That Executive agree Option 1, as detailed in the report, to bring forward the development of 8 new bungalows on the Newbury Avenue site. Reason: To ensure that further account of residents concerns are considered and a development scheme brought forward which meets the council’s and the communities needs. That Executive agree Option 1, as detailed in the report, to bring forward the development of 8 new bungalows on the Newbury Avenue site. 1. Reason: To ensure that further account of residents concerns are considered and a development scheme brought forward which meets the council’s and the communities needs.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. This report provides an update on the additional consultation carried out at the Executive’s request following concerns raised by a small number of residents regarding the approved planning application to build 9 apartments at Newbury Avenue.
Recommendations
2. Executive are asked to:
a) Approve Option 1 to bring forward development of 8 new bungalows.
Reason: To ensure that further account of residents concerns are considered and a development scheme brought forward which meets the council’s and the communities needs.
Background
3. On the 7th May 2013, Cabinet considered a report which set out proposals to deliver a first phase of new council homes and sought approval for the council to pursue development of a number of sites within the Housing Revenue Account that would deliver between 50-70 homes. A table of sites was included which set out the proposal to redevelop Newbury Avenue (garage court) for an indicative 9 apartments.
4. Following the local elections in May 2015, a change of administration took place and at the Executive meeting on the 25th June 2015, Members considered a report which sought approval to include new council housing as part of the ongoing project to demolish and replace Ordnance Lane homeless hostel.
5. The Executive Member presented the report and also drew attention to the status of the current building programme approved in May 2013. In particular he highlighted concerns raised with him by local ward councillors in relation to the proposed new council house building on the Newbury Avenue site in Acomb. Therefore, in order to allay their concerns, Executive requested a re-examination of the proposals for the site and further consultation.
Consultation
6. Following Executives request further consultation was carried out. Local residents and Ward Members were invited to a consultation event held at York & District Indoor Bowls Club, 206 invitations were sent to residents living in the vicinity of the site. Ward member (Cllr Waller) and the housing portfolio holder (Cllr Carr) attended. Drawings of the site layout and property types were available to view.
7. Seventeen people attended the event and eight left feedback on the night with three more submitting feedback by post. A petition with 24 signatures was submitted, eight signatories were from people who also submitted comments sheets. The petition was signed as being from residents who believe ‘the proposed development is too large and all the extra traffic will seriously affect parking in the area, and our right to light will also be affected’.
8. A number of residents felt the area is over developed already particularly with the recent addition of the housing development on Our Lady’s site. Other concerns raised include:
Loss of view over Hob Moor Concerns about contamination Loss of light An out of date geotechnical survey
9. A number of people acknowledged there was a need for additional affordable housing but thought an alternative location should be found. Two respondents suggested building bungalows on the site
10. Following the public consultation a meeting was arranged to feedback to Cllr Carr (Executive Member – Housing & Safer Neighbourhoods) and Cllr Waller (Ward Councillor). Key concerns from the consultation were the level of traffic, parking and the height of the development given that it was 2.5 storeys high. It was resolved at the meeting that the site was appropriate for development, but alternative schemes should be drawn up limiting the height of any development to a maximum of 2 storeys. Alternative Options
11. Given that expenditure had been incurred on the original design, officers met with the architect to agree the scope of any revised sketch schemes that would consider:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.