Executive, Thursday 16 June 2022 at 5.30pm

Castle Gateway Update (6:08 pm)

Noted Executive 2 papers

Executive noted this item on Thursday 16 June 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

(i) That the inclusion of the new public realm at Castle and Eye of York in the council’s round two Levelling Up Fund bid be noted. Reason: To be aware that additional funding is being sought to deliver the Castle Gateway regeneration. (ii) That, subject to planning permission being secured, officers be instructed to prepare tender documents to procure a contractor for Castle and Eye of York so that the procurement is ready to proceed should the Levelling Up Fund bid be successful. Reason: To ensure the ability to deliver the Castle and Eye of York project within the Levelling Up Fund timeframes. (iii) That the termination of the NEC3 PSSC with Wates to produce a RIBA Stage 4 design and construction price for Castle Mills be noted. Reason: To be aware that the council has not been able to reach a satisfactory outcome on identified challenges, and is in the process of terminating the NEC3 PSSC. (iv) That authority be delegated to the Corporate Director of Place, in consultation with the Director of Governance, to take such steps as are necessary to procure a construction contractor to complete the detail design/costing and subsequent construction of the proposed apartments, pedestrian/cycle bridge and riverside park at Castle Mills, and to bring a further report to Executive on the Castle Mills business case before proceeding into the construction contract based upon tendered price. Reason: To enable the delivery of the Castle Mills project and the Castle Gateway regeneration on a 2 phase re-procurement basis to secure firm prices before commencing construction. (v) That authority be delegated to the Corporate Director of Place to submit details to secure the necessary statutory consent under s106 of the Highways Act 1980 from the Secretary of State for the new bridge over the Foss navigation and to enter in to a build over agreement with Yorkshire Water in respect of the sewer running across the Castle Mills development. Reason: To secure the necessary approvals to allow Castle Mills to proceed. (vi) That the decision on whether to build a multi-storey car park (MSVP) at St George’s Field be deferred until Executive has a construction price for Castle Mills. Reason: Deferring until the inter-related point in time when a construction price is agreed for Castle Mills will allow further evidence to be collected to inform a decision on whether the MSCP still represents the best alternative replacement parking solution for the closure of Castle Car Park. (vii) That officers be instructed to collect more data on parking demand, further engage with city centre businesses and stakeholders, and explore alternative options to maximise surface car parking provision at St George’s Field to inform the future decision on car parking replacement. Reason: To provide further information and enable consultation with city centre businesses and scrutiny to inform consideration of replacement parking solutions to allow the closure of Castle Car Park. (i) That the inclusion of the new public realm at Castle and Eye of York in the council’s round two Levelling Up Fund bid be noted. Reason: To be aware that additional funding is being sought to deliver the Castle Gateway regeneration. (ii) That, subject to planning permission being secured, officers be instructed to prepare tender documents to procure a contractor for Castle and Eye of York so that the procurement is ready to proceed should the Levelling Up Fund bid be successful. Reason: To ensure the ability to deliver the Castle and Eye of York project within the Levelling Up Fund timeframes. (iii) That the termination of the NEC3 PSSC with Wates to produce a RIBA Stage 4 design and construction price for Castle Mills be noted. Reason: To be aware that the council has not been able to reach a satisfactory outcome on identified challenges, and is in the process of terminating the NEC3 PSSC. (iv) That authority be delegated to the Corporate Director of Place, in consultation with the Director of Governance, to take such steps as are necessary to procure a construction contractor to complete the detail design/costing and subsequent construction of the proposed apartments, pedestrian/cycle bridge and riverside park at Castle Mills, and to bring a further report to Executive on the Castle Mills business case before proceeding into the construction contract based upon tendered price. Reason: To enable the delivery of the Castle Mills project and the Castle Gateway regeneration on a 2 phase re-procurement basis to secure firm prices before commencing construction. (v) That authority be ... view the full minutes text for item 6.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 21 pages

Summary

1. This report provides a comprehensive update on the regeneration of the Castle Gateway and sets out the next delivery stages. The heart of the masterplan is the new Castle and Eye of York public realm and events space that will replace Castle Car Park. The designs for this world-class public space have been shared extensively and refined in response to public and stakeholder engagement and will be considered by planning committee in July. The project will, subject to Member approval, form part of the Council’s Levelling Up Fund round two bid, which will be submitted on the 6th July 2022, with successful bids announced in the autumn. The recent completion of the English Heritage restoration of Clifford’s Tower and new plaza area has provided an exciting glimpse of how the Castle and Eye of York will be transformed once the full ambition of the regeneration has been realised.

2. The Castle Mills site, which will create a new riverside park, pedestrian/cycle bridge, and new apartments that help to fund the wider masterplan’s public benefits, has been subject to delays during the detailed design and costing process. The Council entered into a NEC3 Professional Services Short Form Contract (“NEC3 PSSC”) with Wates Construction Limited (“Wates”) to develop the RIBA Stage 3 design into a RIBA Stage 4 design, accompanied by a costed proposal for construction. COVID-19, Brexit and rising inflation have created significant cost pressures and supply chain uncertainty, which have made sub-contractor pricing of construction packages challenging. The design evolution process identified further challenges, which were not resolved to the Council’s satisfaction, and as a result this has led to the Council terminating the NEC3 PSSC, and will now need to procure a new contractor. This delay will mean that the detailed design, construction tender price, and subsequent Executive decision to proceed with construction will not be ready until summer 2023, although sufficient progress has been made on the new bridge to enable progress with the associated statutory processes in the meantime.

3. Castle Mills is the primary funding stream for other elements of the masterplan and this delay means that no decision on the optimum replacement car parking options that allow Castle Car Park to close is required until summer 2023. Deferring this decision provides the opportunity to collect more car parking data, engage further with city centre stakeholders, and assess all other options to identify a suitable replacement parking solution for the closure of Castle Car Park. This will ensure the Council adopts the best delivery strategy for the Castle Gateway masterplan.

Recommendations

4. The Executive is asked to:

1) Note the inclusion of the new public realm at Castle and Eye of York in the Council’s round two Levelling Up Fund bid.

Reason: To seek additional funding to deliver the Castle Gateway regeneration.

2) Instruct officers, subject to planning permission being secured, to prepare tender documents to procure a contractor for Castle and Eye of York so that the procurement is ready to proceed should the Levelling Up Fund bid be successful.

Reason: To ensure the Castle and Eye of York project is able to deliver within the Levelling Up Fund timeframes.

3) Note the termination of the NEC3 PSSC with Wates to produce a RIBA Stage 4 design and construction price for Castle Mills.

Reason: Note that the Council have not been able to reach a satisfactory outcome on identified challenges, and are in the process of terminating the NEC3 PSSC.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Castle Gateway Update (6:08 pm)Report 21 pages DownloadRead as text
PDF
View item 6. as HTML 119 KBReport 119 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Castle Gateway Update (6:08 pm)This decision
  2. Major Projects - Castle Gateway Update (6.38 pm)Noted
  3. Called-in Item: Castle Gateway Update Report and Next Steps - Executive Meeting 16 November 2023 (5:49 pm)Agreed
  4. Castle Gateway Update (18:28)Approved
  5. Castle Gateway Update (5.48 pm)Noted
  6. Castle Gateway UpdateNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies