Capital Strategy 2016/17 to 2020/21

Agreed Executive 4 papers

Executive agreed this item on Thursday 11 February 2016. Below is the council's own wording, with the papers it was decided on.

Item121

Resolved

Recommended: That Council: · Agree to the revised capital programme of £180.206m that reflects a net overall increase of £28.451m (as set out in paragraph 54 table 10 and in Annex B). Key elements of this include o Extension of prudential borrowing funded Rolling Programme schemes totalling £4.921m as set out in table 3 and summarised in table 10; o New schemes totalling £2.415m including an increase in prudential borrowing of £643k as set out in tables 4 & 5 and summarised in table 10; o Extension of externally funded Rolling Programme schemes totalling £9.878m as set out in table 6 and summarised in table 10; o An increase in Housing Revenue Account funded schemes totalling £12.009m funded from a combination HRA balances/Right to Buy receipts of £12.009m as set out in table 7 and summarised in table 10 · Approve the full restated programme as summarised in Annex A totalling £180.206m cover financial years 2016/17 to 2020/21 as set out in table 11 and Annex A · Approve the appropriation of the Housing Revenue Account shops into the General Fund as set out at paragraph 5 in the report. Reason: To set a balanced capital programme as required by the Local Government Act 2003
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 24 pages

Summary

1. This report set out the Capital Strategy for 2016/17 to 2020/21, and in particular sets out new capital schemes.

Recommendations

2. The Executive is requested to recommend that Council:  Agree to the revised capital programme of £180.206m that reflects a net overall increase of £28.451m (as set out in paragraph 54 table 10 and in Annex B). Key elements of this include o Extension of prudential borrowing funded Rolling Programme schemes totalling £4.921m as set out in table 3 and summarised in table 10; o New schemes totalling £2.415m including an increase in prudential borrowing of £643k as set out in tables 4 & 5 and summarised in table 10; o Extension of externally funded Rolling Programme schemes totalling £9.878m as set out in table 6 and summarised in table 10; o An increase in HRA funded schemes totalling £12.009m funded from a combination HRA balances/Right to Buy receipts of £12.009m as set out in table 7 and summarised in table 10

 Approve the full restated programme as summarised in Annex A totalling £180.206m cover financial years 2016/17 to 2020/21 as set out in table 11 and Annex A  Members are also asked to approve the appropriation of the Housing Revenue Account shops into the General Fund as set out at paragraph 50

Reason: To set a balanced capital programme as required by the Local Government Act 2003

Background

3. The current 2015/16 –2019/20 capital programme was approved by Council on 26 February 2015. Since then a number of amendments have taken place as reported to the Executive up to and including the 2015/16 Capital Monitor 3 report also on this agenda. The changes made as a result of the above reports have resulted in a current approved capital programme for 2015/16 – 2019/20 of £203.293m, financed by £110.168m of external funding and Council controlled resources of £93.125m. Table 1 illustrates the current approved capital programme profile from 2015/16 – 2019/20 as of capital monitor 3 2015/16.

2015/16 2016/17 2017/18 2018/19 2019/20 Total

£m £m £m £m £m £m Gross Capital 51.538 73.935 33.552 22.717 21.551 203.293 Programme Funded by: External Funding 27.227 29.694 24.344 15.373 13.530 110.168

Council Controlled 24.311 44.241 9.208 7.344 8.021 93.125 Resources Total 51.538 73.935 33.552 22.717 21.551 203.293 Funding

Table 1 – Capital Programme Funding and Receipts Position Funding Position of approved 2015/16 – 2019/20 programme

4. The current economic environment continues to place pressure on the funding of the programme over the 5 year cycle based on current projections. The capital programme continues to place reliance on the achievement of a small number of high value asset disposals which have been affected by the economic downturn, although overall the level of receipts does support the expenditure.

Options

5. This report sets out the new capital investment requests for the 5 year period covering 2016/17 to 2020/21. Members can consider the requests to make additions and amendments to the existing capital programme and choose to approve or reject the proposals contained within the report. Members can choose to approve or reject the recommendations made to Council as a result of the amendments contained in this report. It should be noted that it is a statutory requirement for the Council to set a capital budget for the forthcoming year (2016/17) per Local Government Act 2003 (revised).

Summary of Proposed Capital Investment

6. The Capital Resource Allocation (CRAM) process invited bids from the departments asking to submit requests for the Councils main capital priorities. Of the 32 requests going forward 18 are asking for direct Council funding, this is comprised of 14 requests for extensions to existing rolling programme schemes and 6 requests for new schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Growth Summary 1617Appendix B 1 pages Download
PDF
Capital Strategy 2016/17 to 2020/21Report 24 pages DownloadRead as text
PDF
GlossaryReport 2 pages Download
PDF
v3 Annex A: Capital Programme 1617: 20-21Appendix 4 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. Capital Strategy 2016/17 to 2020/21This decision
  2. Capital Financing and Investment StrategyApproved
  3. Capital & Investment Strategy (17:41)Approved
  4. Capital & Investment Strategy (17:26)Approved
  5. Capital Financing & Investment Strategy (18:45)Approved
  6. Capital Financing and Investment StrategyApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies