Resolved
That the report be noted. Reason: To ensure Members are aware of the risk management process for risks concerning the Community Stadium Project.
Audit and Governance Committee noted this item on Wednesday 11 December 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. Reason: To ensure Members are aware of the risk management process for risks concerning the Community Stadium Project.
Audit & Governance Committee 11 December 2013
Joint Report of Director of City and Environmental Services and Director of Communities and Neighbourhoods
Community Stadium Project – Risk Management Report Summary 1. The purpose of this paper is to: • Outline the risk management process for risks concerning the Community Stadium Project.
Background 2. The Business Case and budget for the project were noted at Cabinet on 6th March 2012 and approved at Full Council on 30th March 2012. Outline planning permission was given on the 5th July, when the Secretary of State agreed that the decision should be dealt with locally. The 3 month Judicial Review period ended without challenge on the 6th October 2012.
3. An Official Journal of the European Union (OJEU) notice starting the formal procurement activity for the project was posted on the 14th September 2012. A number of bidders submitted proposals to Design, Build Operate and Maintain the stadium and associated buildings. These have been assessed down to a final two.
4. The business case has been developed and updated as the project has progressed. The scope of the project has grown, for example, with the inclusion of the management of the city’s leisure management contract. Updates have been reported to Cabinet (November 2012 and a forthcoming paper on 7th January 2014). This is an iterative process that includes changes to the potential funding streams in the project. The requirements of the core tenants have developed as discussions with bidders have progressed and this has impacted on the overall scope and nature of the scheme. 5. Formal dialogue sessions continue with the two remaining bidders and the Invitation to Submit Final Tenders will be posted in February 2014.
6. At the 6 November 2013 Audit & Governance Committee meeting a request was made:
§ That a report on the risk management process in relation to KCR 0016 be presented at the next meeting.
Risk Management Process
7. It is important to note that a risk is something which has not yet occurred but may occur in the future. Risks are rated on the basis of impact and likelihood of the risk occurring. A risk register is a record of all of the risks to a project, regardless of how large or small or of how likely the risk is to occur. Every project should have a formal risk register.
8. The Community Stadium project has a robust risk and issue management system in place that is maintained along Prince II principles. This follows industry best practice and is designed to allow thorough scrutiny of project risks and issues and effective mitigation to be put in place. 9. There is a high degree of commercial sensitivity within the risks and issues recorded in the risk register for the project.
10. The project maintains a comprehensive risk and issue register which includes 67 risks and 8 key issues that cover a broad spectrum of areas of the project. There is also a post contract Risk Register which covers the ongoing risk to the council once the facilities are operational. The registers are reviewed weekly in project team meetings with the mitigations and actions updated and impact ratings altered according to the latest outputs of the project. For comparison the Administration & Accommodation Project incorporating the move to West Offices had circa 100 risks at this point in its project.
11. Risk headings that are covered in the register are:
§ Stadium operations § Stadium design and build § Procurement Process § Project Management § Project partners § Contract management § Finance
12. Version control is applied to the register according to Prince II project management principles. Any changes are then reviewed and agreed at the Stadium Project Board.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Community Stadium Project: Risk ManagementReport | 6 pages | DownloadRead as text |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.