That Members: a) Note the key corporate risks provided at Annex A b) Note the project information provided at Annex B Reason: To provide assurance that the authority is effectively understanding and managing its key risk and is kept updated on major programme and project activities.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to present Audit & Governance Committee (A&G) with an update on the key corporate risks (KCRs) and an update on major projects for City of York Council (CYC).
Background
2. The role of A&G in relation to risk management covers three major areas; Assurance over the governance of risk, including leadership, integration of risk management into wider governance arrangements and the top level ownership and accountability for risk Keeping up to date with the risk profile and effectiveness of risk management actions; and Monitoring the effectiveness of risk management arrangements and supporting the development and embedding of good practice in risk management
3. Risks are usually identified in three ways at the Council;
A risk identification workshop to initiate and/or develop and refresh a risk register. A fundamental review takes place every 3 years with our insurance and risk partners. The risks are continually reviewed through quarterly directorate management teams (DMT) sessions. Risks are raised or escalated on an ad-hoc basis by any employee Risks are identified at quarterly DMT meetings
4. Due to the diversity of services provided, the risks faced by the authority are many and varied. The Council is unable to manage all risks at a corporate level and so the main focus is on the significant risks to the council’s objectives, known as the key corporate risks (KCRs).
5. The corporate risk register is held on a system called Magique. The non KCR risks are specific to the directorates and consist of both strategic and operational risk. Operational risks are those which affect day to day operations and underpin the directorate risk register. All operational risk owners are required to inform the risk officer of any updates on at least a quarterly basis.
6. In addition to the current KCRs, in line with the policy, risks identified by any of the Directorates can be escalated to Council Management Team (CMT) for consideration as to whether they should be included as a KCR. KCRs are reported bi-annually to CMT.
7. The risk management officer meets attends DMTs bi-annually to update directorate risks and KCRs and has one to one sessions with Directors.
8. The Verto system is used for the management of major projects (defined as large or medium sized) and is populated from the directorate project registers. This is reviewed on a two monthly basis at CMT, in addition to any individual reports relating to specific projects. The directorate project lists are being considered on at least a monthly basis by DMTs. The directorate process is facilitated by the directorate assurance lead.
9. The programme assurance group meets on a monthly basis where the corporate programme is considered. The group includes the directorate assurance leads and every other meeting is attended by support leads (which includes HR, legal, finance, audit, property and business support).
10. The project support group meets every month to ensure that project managers have a support mechanism and can discuss improvements to process, project management best practices and share experience. 11. The risk management section within Verto is consistent with the criteria recorded in Magique. The risk management officer has access to all projects in Verto for the purpose of risk oversight.
Key Corporate Risk (KCR) update
12. There are currently 11 KCRs which are included at Annex A in further detail, alongside progress to addressing the risks. A new risk KCR11 is included in this monitor.
13. In summary the key risks to the Council are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.