(i) That the content of the report and the information provided at the meeting be noted. (ii) That the issues raised at this meeting be addressed in the quarterly report to the Customer & Corporate Services Scrutiny Management Committee in January 2021. (iii) That future reports to the Audit & Governance Committee on the KCRs associated with the York Central project include the risks detailed in the IDB risk register. (iv) That, should officers become aware of any proposed change to the project involving a significant risk, the matter be considered if possible at the next available meeting of the Audit & Governance Committee before being taken to Executive. Reason: To ensure that the committee maintains an appropriate oversight of the risks associated with the York Central project.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Risk Management of the York Central Project Summary
1. The July 23rd Executive decision to release further funding to enable the commencement of early, preparatory infrastructure works for York Central was called in by Councillors Myers, K Taylor and Wells. The decision was considered by the Customer & Corporate Services Scrutiny Management Committee (Calling-in) on 13 August 2020. The committee decided that the original decisions should not be referred back to the Executive for reconsideration.
2. The committee also suggested that they would like the Audit & Governance Committee to examine in depth the Key Corporate Risks (KCRs) relating to capital projects, subsequently the Chair of Audit and Governance has requested that this report be brought forward with any issues arising to be reported to Customer & Corporate Services Scrutiny Management Committee (CCSMC).
3. This report therefore presents an overview of risk management arrangements for the council as part of the York Central Partnership (YCP) and attaches the most recent up to date versions of the risk registers used to track and manage risk. Background
4. The York Central project is possibly the most complex project ever facilitated by CYC. It is large scale, multi-faceted, strategically essential and requires the effective collaboration of 4 public sector land owners and is funded from multiple inter-related funding sources which requires CYC to exercise a significant amount of influence as the Council does not directly control the project.
5. Delivery requires effective project management of the individual strands of work, to ensure the achievement of the required outputs, but also requires a comprehensive and holistic approach to programme management to deliver the expected outcomes. The programme governance has evolved as the YCP has matured. Executive have agreed that CYC are content with all governance arrangements proposed by the partnership with the current arrangements agreed by Executive in November 2018 set out in the diagram below.
6. This is predicated on the strategic oversight being undertaken by the York Central Strategic Board, where CYC is represented by the Leader of the Council and the Chief Operating Officer.
7. Programme co-ordination between all partner activities achieved through the York Central Delivery Coordination Board (YCDCB). This board has a rotating chair and monitors the master programme, budget and benefits realisation, making sure that all contributing projects are aligned and that the critical path can be delivered. CYC is represented by the Interim Director of Place. The YCDCB is not a decision making board but acts as a conduit back through each partner’s respective decision making processes. All CYC decisions come to the Executive for approval.
8. There are 4 projects feeding in to the YCDCB and CYC leads the York Central Infrastructure Delivery Board (YCIDB) with representatives of YCP and Network Rail (NR) and both Local Economic Partnerships (LEPs) as key funders in attendance. This board is chaired by the Corporate Director of Place.
9. The Station Frontage project is a separate corporate project undertaken in partnership with NR, but is indicated in the YC governance arrangements due to the clear links between, and need to coordinate, work to both sides of the railway station and WYCA grant funding. 10. The two remaining project boards are operated by YCP partners with the NRM leading on the delivery of their masterplan and the majority landowners Network Rail and Homes England leading the Developer Board. The council are not party to the risk registers from these boards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.