Decision Session - Executive Member for Environment and Climate Emergency noted this item on Monday 3 July 2017. Below is the council's own wording, with the papers it was decided on.
That the following be noted and agreed: a) the governance arrangements in place, in addition to the key H&S risks together with the council’s response to managing and responding to those risks; b) the progress made in establishing and commencing the H&S shared service; c) the focus of current and future work and that a follow-up report summarising any H&S activity following the tragic fire at Grenfell Tower be considered at a future Decision Session under this portfolio. Reason: To ensure the Executive Member and residents are assured that H&S services are resilient and the council has proper arrangements in place for managing and responding to H&S risks. That the following be noted and agreed: a) the governance arrangements in place, in addition to the key H&S risks together with the council’s response to managing and responding to those risks; b) the progress made in establishing and commencing the H&S shared service; c) the focus of current and future work and that a follow-up report summarising any H&S activity following the tragic fire at Grenfell Tower be considered at a future Decision Session under this portfolio. Reason: To ensure the Executive Member and residents are assured that H&S services are resilient and the council has proper arrangements in place for managing and responding to H&S risks.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Environment and Climate Emergency, 7 pages
Recommendations
2) The Executive Member is asked to:
a) note the governance arrangements in place, in addition to the key H&S risks together with the council’s response to managing and responding to those risks; b) note the progress made in establishing and commencing the H&S shared service; and c) note the focus of current and future work and agree that a follow-up report summarising any H&S activity following the tragic fire at Grenfell Tower is considered at a future Decision Session under this portfolio.
Reason: To ensure the Executive Member and residents are assured that H&S services are resilient and the council has proper arrangements in place for managing and responding to H&S risks.
Background and Summary Conclusions
3) The H&S governance arrangements are the main driver for the council’s improvements in health and safety management, and continue to come from the commitment of the Chief Executive, supported by the Council Management Team (CMT) and Heads of Service. Integral to this is the work undertaken by colleagues across the council to ensure services are delivered in a safe and healthy manner. 4) This is further improved by elected member oversight of the management of health and safety undertaken by the Portfolio Holder for the Environment, and the Audit and Governance Committee who have requested reports in the past year in order to effectively scrutinise the activities of the council in relation to health and safety. 5) The council continues to have an on-going emphasis on a sensible, risk- based approach which minimises the risks to staff but is also mindful that council services also need to be delivered in a cost effective way. The attitude of all staff and those with management responsibilities in adopting this approach is to be commended particularly considering the current challenging financial climate. It should be noted that it has been proven that effective health and safety management can have financial benefits due to reduced sickness absence and lost time. It can also minimise damage to equipment. 6) This report covers the council’s financial reporting period 1st April 2016 to 31st March 2017.
Main Activities 2016/17
7) The council’s Health & Safety Policy is what drives our commitment to health and safety and is reviewed, in accordance with best business practice, at least annually. The latest version was adopted in August 2016 following the appointment of the new Chief Executive. The policy is implemented through the work of CMT, individual directors and the Health and Safety Champions for each Department. The Joint Health and Safety Committee (JHSC) which consists of health and safety champions for each department with Trade Union colleagues drive forward the health and safety agenda.
8) In addition to the work of council employees and partners there is independent scrutiny of health and safety activity and performance. Each year an activity in relation to health and safety is audited independently by Veritau and these audits are considered by the Audit and Governance (A&G) Committee. A report was provided to the A&G Committee during the financial year and a follow up is planned for July 2017 demonstrating a clear commitment to continually improve with clear progress in implementing all recommendations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Environment and Climate Emergency at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.