York's Southern Gateway

Agreed Executive 2 papers

Executive agreed this item on Thursday 29 October 2015. Below is the council's own wording, with the papers it was decided on.

Item68

Resolved

That the Executive agree to: (i) Progress to the development stage of the Southern Gateway project and to appoint a Project Manager using grant funding from One Public Estate to take this work forward. (ii) Commence a procurement exercise to identify a joint venture partner to redevelop 17-21 Piccadilly. (iii) Create a conceptual framework for development of the Southern Gateway area and prepare for a public consultation. (iv) Develop a business case for development of the Southern Gateway which will involve undertaking feasibility work to assess the technical, planning and financial deliverability of development of the Southern Gateway. A report will be brought back to Executive to agree a future approach. (v) A budget of £185,000 to be financed from New Homes Bonus, with specific allocations from the budget to be confirmed by the Chief Executive and the Leader of the Council, to enable development of a fully worked up business case for the development of the Southern Gateway area. (vi) Undertake transport modelling and review parking and access arrangements for the Southern Gateway area. (vii) Explore potential delivery mechanisms and commence discussions with land owners in the area. Reason: To deliver early improvement to Piccadilly, to generate capital receipt, and to develop robust plans for the future regeneration of the Southern Gateway area. That the Executive agree to: (i) Progress to the development stage of the Southern Gateway project and to appoint a Project Manager using grant funding from One Public Estate to take this work forward. (ii) Commence a procurement exercise to identify a joint venture partner to redevelop 17-21 Piccadilly (iii) Create a conceptual framework for development of the Southern Gateway area and prepare for a public consultation. (iv) Develop a business case for development of the Southern Gateway which will involve undertaking feasibility work to assess the technical, planning and financial deliverability of development of the Southern Gateway. A report will be brought back to Executive to agree a future approach. (v) A budget of £185,000 to be financed from New Homes Bonus, with specific allocations from the budget to be confirmed by the Chief Executive and the Leader of the Council, to enable development of a fully worked up business case for the development of the Southern Gateway area. (vi) Undertake transport modelling and review parking and access arrangements for the Southern Gateway area. (vii) Explore potential delivery mechanisms and commence discussions with land owners in the area. 1. Reason: To deliver early improvement to Piccadilly, to generate capital receipt, and to develop ... view the full minutes text for item 68.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 14 pages

Recommendations

3. Executive is asked to consider and agree: i. To progress to the development stage of the Southern Gateway project and to appoint a Project Manager using grant funding from One Public Estate to take this work forward. ii. To commence a procurement exercise to identify a joint venture partner to redevelop 17-21 Piccadilly iii. To create a conceptual framework for development of the Southern Gateway area and prepare for a public consultation.

iv. To develop a business case for development of the Southern Gateway which will involve undertaking feasibility work to assess the technical, planning and financial deliverability of development of the Southern Gateway. A report will be brought back to Executive to agree a future approach.

v. To a budget of £185,000 to be financed from New Homes Bonus, with specific allocations from the budget to be confirmed by the Chief Executive and the Leader of the Council, to enable development of a fully worked up business case for the development of the Southern Gateway area. vi. To undertake transport modelling and review parking and access arrangements for the Southern Gateway area.

vii. To explore potential delivery mechanisms and commence discussions with land owners in the area. Reason: - To deliver early improvement to Piccadilly, to generate capital receipt, and to develop robust plans for the future regeneration of the Southern Gateway area.

Background

4. The Southern Gateway area covers the length of Piccadilly, the Coppergate Shopping Centre and the Eye of York and runs through to St George‟s Field and the Foss Basin. Much of the area is of low quality with significant dereliction and underdevelopment and yet the area has great potential in both its location and its historic built assets. The area sits largely within the city walls and within the Historic Core Conservation Area, at the confluence of two rivers, the Ouse and the Foss.

5. The area contains a substantial amount of public estate with three Museums/attractions (Castle Museum, Fairfax House and the Jorvik Viking Centre), three court buildings, many listed structures and a historic monument of international significance (Clifford‟s Tower). A map showing public ownership and setting out the extent of the Southern Gateway area is attached at Annex 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
York's Southern GatewayReport 14 pages DownloadRead as text

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies