York 5 Year Plan Flood Scheme Update

Noted Executive 3 papers

Decision Session - Executive Member for Environment and Climate Emergency noted this item on Monday 3 July 2017. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the update report and the evidence presented by the Environment Agency in the session be noted. Reason: The Executive Member is updated on the progress of the flood risk management works programmes in York and is able advise to ensure wider links and opportunities are considered and built into the process. That the update report and the ... view the full minutes text for item 7.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Environment and Climate Emergency, 5 pages

Summary

1. The flooding in late December 2015 followed an intense period of rainfall across November and December due to the impacts of Storms Desmond and Eva. Record river levels were observed in many river catchments across the north of England. More than 4000 homes and 2000 businesses flooded across Yorkshire with 453 properties and 174 businesses flooded in York.

2. Funding has been allocated to the Environment Agency (EA) following the floods to renew existing and provide new flood defences across the city, £17m has been allocated to the Foss Barrier improvements and £45m to the wider flood defences across the city.

3. Defra approvals are being agreed for the high level business case and a procurement process has been ran in parallel to appoint consultants to develop the detailed business case and consequent detailed design of packages of works.

4. A range of questions have been received from CYC scrutiny sessions a formal response has been made to these by the Environment Agency in Annex 1 and 2.

5. Joint meetings with the Environment Agency have been held to develop the recommendations from the York Flood Inquiry, an update will be brought to the September Executive Member for the Environment Decision Session. Recommendations

6. The Executive Member for the Environment is asked to note the update report and the evidence presented by the Environment Agency in the session, feedback is sought from the Executive Member on all content.

Reason: The Executive Member is updated on the progress of the flood risk management works programmes in York and is able advise to ensure wider links and opportunities are considered and built into the process.

Background

7. Following the development and publication of the York Five Year Plan (https://www.gov.uk/government/publications/york-5-year-flood-plan) the EA have developed the Defra Strategic Outline Business Case, approvals are expected shortly for investigation and design works to commence for all schemes on the programme.

8. The EA have undertaken a procurement process to appoint a consultant to develop the full business case and the preferred bidder will be appointed after the approval of the Strategic Outline Business Case.

9. Site Investigations along the rivers Ouse and Foss will begin in the summer and last for around 3 months, these will provide detailed information on ground and site conditions and any constraints and inform the detailed design work. The EA will engage and inform residents and businesses once the programme is confirmed and this will be agreed with CYC. The works will not cause significant disturbance, but in a small number of situations there will be a need to access private land, early engagement with landowners will be carried out to minimise concerns.

10. A drop in centre is being developed on North Street at the former Bike Hub site, this will provide a place where all partners working on the schemes can co-locate and work together and we can invite residents and businesses in to discuss the schemes in more detail. It is likely that this will open in the summer.

11. The governance of the York 5 Year Flood Plan calls for formal updates to the Executive Member for the Environment Decision Session in addition to presentations at City of York Scrutiny Committee’s, the project team last attended the Communities and Environment Policy and Scrutiny Committee on the 15th March 2017. A range of questions were raised by councillors, a formal response has been made to these in Annex 1 and 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2 pages Download
PDF
Appendix 2Appendix 2 2 pages Download
PDF
York 5 Year Plan Flood Scheme UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. York 5 Year Plan Flood Scheme UpdateThis decision
  2. York Learning Strategic Plan Performance (5:44pm)Decided
  3. Tackling Poverty Today and Turning the Tide to Create Lasting Change: A Strategy and Strategic Action Plan for addressing Poverty in York 2025-2035Approved
  4. York Learning 2024-2025 Strategic Plan Performance (7:18pm)Approved
  5. Hemplands Kids Club, Burnholme Youth Centre, Bad Bargain Lane, York, YO31 0LW [25/01168/GRG3] (5.15 pm)Approved
  6. Adoption of the City of York Local Plan (9:21 pm)Approved

More from York Decision Session - Executive Member for Environment and Climate Emergency

All decisions
MeetingDecisionOutcome
20 May 2025 MinutesThat the minutes of the Decision Session held on 29 April 2025 be approved and signed by the Executive Member as a co... Approved Open
20 May 2025 North Yorkshire & York, Local Nature Recovery Strategy (LNRS) consultation draftThat the Executive Member: i. Noted the work that had been undertaken in relation to the North Yorkshire and York Loc... Noted Open
29 Apr 2025 Minutes (10:01am)That the minutes of the Decision Session held on 18 March 2025 be approved and signed by the Executive Member as a co... Approved Open
29 Apr 2025 Public Realm - Service Developments (10:14am)That the Executive Member: i. Considered the two petitions received by the Council and considered if the actions alre... Noted Open