Economy and Place Policy Development Committee decided this item on Wednesday 21 March 2018. Below is the council's own wording, with the papers it was decided on.
That; i. The principles within the Executive report at Annex A be amended to include a reference to the Third Sector (Voluntary Sector) in paragraph 10biv. ii. The strategic objectives within the Executive report at Annex A (paragraph 9) be bullet points rather than numbered to remove any suggestion of an order of priority. iii. An additional principle be added as identified at the committee workshop, around the protection of the Council’s heritage buildings. iv. The implementation plan be brought back to the committee at a future meeting. Reason: To assist in the establishment of an appropriate for the Council.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Economy and Place Policy Development Committee, 4 pages
Background
2. In September 2017 the Assistant Director for Regeneration and Asset Management presented a report to the Executive which set out a refreshed and updated Asset Management Strategy for the Council, covering the period 2017-2022 (see Annex A).
3. The new Strategy aimed to update the current Asset Management Plan 2011-2016 to make it relevant for the next five years and set out a new context, delivery models and methodologies for engaging customers and communities, all of which had evolved since 2011. To this end three objectives and a set of principles had been developed that would drive future planning, (see Annex A, paragraphs 9 & 10).
4. The Executive report detailed the proposed approach to each separate ‘block’ of the council’s large and varied property estate (see paragraphs 12-35).
5. In respect of operational and community assets the report identified the need for a significant programme of work to develop a Community & Operational Asset Strategy, and the Executive agreed to provide additional funding of £165k from contingency for a project manager, and building condition surveys. 6. At the time of the Executive report, commercial assets were on track to achieve their income target, and work is now ongoing to identify further opportunities to create income, whilst enabling the improvement and regeneration of areas of the city.
7. Work was also ongoing to develop assets for housing delivery, in line with the approach agreed by the Executive in March 2017 to use surplus public sector land assets to increase the volume and accelerate the pace of housing delivery in York. In support of this, a later report presented to the Executive in November 2017, detailed proposals for the development of some affordable houses for rent on two council owned sites, and for the disposal of some other council owned land to generate a capital receipt.
Consultation
8. The Executive agreed that the Asset Management Strategy should be referred to this Committee in order to provide cross-party input into the:
i. Establishment of some clear principles to guide and shape future use of the Council’s assets and; ii. Development of comprehensive asset plans for all Council property assets
9. The Executive requested that a further report be brought back in early 2018.
Analysis
10. Strategic Principles In early November 2017, an informal meeting of this committee was held to consider a presentation on the strategic Management of the council’s commercial portfolio and the development of the council’s Asset Management Strategy – see copy of presentation at Annex B.
11. In regard to the proposed principles within the refreshed Strategy aimed at driving future asset planning, those Members who attended the November meeting identified the need for an additional principle around the protection of the Council’s heritage buildings. 12. Council Property Asset Plans The Executive Report at Annex A details the planned process for developing each of the three blocks of the council’s large and varied property estate which includes:
• The creation of three area based community assets plans - see paragraphs 19 & 20 of Annex A.
• The proposed way forward for the Council’s commercial assets - see paragraphs 28 & 29 of Annex A.
• The progression of ongoing works to develop opportunities for housing development across the city – see paragraphs 32-35 of Annex A.
Options
13. At this meeting, Members may choose to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Economy and Place Policy Development Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.