Internal Audit & Counter Fraud Plans 2018/19

Approved Finance 3 papers

Audit and Governance Committee approved this item on Wednesday 11 April 2018. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

That the 2018/19 internal audit plan be approved and the proposed counter fraud plan be noted. Reason: In accordance with the Committee’s responsibility for overseeing the work of internal audit and the counter fraud service.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Audit and Governance Committee, 5 pages

Background

2. The council’s internal audit service has to comply with the Public Sector Internal Audit Standards, and the council’s own Internal Audit Charter. The standards and charter require that the Head of Internal Audit gives an annual opinion on the adequacy and effectiveness of the council’s framework of governance, risk management, and control. The basis for the opinion is the programme of work that internal audit carries out. An indicative risk based audit plan is drawn up at the start of each year, setting out what work will be done. The plan is required to be approved by this committee as part of its responsibility for overseeing the work of internal audit.

3. In addition to internal audit, Veritau also provides the council with specialist counter fraud services. In previous years, counter fraud work has been included as part of the internal audit plan. However, to reflect the independent nature of the counter fraud and internal audit services, and for the purposes of transparency, counter fraud work is being reported in a separate plan for the first time for 2018/19. 2018/19 Internal Audit Plan

4. Annex 1 sets out proposed internal audit work for 2018/19. The planned audit work is based on a risk assessment undertaken by Veritau. The plan is also informed by discussions with chief officers and members, risk management arrangements, and by plans for development and change within the council.

5. Total planned days for 2018/19 are 1,210 which is a reduction of 60 days from 2017/18.

6. The 2018/19 plan is similar in focus to previous years. It recognises the continuing change taking place within the council. Veritau will continue to provide support, advice and challenge in relation to major projects in addition to overall plans to meet current needs (eg to achieve savings targets). Whilst the plan reflects the continued need to look at key corporate systems, and to undertake regularity work in areas such as the main financial systems, it also recognises the increasing expenditure and focus in areas such as Adult Social Care.

7. Other audits considered for the 2018/19 plan include the following.  Overtime  Risk Management  Members Allowances  Health & Safety  Regional Adoption Agency  Community Safety Plan  Public Health - Delivery of Outcomes  Better Care Fund  Right to Buy  Housing Environment Improvement Programme  Ethics

8. These were not included in the plan in order to balance planned work with available resources. Ultimately these areas were considered a lower priority for internal audit for 2018/19. For example because, they were deemed to be a lower risk, were subject to other scrutiny (eg by external audit), or because of timing issues (eg they were likely to be undertaken later in the year and could be considered in 2019/20). 2018/19 Counter Fraud Plan

9. Annex 2 sets out proposed areas of counter fraud work for 2018/19. No estimate of time is made for each area as this will depend on levels of suspected fraud reported to the team. Reactive investigations (determined by allegations of fraud received) accounts for the largest proportion of work. Priorities for work in the remaining areas will be determined in accordance with the council’s Counter Fraud Strategy and Counter Fraud Risk Assessment (presented to the committee in February).

10. Total planned days for 2018/19 are 1,060, which is a reduction of 63 days from the previous financial year.

Consultation 11. In preparing the audit and counter fraud plans consultation has taken place with the Audit and Governance Committee and key officers across the council.

Options 12. Not relevant for the purpose of the report.

Analysis

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Plan 2018-19Appendix 1 14 pages Download
PDF
City of York Council Counter Fraud Plan 2018-19Appendix 2 4 pages Download
PDF
Internal Audit & Counter Fraud Plans 2018/19Plan 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
DM
Dave MannIndependent Person, apologies
FD
Councillor Fiona DerbyshireChair, present
SL
Councillor Sam LisleCommittee Member, present
HS
Councillor Hilary ShepherdCommittee Member, present
IC
Councillor Ian CuthbertsonCommittee Member, present
SF
Councillor Stephen FentonCommittee Member, present
LK
Councillor Lars KrammCommittee Member, present
CS
Councillor Chris StewardCommittee Member, present
AM
Andrew MendusCommittee Member, present

On this subject at York

Search all
  1. Internal Audit & Counter Fraud Plans 2018/19This decision
  2. Internal Audit Progress Report 2026/27 (19:19)Noted
  3. Internal Audit Progress Report 2026/27 (19:47)Noted
  4. Internal Audit Progress Report 2025/26 (6:40pm)Noted
  5. Internal Audit Work Programme 2026/27 (20:05)Approved
  6. Internal Audit Progress Report 2025/26 (20:23)Noted

More from York Audit and Governance Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... Decided Open
21 Oct 2026 Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... Approved Open
21 Oct 2026 Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... Noted Open
21 Oct 2026 Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... Noted Open
21 Oct 2026 Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... Approved Open