(i) That the contents of Mazars Audit Report be noted. (ii) That the action plan at Annex 3 of the report be endorsed. (iii) That the committee receive six monthly update reports on progress in implementing the action plan. Reason: To ensure that the committee can monitor progress in addressing the issues raised in the audit review.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to provide Members with –
Audit review of the Elderly Person’s Home Project, carried out by Mazars;
An action plan developed in response to the key findings in the report;
Recommendation that further updates are provided on progress to implement the action plan.
Background
2. In February 2015, the Chief Executive commissioned an external audit of the Council’s Elderly Person’s Home (EPH) Project following a decision to end the project following an unsuccessful procurement process. It was agreed at Health Overview and Scrutiny Committee in March 2015 that the audit report would be presented to Audit & Governance Committee before the end of the summer.
3. The EPH project was formally initiated in June 2013 when Cabinet approved plans to fund the building of care homes at Burnholme and Lowfield. Cabinet agreed to enter into a single procurement process for both sites to secure an external provider to design, build, operate and maintain the Burnholme Care Home and Lowfield Community village for Older People. Estimated project costs of up to £500,000 were approved towards the procurement process. 4. The Cabinet paper considered in June 2013 was explicit about the risks involved with this project. At Para 27, the paper said,
‘Only once the council has been through a full procurement will the actual costs be known and then allow for proper consideration as to affordability from the existing budget’.
At Para 29
‘In order to stay within the existing revenue budget, and be able to finance the capital costs, it is estimated that the tender price will need to be towards the lower end of the estimated £25m-£30m. The procurement process will seek to develop a solution that can be met from the council’s existing budget provision. It is not expected that the project will deliver further savings, with the likely need to use the entire budget to fund the capital/revenue operating costs of the new service.’
Para 31
‘Until the full procurement has been completed, there clearly remains a risk that the project may not be able to be delivered within the existing budgetary provision’.
Para 32
‘There is the risk that, if the care home developments do not happen for any reason (eg a failed procurement exercise), the project costs would need to be written off’.
Para 54
‘The proposals outlined in this report have significant, long term financial implications for the council and there is clearly an inherent risk attached to any project of this size and nature. The financial estimates have been verified as far as possible however, there is a risk that the tenders could come back at a higher cost than estimated, resulting in an ongoing budget pressure for the council. There is also a risk that the existing sites may not realise the anticipated level of capital receipts included in the financial model and this will need to be carefully monitored’. 5. Although the proposals were ambitious, given the significant interest from organisations wanting to develop and run the homes it was reasonable for the council to believe that the market thought that the plans were realistic and achievable. Various procurement routes were considered by the project and it was agreed (following legal and procurement advice) that the most appropriate method was the Competitive Dialogue route. This approach provided the council with greater flexibility to work with bidders through the dialogue process to refine the requirements in line with budgetary constraints.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.