CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive, Tuesday 3 March 2026 at 4.30pm

Update on the Asset Management Strategy - 2026 to 2031

Agreed Executive 8 papers

AI summaryCity of York Council Executive agrees new five-year Asset Management Strategy, approving sale of 25/27 Coney Street, lease extension at Spark:York, and peppercorn community asset transfers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFive-year property strategy approved with disposals and community leases
Moneyc. £6.9m annual incomeCommercial property estate valued c. £396m, generating c. £6.9m yearly
What happens nextDirector of Finance to actAuthority delegated to Director of Finance to complete all transactions
Who it affectsCommunity groups and tenantsAllotments, parks, sports clubs, and community organisations across York

What was decided

The Executive agreed the principles of a new five-year Corporate Asset Strategy for 2026 to 2031, covering the commercial portfolio, operational estate, and community assets. Report P38

The Executive approved the sale of 25/27 Coney Street to the Helmsley Group with a 999-year leaseback of a refurbished ground floor retail unit, alongside a lease renewal for Spark:York at 17-21 Piccadilly. Report P71, P76

The Executive approved nine new community asset leases at peppercorn rent, covering allotments, Rowntree Park facilities, Strensall open space, and Hull Road Park, and delegated authority to the Director of Finance to complete all transactions and future disposals. Report P108, P114, P129, P135

Why

To maintain the existing principles of the Asset Management Strategy to guide future use of the council's property portfolio. Report P39

To support the economic vibrancy of the city and protect or increase income from the commercial property portfolio. Report P39

To dispose of surplus property, reduce the council's financial obligations, and encourage regeneration and community involvement through use of its assets. Report P39

What happens next

The Director of Finance, in consultation with the Director of Governance, is authorised to complete the agreed transactions and to acquire or dispose of all future interests in land. Report P38

Disposals involving Rowntree Park, York Road Strensall, and Hull Road Park will be advertised under section 123 of the Local Government Act 1972, with any objections reported to the relevant Executive Member. Report P172, P184

A full business case for up to 28MW of ground-mounted solar at Harewood Whin is scheduled for 2027, and rooftop solar will be installed at Yearsley Swimming Pool, Joseph Rowntree School, and Acomb Explore Library. Report P150, P165, P166

The money

  • c.£6.9m Annual rent roll from c.1,100 commercial legal agreements Report P46
  • c. £396m Total value of c.1,300 property assets including schools Report P41
  • c.6.6% Return on the commercial property portfolio Report P52
  • £675k Total One Public Estate funding attracted since 2014 Report P25
  • £2.64m Funding from OPE brownfield land release fund for Ordnance Lane and former Tang Hall library Report P27
  • £2 million Near-annual income now generated at West Offices, against c. £2.6m running costs Report P82
  • approximately. £3.9 million Capital budget for acquisition of head leasehold of Eco Centre, Amy Johnson Way Report P56
  • c. £500k Receipt from disposal of shareholder interest in York Science Park Ltd Report P60

Options considered

  • Chosen: Sell 25/27 Coney Street outright to Helmsley Group and lease back a refurbished unit for 999 years at nil rent. Independent valuation confirms market value, securing a capital receipt, retained long-term interest, and delivery of a riverside path Report P71, P72, P73
  • Rejected: Pursue affordable housing on 17-21 Piccadilly via registered providers. Only one expression of interest received; rising build costs and small site size deterred bidders Report P75
  • Chosen: Renew the Spark:York lease at 17-21 Piccadilly tied to planning consent. Spark is a popular, near-fully occupied facility; an alternative site at York Central will not be ready before the current lease ends Report P75, P76
  • Chosen: Grant a 35-year peppercorn lease to York Allotment Charitable Incorporated Organisation for 16 allotment sites. YACIO has successfully managed the sites for seven years with stable governance and a small surplus Report P102, P108
  • Rejected: Bring allotment management back in-house if YACIO lease is not renewed. Would require appointing an allotment officer and administrative support, and rents previously did not cover council costs Report P109
  • Chosen: Terminate Bustardthorpe Allotment Association's existing lease and grant a new 35-year peppercorn lease. Brings BAA in line with other community asset transfers; BAA is the only allotment group paying rent Report P114

Implications

  • Financial: The Coney Street sale will generate a capital receipt to reduce borrowing against future capital programme spend, supporting the revenue budget. Report P177
  • Financial: Peppercorn community leases limit financial risk to the council while continuing service to local residents without ongoing cost. Report P179
  • Legal: Disposals of land at Rowntree Park, York Road Strensall, and Hull Road Park require advertisement under section 123 of the Local Government Act 1972, as the loss of open space is involved. Report P172, P184
  • Equalities: The strategy supports using the estate to overcome deprivation and create more affordable housing on council-owned land. Report P16, P17
  • Climate: The estate contributes to the council's net zero by 2030 ambition, with gas emissions down 26% since 2019 and 2,102 tCO2e reduced through renewable electricity purchasing. Report P138, P143, P152
  • Risk: Each community asset transfer is assessed for the group's sustainability, governance, and capacity to manage the asset, with maintenance and repair obligations transferred under the lease. Report P89, P92, P96

Who and where

  • Helmsley Group as purchaser of 25/27 Coney Street Report P71
  • Holland and Barrett as current tenant at 25/27 Coney Street Report P68
  • Spark:York and 26 of its previous occupiers at 17-21 Piccadilly Report P75
  • York Allotment Charitable Incorporated Organisation (YACIO) and its 1,500 tenants across 16 allotment sites Report P102
  • Bustardthorpe Allotments Association CIO and its tenants Report P113
  • Friends of Rowntree Park and York Canoe Club using park facilities Report P74, P121
  • Strensall and Towthorpe Parish Council as new leaseholder of land at York Road Report P129
  • Choose 2 Youth social enterprise operating a café in Hull Road Park Report P132, P135

Timeline

  • January 2020: Council purchased 25/27 Coney Street after Executive approval in November 2019 Report P68
  • October 2025: Spark:York granted a five-year planning extension under reference 25/01151/FULM Report P76
  • 2026: Helmsley Group hopes to start development of the Coney Street scheme later in 2026 Report P70
  • November 2025: Executive agreed a £750k park fund, with s106 money taking the Parks Investment Programme to around £925k Report P136
  • January 2026: Paper taken to Place Scrutiny meeting on 26 January 2026 Report P174
  • 3 March 2026: Executive meeting at which this Asset Management Strategy was agreed Report P1
  • 2027: Full business case for up to 28MW of solar at Harewood Whin scheduled for consideration Report P150

Plain English for the jargon

  • Asset Management Strategy: The council's five-year framework setting principles and objectives for managing its land and property portfolio.
  • Peppercorn rent: A nominal rent, typically set at nil or a token amount, often used for community asset transfers.
  • One Public Estate (OPE): A national programme the council has been part of since 2014, supporting cross-public-sector property projects to generate capital receipts, reduce running costs, and enable integrated services.
  • Community Asset Transfer: The lease or sale of a council-owned asset to a community group, transferring maintenance and operating responsibility.
  • Heat Decarbonisation Plan (HDP): A site-level plan setting out how a building can reduce or eliminate fossil fuel use to reach net zero.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item212

Resolved

Resolved (unanimously): That Executive a) Notes: i) The performance of the council’s property estate and the annual revenue it provides. ii) The performance against the specific workflows, including disposals, as previously set out in the previous Strategy and the re-shaping of the operational estate at West Offices to provide additional annual revenue. iii) The performance and role the estate has played in helping to reduce the council’s carbon footprint. b) Agrees the principles of the Strategy which will form the Corporate Asset Strategy for the next 5 years, 2026-2031. c) Agrees to: i) The sale of 25/27 Coney Street and lease back of part on a 999-year lease. ii) The grant of a lease renewal at 17-21 Piccadilly. iii) Lease the various City Council owned allotments, as detailed within the report to York Allotment Charitable Incorporated Organisation (YACIO) for 35 years at a peppercorn rental. iv) Lease Bustardthorpe Allotments, Bishopthorpe Road, to Bustardthorpe Allotment Association for 35 years at a peppercorn rental. v) Lease the store and outdoor space in Rowntree Park maintenance depot to York Canoe Club for 15 years at a peppercorn rental. vi) Lease the garage in Rowntree Park to the Friends of Rowntree Park for 15 years at a peppercorn rental. vii) Lease of the Rowntree Park Lodge Garden to the Friends of Rowntree Park for 99 years at a peppercorn rental subject to the Friends meeting the requirement of original lease for the upper floors. viii) Lease the land at York Road, Strensall to Strensall and Towthorpe Parish Council for 70 years at a peppercorn rental. ix) Lease the land in Hull Road Park to Choose 2 Youth for 10 years at a peppercorn rental, all on the terms and conditions outlined in the report. d) Delegates to the Director of Finance (in consultation with the Director of Governance) authority: i) To take such steps as are necessary to agree and complete the above transactions as detailed in this report; and ii) To acquire and dispose of all interests in land for all future acquisitions and disposals. Reasons a) To ensure work continues to accord with the clear principles as set out under the Asset Management Strategy, which will continue to guide and shape future use of the council’s property portfolio. b) To continue to support the ongoing economic vibrancy of the city, to protect and increase the income from the council’s commercial property portfolio. c) To dispose of surplus property with an emphasis on providing affordable accommodation within the city; reduce the council’s financial obligations and encourage regeneration and community involvement through the use of its assets.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Meeting: Executive Meeting date: 3 March 2026

Report of: Debbie Mitchell, Director of Finance

Portfolio of: Councillor Lomas, Executive Member for Finance, Performance, Major Projects, Human Rights, Equality and Inclusion

Decision Report: Update on the Asset Management Strategy – 2026 to 2031 Subject of Report 1. This report sets out progress against the delivery of the Asset Management Strategy for the council for the period 2020-2025, as reported to Executive in November 2020. The report provides an update on the performance of the council’s commercial portfolio of property, which provides a vital source of income in financing Council services. The report provides updates on work flows and sets out the Strategy for a further 5- year period to 2031, to benefit both social outcomes and financial performance, arising from the council’s land and property assets.

2. The report sets out; a. The key principles of the Asset Management Strategy b. An update on those work flows as identified previously by the Asset Management Strategy split into; (I) Commercial Portfolio (Paras 22 to 40) (II) Operational Estate (Paras 41 to 48) (III) Community Assets (Paras 49 to 90) c. A number of property led proposals deliver strategic and financial benefits to the council, as set out within the main body of this report.

Benefits and Challenges 3. This report illustrates the benefits of the council’s property portfolio both in terms of its revenue generation and its ability to aid the facilitation of regeneration.

4. The report provides an update on previously reported decisions, including disposals, bringing in the benefit of financial receipts to the council.

5. The report outlines a number of proposed property transactions whereby assets will be transferred to the community enhancing community involvement in the running of those facilities.

Policy Basis for Decision 6. The management of General Fund assets was set out by the previous Asset Management Strategy covered by the current Asset Management Plan 2020- 2025 and reported to Executive in November 2020. The principles of the Strategy were maintained in 2020 from the previous Strategy, with the addition to incorporate the impacts of the council’s commitment to net carbon neutrality by 2030. The current Strategy sets out three objectives and a set of principles to drive future asset planning. The Objectives are;

1. To use our assets to deliver policy goals; 2. To operate our estate efficiently and dynamically to support the effective delivery of council services; 3. To use council assets to generate maximum income in order to support the delivery of council priorities.

7. These objectives are broken down into more detailed principles which guide our activity planning and decision making, the principles are:

a. We will use our assets to maximise positive outcomes for our communities; b. In order to protect direct services, we should reduce the overall cost of the estate through:

I. rationalisation of assets II. disposal of poor-quality assets III. exploiting commercial opportunities IV. co-location of Council and other public sector services (including Health, care, police, education);

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 15: Update on the Asset Management Strategy (2026 to 2031): Appendix AAppendix 317 KB Download
PDF
Item 15: Update on the Asset Management Strategy (2026 to 2031): Appendix BAppendix 365 KB Download
PDF
Item 15: Update on the Asset Management Strategy (2026 to 2031): Appendix CAppendix 168 KB Download
PDF
Item 15: Update on the Asset Management Strategy (2026 to 2031): Appendix DAppendix 185 KB Download
PDF
Item 15: Update on the Asset Management Strategy (2026 to 2031): Appendix EAppendix 313 KB Download
PDF
Update on the Asset Management Strategy: 2026 to 2031Report 1 MB DownloadRead as text
PDF
View as HTML (212./4) 13 KBAppendix 13 KB Copy on its way
PDF
View item 212. as HTML 246 KBReport 246 KB Copy on its way

At this meeting

Whole meeting

Who was there

8 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneVice-Chair, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbCommittee Member, present

On this subject at York

Search all
  1. Update on the Asset Management Strategy - 2026 to 2031This decision
  2. 2023-2028 Housing Asset Management and Energy Efficiency Retrofit PlanApproved
  3. Housing Asset Management - Planned Investment at Glen Lodge and Bell Farm (7:31 pm)Approved
  4. Highways Infrastructure Asset Management PlanApproved
  5. Called-in Item: Update on the Asset Management Strategy 2017-2022Approved
  6. Update on the Asset Management Strategy 2017-2022Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies