(a) That the progress made in delivering the 2017/18 internal audit work programme and current counter fraud activity be noted. (b) That the Head of Internal Audit ( Veritau Ltd) considers member’s suggestions to the layout of the report to enhance the usability for members. Reason: To enable Members to consider the implications of audit and fraud findings.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 This report provides an update on progress made in delivering the internal audit workplan for 2017/18 and on current counter fraud activity.
Background
2 The work of internal audit is governed by the Accounts and Audit Regulations 2015 and the Public Sector Internal Audit Standards (PSIAS). In accordance with the standards, periodic reports detailing the outcomes of internal audit work are presented to this committee.
Internal Audit
3 To date (up to 6th September 2017), internal audit has completed 27% of the 2017/18 audit plan based on reports issued. The figures do not reflect audits in progress or recently completed1. It is anticipated that the 93% target for the year will be exceeded by the end of April 2018 (the cut off point for 2017/18 audits). The current status of audits included in the audit plan is shown in annex 5.
4 Details of the audits completed and reports issued since the last report to this committee in June 2017 are given in annex 1.
1 The figure including work in progress and work completed but not yet reported is 64%. 5 A number of variations to the audit plan have been approved by the Director of Customer and Corporate Services since the last report to this committee in June 2017. Details of these variations are included in annex 2.
Counter Fraud
6 Counter fraud work has been undertaken in accordance with the approved plan. Annex 3 provides a summary of the work undertaken in the period.
7 Up to 31st July, the fraud team had achieved £123k in savings for the council as a result of investigation work (against a target for the year of £100k). Successful outcomes were recorded for 50% of the investigations undertaken (where cases have resulted in some form of action against the perpetrator, recovery of funds or other action by management). The team also identified £19k in notional savings principally derived from housing fraud investigations.
Breaches of Financial Regulations
8 There has been one breach of the council’s financial regulations identified during the course of recent audit work. Details of this breach is summarised in annex 4.
Consultation
9 Not relevant for the purpose of the report.
Options
10 Not relevant for the purpose of the report.
Analysis
11 Not relevant for the purpose of the report.
Council Plan
12 The work of internal audit and counter fraud helps to support overall aims and priorities by promoting probity, integrity and accountability and by helping to make the council a more effective organisation. Implications
13 There are no implications to this report in relation to:
Finance Human Resources (HR) Equalities Legal Crime and Disorder Information Technology (IT) Property Risk Management Assessment
14 The council will be non-compliant with the PSIAS if the results of audit work are not reported to the committee and could therefore be exposed to increased levels of scrutiny and challenge.
Recommendation
15 Members are asked to:
(a) Note the progress made in delivering the 2017/18 internal audit work programme, and current counter fraud activity.
Reason
To enable members to consider the implications of audit and fraud findings. Contact Details Author: Chief Officer Responsible for the report: Max Thomas Ian Floyd Head of Internal Audit Deputy Chief Executive / Director of Veritau Limited Customer & Corporate Services 01904 552940 Telephone: 01904 551100
Report Date 11/09/17 Approved
Specialist Implications Officers
Not applicable
Wards Affected: Not applicable All
For further information please contact the author of the report
Background papers
2017/18 Internal Audit and Counter Fraud Plan
Annexes
Annex 1 – 2017/18 Audits Completed and Reports Issued Annex 2 - Variations to the 2017/18 Audit Plan Annex 3 - Counter Fraud Activity Annex 4 - Breaches of Financial Regulations Annex 5 - Current Status of Planned Audits
Available on the council’s website
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.