ResPark for the area around the University of York

Approved Executive 1 paper

Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 21 July 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

(i) That option 1b be approved and the residents’ parking scheme, either as an extension to the R39 Zone or as an additional zone based on the R39 Zone, be progressed directly to the Traffic Regulation Order consultation stage, with the exemption of the unadopted streets and retail areas, where officers will further consult, to enable the scheme to meet the needs of the community, the results of which will be reported back to an Executive Member for Transport Decision Session. (ii) That the scheme be progressed on the basis that the University of York would fund the implementation process, the issue of permits and operation of the enforcement hotline, up to a maximum level of funding of £42,100. (iii) That the Assistant Director of Transport, Highways and Environment and the Executive Member for Transport consult on the zone areas and notifications to be issued. Reasons: After several years of negotiation the University of York ( UoY ) has agreed, in principle, to fund the implementation (including public consultation) of extending the existing residents parking zone R39 to incorporate on-street parking survey zones 5-8 and fund the issue of permits and operation of the enforcement hotline, up to a maximum level of funding of £42,100, from this point in time onwards until 15 years after the first occupancy of the Site (i.e. until 30 September 2024 as Goodricke College was first constructed and occupied in September 2009). Failure to approve this option would result in further protracted negotiation with the UoY pertaining to the impact of UoY related parking on residential streets, the need for mitigation and the mitigation measures required, which is likely to lead to no mitigation being put in place prior to the time limiting period of 15 years after the first occupancy of the site in which to implement mitigation measures expiring. (i) That option 1b be approved and the residents’ parking scheme, either as an extension to the R39 Zone or as an additional zone based on the R39 Zone, be progressed directly to the Traffic Regulation Order consultation stage, with the exemption of the unadopted streets and retail areas, where officers will further consult, to enable the scheme to meet the needs of the community, the results of which will be reported back to an Executive Member for Transport Decision Session. (ii) That the scheme be progressed on the basis that the University of York would fund the implementation process, the issue of permits and operation of the enforcement hotline, up to a maximum level of funding of £42,100. (iii) That the Assistant Director of Transport, Highways and Environment and the Executive Member for Transport consult on the zone areas and notifications to be issued. Reasons: After several years of negotiation the UoY has agreed, in principle, to fund the implementation (including public consultation) of extending the existing residents parking zone R39 to incorporate on-street parking survey zones 5-8 and fund the issue of permits and operation of the enforcement hotline, up to a maximum level of funding of £42,100, from this point in time onwards until 15 years after the first occupancy of the Site (i.e. until 30 September 2024 as Goodricke College was first constructed and occupied in September 2009). Failure to approve this option would result in further protracted negotiation with the UoY pertaining to the impact of UoY related parking on residential streets, the need for mitigation and the mitigation measures required, which is likely to lead to no mitigation being put in place prior to the time limiting period of 15 years after the first occupancy of the site in which to implement mitigation measures expiring.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 22 pages

Summary

1. The Heslington East Campus Outline Consent Planning Conditions (Condition 10 and associated Section 106 Agreement) state what surveys will be carried out and the consequences of what is to be done if University related parking increases by more than 20% in the vicinity of the University Development. This is for a period of 15 years from the first occupation of the Development.

2. The University of York (UoY) has agreed, in principle, to  fund the implementation a residents parking zone to incorporate the on street parking survey zones 5-8, complementing the existing residents parking zone R39, to incorporate on-street parking survey zones 5-8, and  fund the administrative costs for the issue of permits and operation of the enforcement hotline.

3. The purpose of this report is to  seek approval to consult with residents regarding the expansion of the existing residents’ parking in the area around the University of York to suit the proposed strategy for extending the coverage of residents parking in the area around the University of York, for which the University of York has agreed, in principal, to fund its implementation (including consultation with residents) and administrative costs for the issue of permits and the operation of the enforcement hotline. Recommendations

4. The Executive Member is asked to

Approve Option 1a – Progress the extension of Resident Parking zone R39 to incorporate on-street parking survey zones 5-8 through the Council’s process for introducing residents parking and, subject to the results of the public consultation, bring forward further reports to the Executive Member prior to implementation. The scheme to be progressed on the basis that the UoY would fund the implementation process, the issue of permits and operation of the enforcement hotline, up to a maximum level of funding of £42,100.

Reasons: After several years of negotiation the UoY has agreed, in principle, to fund the implementation (including public consultation) of extending the existing residents parking zone R39 to incorporate on-street parking survey zones 5-8 and fund the issue of permits and operation of the enforcement hotline, up to a maximum level of funding of £42,100, from this point in time onwards until 15 years after the first occupancy of the Site (i.e. until 30 September 2024 as Goodricke College was first constructed and occupied in September 2009).

Failure to approve this option would result in further protracted negotiation with the UoY pertaining to the impact of UoY related parking on residential streets, the need for mitigation and the mitigation measures required, which is likely to lead to no mitigation being put in place prior to the time limiting period of 15 years after the first occupancy of the site in which to implement mitigation measures expiring.

Background

Planning Condition 10 and S106 Agreement

5. In summary, Condition 10 to planning application 15/02923/OUT (replicated at Appendix A) states  before commencement of development the developer will carry out a survey of current on street parking and thereafter repeat annually,  the survey is to be carried out to a specification and at a time agreed with the LPA, and  within 3 months of the survey being carried out the developer will review the results and submit the review to the LPA to demonstrate whether the volume of on-street parking has increased by more than 20% of the survey as a consequence of the development.

6. In summary, the associated S106 Agreement (replicated at Appendix A) states

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ResPark for the area around the University of YorkReport 22 pages DownloadRead as text

At this meeting

Whole meeting

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies