Condition of 17-21 Piccadilly

Agreed Executive 6 papers

Executive agreed this item on Thursday 25 June 2015. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

That the Executive agree to: ( i ) Apply for planning permission to demolish 17-21 Piccadilly and proceed with the works to demolish the building as quickly as possible, if that permission is granted. (ii) Receive a report in September 2015 setting out the work undertaken to assess a future regeneration of the area so that an appropriate future use for the site can be identified, which supports the overall development proposals for the Southern Gateway project and ensures that a replacement structure reflects the important heritage of the current building. (iii) Instruct Officers to actively engage with interested groups, including the Yorkshire Air Museum and the York Civic Trust on the future of the Southern Gateway area. Reason: In order to address the health and safety risks to the public and ensure that the relevant groups are able to give their views as the plans progress. That the Executive agree to: (i) Apply for planning permission to demolish 17-21 Piccadilly and proceed with the works to demolish the building as quickly as possible, if that permission is granted. 1. (ii) Receive a report in September 2015 setting out the work undertaken to assess a future regeneration of the area so that an appropriate future use for the site can be identified, which supports the overall development proposals for the Southern Gateway project and ensures that a replacement structure reflects the important heritage of the current building. 2. (iii) Instruct Officers ... view the full minutes text for item 14.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 10 pages

Summary

1. This report updates the Executive on the condition of 17-21 Piccadilly, the former Reynards Garage, and seeks a decision on whether to demolish, or carry out emergency health and safety repairs, to the building. It also sets out recent activity to dispose of the site and forthcoming work on the strategic importance of this site to the wider Southern gateway area. Recommendations 2. That the Executive agree to apply for planning permission to demolish 17-21 Piccadilly and proceed with the works to demolish the building as quickly as possible, if that permission is granted.

3. That the Executive will receive a report in September 2015 setting out the work undertaken to assess a future regeneration of the area so that an appropriate future use for the site can be identified, which supports the overall development proposals for the Southern Gateway project and ensures that a replacement structure reflects the important heritage of the current building.

Reason: In order to address the health and safety risks to the public. Background

4. This vacant site (location plan at Annex 1) was part of a joint venture agreement between CYC and Lasalles with a view to jointly redeveloping the Castle Piccadilly area. This partnership was dissolved in September 2013 when Lasalles indicated that they were selling individual sites separately and did not intend to undertake a comprehensive redevelopment. 5. 17-21 Piccadilly was marketed for sale by CYC in October 2013. A number of bids were received for the site for a range of uses and with vastly varying capital values. These bids were assessed against agreed criteria, these being the level of capital receipt, economic impact of the development, community benefit and the deliverability of the scheme.

6. A shortlist of the 4 bids which scored the highest against the criteria was drawn up in January 2014. All the shortlisted bids proposed a hotel with other facilities. They were all subject to planning approval and so further evaluation was needed to refine the initial evaluation. As a result, further information was sought from shortlisted bidders to be evaluated, before a preferred bidder could be identified.

7. At a meeting of the Council’s Cabinet on 7th January 2014 it was resolved that the final evaluation and selection of a purchaser would be delegated to the Director of Customer and Business Support Services, in consultation with the Cabinet Member for Finance, Performance and Customer Services, subject to the provision of adequate supporting valuations.

8. Following the Cabinet decision the four shortlisted bidders were invited to present their proposals to a panel of officers. Two bidders declined to do so, and the two remaining bidders presented their proposals on 30th January 2014. 9. In February 2014 the Council were advised by English Heritage (now Historic England) that an application had been received to list the building. The sale was paused to enable determination of the listing. This application was rejected in mid June 2014 and the decision note is attached as Annex 2. Following this, further evaluation and due diligence of the two remaining bids was undertaken.

10. At the beginning of November 2014, following changes to property ownership in the area with the Lasalle assets going into receivership, the disposal was terminated whilst the plans for the wider Southern Gateway area were considered. Southern Gateway Project

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site plan 17-21 PiccadillyAppendix 1 1 pages Download
PDF
Online: Notication report from EH on application to list 17-21 PiccadillyAppendix 2 6 pages Download
PDF
Online -Structural Survey 17-21 Piccadilly: 2009Appendix 3 44 pages Download
PDF
Online -Structural Survey 17-21 Piccadilly: 2015Appendix 4 45 pages Download
PDF
Online: Surveyors view on renovation worksAppendix 5 2 pages Download
PDF
Condition of 17-21 PiccadillyReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
CS
Councillor Chris StewardChair, present
KA
Councillor Keith AspdenVice-Chair, present
NA
Councillor Nigel AyreCommittee Member, present
JB
Councillor Jenny BrooksCommittee Member, present
DC
Councillor David CarrCommittee Member, present
IG
Councillor Ian GilliesCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance
MW
Councillor Mark WartersAttendee, in attendance
IC
Councillor Ian CuthbertsonAttendee, in attendance
NB
Councillor Neil BarnesAttendee, in attendance

All 16 on the meeting page

On this subject at York

Search all
  1. Condition of 17-21 PiccadillyThis decision
  2. Proposal to offer a conditional 2 year lease extension to Spark:York for 17-21 PiccadillyAgreed
  3. Castle Piccadilly -Conditional Concession AgreementAgreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open