That the application be approved, subject to: i. Conditions 1-11 as set out in the report. Reason: for the avoidance of doubt and to ensure that the development is carried out only as approved by the Local Planning Authority and to ensure use of vacant land prior to its expected longer term regeneration, in the interests of vitality and viability of the city centre. [At 11:30, the meeting was adjourned to enable the registered public speakers for the next item to be brought in. It was re-convened at 12:00]
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Reference: 20/00561/FUL Application at: Spark York Piccadilly York For: Variation of condition 2 of permitted application 17/00274/FUL to extend duration of permission to 31.3.2022 By: [name removed] Type: Full Application Target Date: 1 June 2020 Recommendation: Approve
1.0PROPOSAL
APPLICATION SITE
1.1The application relates to the Spark venue, which comprises of multiple small commercial units and outside amenity space. The commercial units are occupied as a social hub, retail/A1 uses, and food and drink outlets.
1.2The scheme was granted permission originally for a temporary period only, expiring 1 July 2020.
1.3The site is Council owned and a temporary permission was sought as Spark has always been intended as a temporary “meanwhile” use of the site. The Council’s long-term intention, as part of the Castle Gateway project, is for alternative redevelopment of the site. This site sits within a later phase of the project and the Council is currently working on development proposals for the site A report is expected to be presented to Executive later in the year seeking approval for a re- development strategy for the site.
PROPOSALS
1.4The application is to vary condition 2 of the original permission, allowing Spark to remain onsite until 31.3.2022.
Page 1 of 17 1.5 The relevant condition stated as follows –
“This (approved) use (of the site) shall cease and all associated structures shall be removed from the site by 1 July 2020; unless prior to that date the consent of the Local Planning Authority has been obtained to extend the period of the permission”.
1.6Although the development is now in breach of this condition, and technically the permission is no longer valid, under the circumstances officers are content committee could still determine to approve this application. This is on the following grounds -
1.7On 22 June the government issued a press release that stated as follows – “Sites with consent that have an expiry date between the start of lockdown and the end of this year will now see their consent extended to 1 April 2021”. At the time of writing the associated legislation regarding this is not yet in force (and consequently we do not know the details of this change). It is assumed this legislation will extend the lifetime of the existing permission into next year.
1.8However should this legislation not be in force by the time of committee, the recommendation will be approval subject to the legislation coming into force to automatically extend permissions that have expired during lockdown.
1.9The application is for the consideration of Main Planning Committee at the request of the Assistant Director for Planning and Public Protection.
BACKGROUND / RELEVANT SITE HISTORY
17/00274/FUL Original permission, subject to conditions regarding opening times, with certain areas to close at 9pm.
18/01102/FUL Application to omit timber cladding to exterior, refused; appeal dismissed.
18/02268/FUL Permission to allow roof canopy on a seasonal basis, between 1 September 2018 and 1 May 2019 and 1 September 2019 and 1 May 2020.
Page 2 of 17 2.1 Section 38(6) of the Planning and Compensation Act 2004 requires that determinations be made in accordance with the development plan unless material considerations indicate otherwise.
2.2Key policies / sections of the NPPF are as follows -
The Publication Draft City of York Local Plan 2018 ('2018 DLP') was submitted for examination on 25 May 2018. Phase 1 of the hearings into the examination of the Local Plan took place in December 2019. In accordance with paragraph 48 of the NPPF the Draft Plan policies can be afforded weight according to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.