Definitive Map Modification Order (DMMO) application to add a footpath to the Definitive Map and Statement: Hoisty Field, Fulford.
AgreedExecutive5 papers
Decision Session - Executive Member for Transport - Expired agreed this item on Thursday 14 July 2016. Below is the council's own wording, with the papers it was decided on.
That Option A- that the authority does not make an Order- be agreed. Reason:The supporting evidence of use does not meet the application criteria. That approval be given to Option A, not to authorise the Assistant Director of Governance and ICT to make a Definitive Map Modification to add a footpath to the Definitive Map and Statement. Reason: The supporting evidence of use does not meet the application criteria.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 9 pages
Summary
1. A definitive map modification order application has been received, supported by 19 evidence of user forms (UEFs). The claimed route is located at Hoisty Field, Fulford (Annex 1: Location Plan). The Planning Inspectorate produces guidance to assist in the interpretation of the Wildlife & Countryside Act 1981 (Annex 2: WCA 81 Definitive Map Orders: Consistency Guidelines). Evidence of user that supports a definitive map modification order application must have been by „the public‟, representative of the people as a whole or the community in general.
2. In this case, the user evidence supplied in support of the application by a very limited number of local people is insufficient to be regarded as use by the public. The report therefore recommends that the Authority declines to make an Order on the basis that the application criteria has not been met. Recommendations 2. The Executive Member is asked to consider:
1) Option A - The Authority does not make an Order. This option is recommended.
Reason: The supporting evidence of use does not meet the application criteria.
2) Option B – The Authority makes an Order. This option is not recommended. Reason: The making of an Order lies outside the application criteria for a definitive map modification order that is supported by evidence of user.
Background
A DMMO application was received in January 2012 under the provisions of section 53 of the Wildlife and Countryside Act 1981. The claimed route commences at its junction with Public Footpath No.8 Fulford Parish, and proceeds in a generally northerly direction to exit onto Landing Lane (Annex 1: Location Plan). The application relies upon 19 UEFs (Annex 3) to support the claim that a public right of way subsists or is reasonably alleged to subsist.
This user evidence must be considered against the requirements of section 31 of the Highways Act 1980 (as set out in the Legal Implications below). There will be no presumption of dedication unless the claimed route has been actually enjoyed by the public as of right continually for the requisite period, on the balance of probabilities. The burden of proving this falls to the applicant. In determining the application, matters relating to suitability and condition of a route and possible need or nuisance are irrelevant and cannot be taken into account.
Prior to the receipt of the DMMO application, the land over which the claimed public footpath crosses, had been sold, and the new landowner has since carried out fencing works to secure the boundary. It appears that this has brought the status of the route into question for the purposes of section 31 of the Highways Act 1980.
In the case of non-determination of a DMMO application by the surveying authority, the applicant can apply to the Secretary of State for a direction requiring the local authority to determine a claim if it has not done so within 12 months of the date of receipt of the application. In this instance, the Secretary of State has directed the authority to determine the DMMO Order. If, there had been no direction from the Secretary of State, the DMMO Order would have progressed in date order with other applications which have been received but not yet determined, in accordance with the authority‟s Statement of Priorities. Consultation
4. Pre-order consultation has taken place with the prescribed bodies and utility companies: no additional information has been forthcoming. Further contact with users who support the application has taken place with the request to clarify some details stated within their use of evidence forms.
A signed copy of a statement from the landowner‟s representative has been received from solicitors on behalf of the landowner and is attached at Annex 7.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.