be around £925k. However, this was still considered to represent good value in terms of the quality of the proposed facilities and potential usage levels, and within the overall grant allocation of £4.6million there was sufficient flexibility to adjust allocations for other proposals. Therefore as part of the Capital programme for 2013/14 a sum of £825k has been allocated for this scheme, with the intention of providing the remaining amount needed to complete the scheme in early 2014/15.

Proposals

Haxby Road Connection and Crossings

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Indicative Route PlanAppendix A 1 pages Download
PDF
Haxby Road North Crossing-Haxby Road Xing NorthAppendix B 1 pages Download
PDF
Haxby Road South Crossing-Haxby Road Xing SouthAppendix C 1 pages Download
PDF
Typical Bridge ExampleAppendix D 1 pages Download
PDF
Path alignment on Embankment BermsAppendix E 1 pages Download
PDF
Haxby to Clifton Moor Cycle RouteReport 21 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 2 attended
DM
Councillor Dave MerrettCabinet Member, apologies
JL
Councillor Janet LookerCommittee Member, present as substitute

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies