( i ) That approval be given to proceed with the procurement, as set out in the report. (ii) That authority be delegated to the Assistant Director of Housing and Community Safety to approve the award of the contract once the tender process is complete. Reason: In line with the council’s internal governance rules and the requirements of the Public Contract Regulations, and to facilitate a quicker route into the critical mobilisation phase of the project. ( i ) That approval be given to proceed with the procurement, as set out in the report. (ii) That authority be delegated to the Assistant Director of Housing and Community Safety to approve the award of the contract once the tender process is complete. Reason: In line with the council’s internal governance rules and the requirements of the Public Contract Regulations, and to facilitate a quicker route into the critical mobilisation phase of the project.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. To seek approval to proceed with the re-procurement of the Managed Stores service for Building Services and Highway departments.
2. The following report is submitted in line with City of York Council’s (CYC) finance and governance requirements regarding the procurement of services with a value in excess of £500k.
Recommendations
3. Executive is asked to approve the request to proceed with the procurement as set out in this report.
4. Delegated authority to be given to the Assistant Director for Housing and Community Safety to approve the award of contract once tender process is complete.
Reason
5. The above award approval process is in line with CYC’s internal governance rules and our Public Contract Regulations obligations (PCRs). It also facilitates a quicker route into the critical mobilisation phase of the project. Background
6. Following a review of the Council’s existing materials store and supply service, and the future supply requirements for Building Services and Highways departments, it is proposed that CYC re- procure an on-site Managed Stores solution, to commence upon the existing contract’s expiry in September 2018.
7. Given its value and importance to effective service delivery, a project board made up of senior managers, and officers, from Procurement, Building Services, Highways and Legal, and the University of York has been established to oversee the procurement of this service contract.
8. The existing service is delivered via a framework agreement supplied by Crown Commercial Services (CCS), which has now expired. CYC entered into the framework agreement jointly with the University of York (UoY) in 2013. The respective annual throughput for each organisation is currently £2.1m for CYC (this includes £1.6m of reactive repairs spend, and an additional £500k of capital maintenance, facilities management, highways and street lighting spend), and £800k for UoY.
9. The existing supplier leases warehouse storage and office premises from us at Hazel Court, through which we derive an income of £65k pa. The lease runs concurrently with the supply contract, terminating in September 2018. We would seek to replicate this arrangement in any re-procured contract.
Procurement compliance
10. As the estimated contract value of the re-procured contract exceeds the relevant EU Threshold set out in the Public Contracts Regulations 2015 (PCRs), CYC is required to procure the contract in accordance with the PCRs. Current procurement rules mean that the term of a framework agreement shall not exceed 4 years, unless exceptional circumstances apply. The subject matter of this procurement is unlikely to fall within exceptional circumstances. Therefore, if the re-procurement were to be via a framework agreement (there are a number of managed stores framework agreements in existence, e.g. YPO, Cirrus, Fusion) it would be restricted to a maximum duration of four years. However service managers are keen to secure a longer term contract in order to access further value for money and service quality; deriving these improvements by providing greater certainty for any supplier, plus a higher value throughput. In addition framework agreements do not provide suppliers with exclusivity; therefore CYC and UoY would be unlikely to benefit from further economies of scale if we were to continue to operate through this type of contract.
11. In order to secure a contract that is compliant with the PCRs and with a longer term than 4 years we will need to procure the goods and services through a contract based on our own terms and conditions. Our Procurement team have provided the Project Board with the necessary assurance that they possess both the necessary experience and capacity to undertake a ‘bespoke’ procurement of this nature.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.