Decision Session - Executive Member for Transport - Expired approved this item on Thursday 19 September 2019. Below is the council's own wording, with the papers it was decided on.
(i) That Option 1: to implement the scheme as shown in Annex C, be approved. Reason: To help reduce vehicle speeds in an existing 20mph speed limit on Hempland Avenue. (i) That Option 1: to implement the scheme as shown in Annex C, be approved. Reason: To help reduce vehicle speeds in an existing 20mph speed limit on Hempland Avenue.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 5 pages
Summary
1. This report summarises the results of consultation with regard the speed management scheme at the junction of Hempland Avenue and Hempland Lane and asks the Executive Member to decide how to proceed with the scheme.
Recommendations
2. The Executive Member is asked to approve:
Option 1: Implement the scheme as shown in Annex C.
Reason: To help reduce vehicle speeds in an existing 20mph speed limit on Hempland Avenue.
Background
3. Hempland Avenue was referred to the Transport Projects team for investigation via the Speed Management Partnership following a review of speed data.
4. To address concerns about vehicle speeds, a scheme was developed and approved at Executive Member Decision Session in September 2018. A copy of the Report and Decision are included in Annex A. The Executive Member approved progression of the scheme, as shown in Option 3 of the report, to consultation and for any objections to be reported back to a future decision session on implementation. Consultation
5. Consultation was undertaken with residents directly affected by the proposed changes to the highway. A letter and plan shown in Annex B were distributed to 21 residents who live the vicinity of the junction. It was also issued to the emergency services and other road user groups.
6. Responses were received from three local residents, with two issues being raised with the proposed scheme:
7. Issue 1: One resident responded generally in favour of the scheme but noted concerns for cycle safety if the junction mouth is made narrower.
8. Officer response: Whilst the junction is narrower than in its current arrangement the sharper turn into the junction will force drivers to slow down and gives them less chance to try to overtake cyclists within the junction. No cycle facilities currently exist on Hempland Avenue or Hempland Lane which are affected by these proposals and none are proposed as part of this scheme.
9. Issue 2: Two residents objected to the proposals as they considered the speed of vehicles on Hempland Lane to be the main contributory factor to high speeds on Hempland Avenue. They suggested that the 20mph limit be extended or speed cameras installed to reduce speeds.
10. Officer Response: The purpose of the proposed scheme is to address a speeding concern on Hempland Avenue which is subject to a 20mph speed limit. No speed concerns on Hempland Lane have previously been raised through the 95Alive partnership for investigation and so the focus for this scheme has always been Hempland Avenue.
11. The length of Hempland Lane between Stockton Lane and Heworth Village is part of the strategic network for the city and for this reason was excluded from the signed 20mph speed limit for the area when it was rolled out in 2014 and retained a 30mph speed limit. Therefore extending the 20mph limit onto Hempland Lane would go against the 20mph Speed Limit Policy.
12. The junction of Hempland Lane and Hempland Avenue features a wide junction mouth which allows vehicles to turn into the lower speed side road without needing to slow down. The proposed tighter turn will require drivers to slow down and therefore they will be more likely to adhere to the 20mph limit. Design Changes
13. During the period following the consultation a topographical survey was undertaken to allow the detailed design of the scheme to take place. This confirmed that re-profiling of the carriageway surface at the junction would be required to ensure the cross section of the carriageway matched the new alignment of the junction. This change and associated increased estimated cost was report to Transport Board and a budget increase was agreed. A general arrangement plan showing the extents of surfacing required is provided as Annex C.
Options
14. Option 1: Implement the scheme as shown in Annex C.
15. Option 2: Do nothing.
Analysis
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.