OS Field 5070, Hull Road, Dunnington, York [18/02659/OUT]

Approved Planning 2 papers

Planning Main approved this item on Thursday 21 February 2019. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

That the application be approved subject to the conditions and informatives listed in the report and the following conditions: Condition 1 The containers must be painted matt dark green. Condition 2 Reactive lighting must be installed. Reasons: i. The proposed energy storage facility with ancillary compound and structures is considered inappropriate development in the Green Belt by definition. Further harm has been identified as a result of the limited impact on openness and the landscape and visual character of the area. Very special circumstances relating the locational need; innovative nature of the technology proposed; and the sustainability and energy resilience benefits of the proposal have been put forward. Support has also been found in paragraph nos. 8 and 148 of the NPPF for the scheme as well as policies DP2 and CC1 of the emerging Local Plan. ii. It is considered that the very special circumstances are sufficient to clearly outweigh the harm through inappropriateness and identified further harm and the proposal is recommended for approval subject to relevant planning conditions.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Planning Main, 12 pages

COMMITTEE REPORT

Date: 21 February 2019 Ward: Osbaldwick And Derwent Team: Major and Parish: Murton Parish Council Commercial Team

Reference: 18/02659/OUT Application at: OS Field 5070 Hull Road Dunnington York For: Outline application seeking approval for the layout and appearance of an energy storage facility with up to 25 battery storage units along with ancillary structures including switchgear, transformer, standby emergency generator and 2 no. containers enclosed with steel palisade fencing and screened with landscaping By: [name removed] Type: Outline Application Target Date: 26 February 2019 Recommendation: Approve

1.0PROPOSAL

1.1The application is in outline with approval sought for appearance and layout. The proposal is for an energy storage facility of 25 battery storage units housed within steel shipping containers along with ancillary structures including an emergency generator, storage containers, auxiliary transformer and switchgear unit. Each battery storage unit will measure approximately 14m by 2.4m and 2.5m in height. The site will be fenced with a landscape buffer. It is intended that the site will be in operation for 20 to 25 years after which it will be returned to its current state.

1.2The facility would provide rapid-response electrical back-up to the National Grid by storing energy in times of over provision and releasing it at times of high usage. It would result in the creation of the equivalent of 2 full time jobs.

1.3Details of access are reserved for future consideration and therefore have not been provided but it is understood that once the facility is installed only limited maintenance visits are anticipated amounting to one or two per week.

SITE AND SURROUNDINGS

1.4The site is within the general extent of the Green Belt. There is an existing field access from the A1079 to the site which slopes down from the road. The site was most recently used as a Christmas tree plantation and now appears to be left to grass. There is a hedge along the frontage and to the West boundary. The other side of this hedge is an area of local interest for nature conservation and beyond

Application Reference Number: 18/02659/OUT Item No: 3e that a transformer station. To the East of the site a small group of properties front the highway.

2.0POLICY CONTEXT

2.1Policies:

Emerging Local Plan

DP2 Sustainable development CC1 Renewable and low carbon energy generation and storage GB1 Development in the Green Belt D1 Placemaking D2 Landscape and setting D6 Archaeology GI4 Trees and hedgerows ENV5 Sustainable drainage

The City of York Draft Local Plan Incorporating the Fourth Set of Changes April 2005 (DCLP)

GP1 Design GP9 Landscaping NE1 Trees, woodlands and hedgerows GB1 Development in the Green Belt

3.0CONSULTATIONS

INTERNAL

Design, conservation and sustainable development (Archaeology) 3.1 There have been few archaeological interventions in the vicinity of the site and the site is likely to preserve evidence for a range of undesignated heritage assets dating to the late-prehistoric and Roman periods; and the agricultural and associated uses of the site in the medieval and post-medieval periods. The proposal is likely to require top soil stripping which will have a detrimental impact on any subsurface features remaining on the site. A condition is recommended to ensure archaeological work is undertaken during site stripping.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OS Field 5070, Hull Road, Dunnington, York [18/02659/OUT]Report 12 pages DownloadRead as text
PDF
Os Field 5070, Hull Road, Dunnington Site PlanPlan 1 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. OS Field 5070, Hull Road, Dunnington, York [18/02659/OUT]This decision
  2. Proposed University Campus Lying Between Field Lane and Low Lane, A64 Trunk Road and Hull Road, York (14/00633/REMM)Approved
  3. Proposed University Campus, Lying Between Field Lane and Low Lane A64 Trunk Road And Hull Road, York. (12/03617/REMM)Approved
  4. Proposed University Campus Lying Between Field Lane and Low Lane A64 Trunk Road and Hull Road, York. (12/02306/FULM).Approved
  5. Proposed University Campus Lying Between Field Lane and Low Lane, A64 Trunk Road and Hull Road, York (10/02696/REMM)Approved
  6. Proposed University Campus Lying Between Field Lane and Low Lane, A64 Trunk Road and Hull Road, York (10/02734/REMM)Approved

More from York Planning Main

All decisions
MeetingDecisionOutcome
5 May 2022 MinutesThat subject to the addition of Cllrs Melly and Ayre to the list of apologies, the minutes of the last meeting held o... Approved Open
7 Apr 2022 Minutesi. That the minutes of the meeting held on 3 February 2022 be approved and then signed by the chair as a correct reco... Approved Open
3 Mar 2022 MinutesThat the minutes of the last meeting held on 3 February 2022 be approved at the next meeting. Approved Open
3 Mar 2022 Lindum Group Limited, York Road, Elvington, York YO41 4EP [21/01709/REMM]That the application be approved subject to the conditions listed in the report and the addition of an informative in... Approved Open
3 Feb 2022 MinutesThat, subject to the amendment stated above, the minutes of the last meeting held on 6 January 2022 be approved and s... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies