Key Corporate Risks Monitor 1

Noted Finance 4 papers

Audit and Governance Committee noted this item on Wednesday 29 July 2015. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

(i) That the refreshed key corporate risks, detailed in Annex A of the report, be noted. (ii) That the draft policy, strategy and associated guidance document be approved. Reason: To provide assurance that the authority is effectively understanding and managing its key risks.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Audit and Governance Committee, 5 pages

Summary

1. The purpose of this paper is to present to Audit & Governance Committee (A&G) an update on the key corporate risks for City of York Council (CYC), and the present refreshed Key Corporate Risk (KCR) Register 2015.

2. Risk management at CYC identifies the key risks for the authority and how they are being managed. This process may demonstrate that risks are being managed very well but need ongoing monitoring, others need action taken to manage the risk effectively. The role of this Committee is to assess whether the full risk environment is being adequately reviewed, key risks are identified and receive assurances that risks are being mitigated through targeted monitoring and/or action.

Background

3. The risk management process at CYC ensures that all key and emerging risks are reported regularly to A&G on at least a quarterly basis. The purpose of this paper is to provide assurance that the council identifies understands, effectively manages and reviews its key risks.

4. A key element in the work to revitalise risk management throughout the authority was to get risk back onto the corporate agenda.

5. This work has been very successful and we now see risk routinely featuring on Directorate Management Team agendas on a quarterly basis. These sessions are used to update both the departmental and any key corporate risk (KCR) responsibility which has been allocated to the Director. It is also an opportunity to consider any risks which might be on the horizon and facilitate dialogue around risk in general.

Key Corporate Risk (KCR) update

6. By their very nature, the KCRs remain reasonably static with any real movement in further actions that are undertaken which strengthen the control of the risk. The current and updated KCRs can be found at Annex A with key changes outlined below:

Safeguarding

7. This KCR relates to both childrens and adults safeguarding and arises out of the council’s statutory duties.

8. With regard to the childrens safeguarding risk, the cause of the risk has been updated to reflect the radicalisation of young people. Whilst it is not suggested that this is a particular risk specific to York, there is an issue nationally and as such it is sensible for it to be on the risk radar locally.

9. This issue is also dealt with as part of the Prevent programme which is part of the Government’s counter terrorism strategy. It places responsibilities on local agencies to identify individuals who are at risk or who have already succumbed to radicalisation.

10. Significant work has been undertaken in relation to the management of risk around safeguarding of adults. This position is evidenced by the Assistant Director, Adults Safeguarding who asked that the following be appended to the risk:

“Veritau Audit completed May 2015 reported that considerable amounts of work have been put into ensuring that Safeguarding Adults processes in York are robust and fit for purpose. Arrangements for managing risk were good with few weaknesses identified. An effective control environment is in operation.” Local Plan

11. This will be a statement of the planning strategy and vision for the City of York which sets out the opportunities and development management policies on what will or will not be permitted and where, including new homes and businesses.

12. Given the delays in the agreement and adoption of a Plan the risk has been amended to include further detail around the consequences of not having a plan as these have become clearer, they are:

inability to maximise planning gain from investment; adverse impact on investment in the City; unplanned development do not meet the authority’s aspiration for the City; ongoing costs of the preparation of the Local Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 12 pages Download
PDF
(i)Appendix B 15 pages Download
PDF
Appendix BAppendix B 8 pages Download
PDF
Key Corporate Risks Monitor 1Report 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
NB
Councillor Neil BarnesChair, present
PD
Councillor Peter DewVice-Chair, apologies
CC
Councillor Chris CullwickCommittee Member, present
SF
Councillor Stephen FentonCommittee Member, apologies
JG
Councillor Julie GunnellCommittee Member, present
LK
Councillor Lars KrammCommittee Member, apologies
SL
Councillor Sam LisleCommittee Member, present
AM
Andrew MendusCommittee Member, present
CB
Chris BatemanCommittee Member, apologies
DC
Councillor Denise CraghillSubstitute, present as substitute
IC
Councillor Ian CuthbertsonSubstitute, present as substitute
MN
Michelle NaylorOfficer, expected

All 13 on the meeting page

On this subject at York

Search all
  1. Key Corporate Risks Monitor 1This decision
  2. Key Corporate Risk Monitor 1 (18:03)Noted
  3. Key Corporate Risks monitor 4 (17:51)Noted
  4. Key Corporate Risks monitor 3 (18:54)Noted
  5. Key Corporate Risks monitor 2 (17:54)Noted
  6. Key Corporate Risks monitor 1 (17:45)Decided

More from York Audit and Governance Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... Decided Open
21 Oct 2026 Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... Approved Open
21 Oct 2026 Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... Noted Open
21 Oct 2026 Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... Noted Open
21 Oct 2026 Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies