Resolved
That the report be noted. Reason: To enable the committee to consider the Executive approval for the vision and delivery of the Castle Gateway regeneration project.
Economic Development and Transport Policy and Scrutiny Committee noted this item on Wednesday 8 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. Reason: To enable the committee to consider the Executive approval for the vision and delivery of the Castle Gateway regeneration project.
3. The council is one of the principal land owners in the Castle Gateway, which encompasses the area around Piccadilly, Coppergate Centre, the Eye of York, Clifford’s Tower, St George’s Field and the Foss Basin and many parts of the area are underused, semi derelict or of poor quality. 4. As the principal landowner, the council is instrumental in delivering a joined-up regeneration of the area which will maximise social and economic benefits for the city. Following a report to Executive in October 2015 officers were asked to initiate negotiations with adjoining land owners to develop a vision for the area and explore practical arrangements to deliver regeneration.
5. On the 26th January 2017 a major report on the Castle Gateway was taken to the council’s Executive. This wide-ranging report principally considered:
The vision for the regeneration of the area. The Local Plan draft Area of Opportunity Policy to support that vision.
A proposed stakeholder group of principal custodians to advise on the master plan and designs for the public areas and spaces.
A potential commercial partnership to deliver the redevelopment of council land and property assets and surrounding development sites.
The strategy and resources needed to deliver the above
6. The report made 12 recommendations to achieve the above, all of which were approved by the Executive. Members did also ask that the project was taken forward on a cross party basis as the delivery is likely to extend beyond the next election. The recommendations are set out in paragraph 6 of the Executive report (Appendix 1). Annexes 1 to 8 provide the supporting documents that formed the annexes to the Executive report.
Consultation 7. The Executive have approved the recommendations in the report. The recommendations were developed in consultation with relevant officers, neighbouring landowners and key stakeholders. This report has been discussed with ward councillors from Guildhall and Fishergate Wards, and presentations were delivered to those ward committees on the emerging vision. 8. A comprehensive public consultation will help to shape and develop proposals that emerge from the vision. It is proposed that this should be developed through a community forum approach as employed on the York Central project.
Options 9. Members of the Economic Development and Transport Policy Scrutiny Committee are asked to consider and comment on the report taken to January Executive, and identify any area of ongoing scrutiny.
Analysis
10. Detailed analysis of the Castle Gateway project is contained in the Executive report (Appendix 1). EDAT have asked to consider this project and report as it is a major regeneration project which with impacts on economic development and transport in the city. Council Plan
11. Under the council plan objectives the project will assist in the creation of a Prosperous City for All, and vision to be a Council that listens to residents, particularly by ensuring that :
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Scope of Castle Gateway and sub areasAppendix 1 | 1 pages | Download |
PDF |
Land ownership and Development OpportunitiesAppendix 2 | 1 pages | Download |
PDF |
Castle Gateway Draft Area of Opportunity PolicyAppendix 3 | 4 pages | Download |
PDF |
York Museums Trust statement of aspirationAppendix 4 | 4 pages | Download |
PDF |
York Castle Gateway Exec reportAppendix 1 | 23 pages | Download |
PDF |
Castle Gateway ProjectReport | 7 pages | DownloadRead as text |
Follow Economic Development and Transport Policy and Scrutiny Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 May 2017 | MinutesThat the minutes of the meeting of 8 March 2017 be approved as a correct record and then signed by the Chair, subject... | Approved | Open |
| 10 May 2017 | Report of York Civic Trust - Proposed Transport PolicyThat the report be noted. Reason: To update Members on the findings from York Civic Trust workshops focusing on a fut... | Noted | Open |
| 10 May 2017 | Annual Report from Make it YorkThat Members note the report. Reason: To ensure that Members are aware of the progress of Make it York. | Noted | Open |
| 10 May 2017 | Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ... | Noted | Open |
| 10 May 2017 | Economic Strategy UpdateThat Members note the report. Reason: To enable the delivery of the Economic Strategy, and priority actions and outco... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.