i. It is noted that the Terms of Reference for the York Central Delivery Co-ordination Board makes a commitment at paragraph 10.19 to “Monitor, review and amend its own Terms of Reference as the project evolves”. With this in mind, can the CSMC be advised of: i.i. How does the Board propose to monitor its terms of reference? i.ii. When were the terms of reference reviewed and if so what were the outcomes and how were these communicated to CYC and partners/stakeholders? If a review has not yet taken place, when does the board propose to undertake a review? i.iii. If any changes to the Board’s terms of reference have been or are to be made, will there be a review of the terms of reference of the associated boards charged with the global delivery of York Central so as to ensure alignment of aims and commitments for example towards climate change? ii. Can the CSMC be provided with quarterly updates on the York Central project performance with the first report to include an updated issues schedule (page 59 of the agenda dated March 2019) with details of the actions taken and any resulting new risks given that the project is now almost 12 months further on. Reason: To ensure that the Committee can ... view the full minutes text for item 63.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Customer and Corporate Services Scrutiny Management Committee
Summary
1. The purpose of this report is to brief the Customer and Corporate Services Scrutiny Committee (CCSSMC) on the status of the York Central project as requested at the CCSSMC, in the context that this is the largest project in the Major Projects portfolio.
Background
2. CCSSMC considered an update report on the approach to Corporate Projects in October 2019 in order to explore the potential for scrutiny topics in this area. It was asked that a scoping report was brought back to the Committee in December 2019 in order to look at potential pieces of work.
3. The Committee suggested several areas for investigation, one of which was a look into the structure and processes around the York Central project.
4. It was acknowledged that a review of the York Central project has been to the Audit and Governance Committee in the autumn and that, along with a brief update on the project taken from the latest highlight report, the paper from the Audit and Governance briefing (see Annex A - Managing Risk in the York Central Project) would be presented for the Committee’s consideration. York Central Update
5. The progress of the project can be tracked through the monthly highlight report on the York Open Data platform. The current status of the project is as follows (the full highlight report is included in Annex A):
Current status
The Outline Planning Application was approved by Planning Committee in March 2019. The Reserved Matters Application for phase 1 off plot infrastructure is being prepared and will be submitted in February 2020. John Sisk Ltd have been appointed as infrastructure delivery partner for Phase 1 Infrastructure on PCS, looking at Value Engineering, Buildability, and risk management The WY+TF Full Business Case has been conditionally approved by WYCA. HIF decision awaited.
Future outlook
The Outline Planning Application was approved by Planning Committee in March 2019. The Reserved Matters Application for phase 1 off plot infrastructure is being prepared and will be submitted in late February/March 2020. John Sisk Ltd appointed as infrastructure delivery partner for Phase 1 Infrastructure PCS, they have reported on Value Engineering, Buildability and risk management. The output will now be reviewed and considered by Infrastructure Delivery Board and Infrastructure Co-ordination Board prior to progressing to Stage 4 Design The WY+TF Full Business Case is conditionally approved by WYCA and CYC are working through discharge of the conditions. HIF decision awaited.
Recommendations
6. The Customer and Corporate Services Management Committee is asked to review the documentation in the body of the report and explore areas for potential further work.
Reason: To ensure that the committee is confident of the structure of the Council’s largest Major project. Contact Details
Author: Chief Officer responsible for the report: Dave Atkinson Neil Ferris Head of Programmes and Corporate Director for Economy and Place Smart Place 01904 553481 Report Date 24/01/2020 √ Approved
Specialist Implications Officer(s) None
Wards Affected: All √
For further information please contact the authors of the report
Abbreviations CCSSMC – Customer and Corporate Scrutiny Management Committee
Annexes Annex A - Managing Risk in the York Central Project Annex A1 - Governance arrangements (excerpt from Nov 18 Executive report) Annex A2 - Terms of reference for the Strategic Board and the Coordination Board and the Infrastructure Delivery Board Annex A3 - York Central Risk Log Annex A4 - Verto York Central Highlight report Annex A5 - York Central Gateway Review report Annex A6 - Summary of York Central Executive decisions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customer and Corporate Services Scrutiny Management Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.