Decision Session - Executive Member for Transport - Expired agreed this item on Thursday 15 November 2018. Below is the council's own wording, with the papers it was decided on.
That Option 1 be agreed – to approve the proposed preliminary junction layout shown in Annex B to the report. Reason: To mitigate the risk of failure of the junctions signal equipment. That Option 1 be agreed – to approve the proposed preliminary junction layout shown in Annex B to the report. Reason: To mitigate the risk of failure of the junctions signal equipment.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 8 pages
Summary
1. The traffic signalling equipment at this junction is life expired and has become difficult and costly to maintain, it needs to be replaced.
2. The signalling equipment at this junction is in very poor condition and is at risk of irreparable failure which would result in a significant period of time without signal operation.
3. The TSAR (Traffic Signal Asset Renewal) programme is addressing the issue of life expired traffic signal assets across the city. Walmgate Bar is now the highest priority for renewal.
4. Although the primary aim of TSAR is to replace life-expired assets, carrying out this work means the Authority is required to also consider bringing the junction up to current standards in terms of safety and junction geometry.
5. Due to necessary minor changes to improve compliance, a decision is required to approve the alterations.
Recommendations
6. The Executive Member is asked to approve Option 1.
Reason: To mitigate the risk of failure of the junctions signal equipment.
Background 7. A report was brought to the Executive Member for Transport and Planning on 12 November 2015 to seek approval to undertake the 5-year ‘TSAR’ (Traffic Signal Asset Renewal) programme.
8. To date, through the TSAR programme 19 sets of signals have been refurbished. These have been prioritised in order of condition and liability to failure. Availability of road space also dictated the order in which schemes were constructed. Walmgate Bar is now the clear leader in terms of priority junctions to refurbish.
9. Maintenance Engineers have informed the Authority that the junction is liable to imminent failure due to its condition. Additionally, the condition of the junction means that when it does fail it may not be possible to repair it and bring it back into operation.
Consultation
10. The scope of the works included within this proposal are relatively minor and in normal circumstances would not require an executive decision for approval, or an external consultation.
11. However, due to the sensitivity of the location a consultation has been carried out to offer key user groups an opportunity to have their say on the proposed scheme.
12. Annex A shows the distribution of the consultation and the consultation content.
13. Annex D highlights key feedback items drawn from the consultation responses
Progress since the consultation
14. The drawing that was sent out for consultation is shown in Annex C. A minor change has been made to the proposed preliminary design since consultation.
15. It is no longer proposed to make alterations to the cycle facility within the bar walls. Initially it was thought that there was an outstanding safety issue in this location that needed addressing. Further safety assessment work has determined that in fact the accident record at this location is good and no remedial work is required.
16. Due to the minor nature of this change since consultation, a further round of consultation is not seen as being of benefit. Options
17. The following options are available:
18. Option 1 – Approve the proposed preliminary junction layout shown in Annex B
19. Option 2 – Do not approve the proposed junction layout
Analysis
Option 1
Decision
20. Approving this Option will result in progressing the proposed preliminary design to the detailed design stage and on to construction, with no further Executive Member decision required.
Description of changes
21. A drawing showing the proposed changes is included in Annex B. These changes consist:
22. A full replacement of all traffic signalling technology, including signal heads, poles, cabling, cabinets, detectors, pedestrian indicators, communications and ducting.
23. Widening of all pedestrian crossings.
24. Realignment of the pedestrian crossing over Foss Islands Road.
25. Widening and lengthening of the pedestrian islands on Lawrence Street and Barbican Road.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
50Walmgate Bar Traffic Signal RefurbishmentThis decision
Hear about the next one first
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.