Removal of Parliament Street Fountain and Saint Sampson Square Toilets
ApprovedExecutive4 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 12 April 2018. Below is the council's own wording, with the papers it was decided on.
That Option 3 To remove the toilet block and fountain replacing the Fountain with an intermediate floral display and to establish a task and finish group to bring forward proposals for the use of the space created by the removal of the fountain. These proposals will be brought back to the Executive Member. be approved. Reason: To improve the public realm of Parliament Street and support the economic growth of the city. That Option 3 To remove the toilet block and fountain replacing the Fountain with an intermediate floral display and to establish a task and finish group to bring forward proposals for the use of the space created by the removal of the fountain. These proposals will be brought back to the Executive Member. be approved. Reason: To improve the public realm of Parliament Street and support the economic growth of the city.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 7 pages
Summary
1. York is one of the most visited places in the UK with over 7 million visitors and each year hosts a number of events and festivals. Parliament Street is a key part of the city centre; it is not just a focus for retail but hosts many of the events and festivals that make York such a vibrant thriving city. 2. However, Parliament Street has a number of items of redundant, life expired public realm infrastructure that blight the space. The fountain at the centre of Parliament Street has not worked for a number of years and the toilet block at Saint Sampson Square is no longer used.
3. The fountain is a landmark and key focal and meeting point for the city. Therefore it is appropriate to consider how to replace the fountain with more than just paving. This is a more significant decision for the city and it is proposed to establish a task and finish group including York Businesses Improvement District; Make it York and the Civic Trust to establish permanent replacement proposals.
4. This report recommends the removal of both the Fountain and the Toilet Block with a temporary feature installed at the former fountain site. The BID have commissioned design proposals for a floral display and additional seating to coincide with this years floral celebrations. The removal of the toilet block is subject to planning permission.
Recommendation 5. It is recommended:
Option 3 - To remove the toilet block and fountain replacing the Fountain with a intermediate floral display and establish a task and finish group to bring forward proposals for the use of the space created by the removal of the fountain. These proposals will be brought back to the Executive Member. This is the recommended option as it will improve the public realm of Parliament Street and encourage meaningful engagement on the future uses of the Fountain Site.
Reason: To improve the public realm of Parliament Street and support the economic growth of the city.
Background 6. The toilet block at Saint Sampson Square was has not been used since 2010, it offers no value to the public it merely houses some electrical and mechanical plant that can be removed/relocated.
7. However, below is a list of the public toilets within this city:
Coppergate Shopping Centre
Nunnery Lane
Silver Street
St Georges Fields
St Leonard’s Place
Tanner Row
Union Terrace
8. All of the above toilets offer disabled access. This in addition to the many toilet facilities contained within the businesses; restaurants and cafe’s of the city
9. This year will see the Council invest £70,000 to refurbish the public toilets in the Coppergate Centre and on Silver Street.
10. The toilet block does not complement the historic setting of Saint Sampson Square.
11. Its removal will enable the square to be better used offering increased space for the temporary cultural, recreational and retail events that happen in the city. The water and drain connections will remain to allow toilet facilities to be provided for such events if needed. 12. The building is greater than 50 cubic metres and therefore planning permission will be required for its demolition.
13. The fountain was installed back in the 1990s. Key issues about the fountain are:
The fountain has not worked for a number of years due to failure of the associated plant It is not certain whether the fountain could be restored but, if it were possible, the final capital cost would need to be established following excavations and in light of a full scheme design. It has however been estimated the cost is circa £13k. It should also be noted that fountains carry significant running / maintenance costs for which no budget currently exists. This cost has been estimated at £10k per year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.