Innovative Flood Resilience Programme

Decided Executive 2 papers

Executive decided this item on Tuesday 20 July 2021. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

That the ongoing work to develop the business case to access the funding indicatively valued at £5.8m be supported. Reason: To support the delivery of the York and North Yorkshire Natural Flood Risk Management Innovative Flood Resilience project. That the ongoing work to develop the business case to access the funding indicatively valued at £5.8m be supported. Reason: To support the delivery of the York and North Yorkshire Natural Flood Risk Management Innovative Flood Resilience project.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 8 pages

Summary

1. Government announced a programme to test and demonstrate ways to help communities become more resilient to flooding and coastal change in the 2020 budget. The programme aims to allocate £150 million to 25 areas in England to deliver innovative flood resilience projects.

2. City of York Council and North Yorkshire County Council have worked with a number of project partners to develop a bid for this funding, our project aims to deliver catchment wide natural flood risk management solutions that will provide increased flood resilience to North Yorkshire and York communities and reduce the impacts of existing and future flood events.

3. Following the successful award of funding members are recommended to approve the development of the business case for the project as detailed in paragraph 4 of this report.

Recommendations

4. The Executive is asked to:

i. Approve the ongoing work to develop the business case to access the funding indicatively valued at £5.8m.

Reason: To support the delivery of the York and North Yorkshire Natural Flood Risk Management Innovative Flood Resilience project. Background

5. City of York Council have developed a proposal for Defra’s Innovative Flood Resilience Grant to support catchment scale natural flood risk management solutions which would be funded through the utilisation of innovative modelling linking beneficiaries with those that can provide the services upstream. Financial modelling will identify the ways in which the services could be funded.

6. The proposal was successful and funding has been allocated to deliver the six year project. Initial funding has been provided for a development phase through to early 2022 to finalise the business case, refine the project and confirm all budgets and outcomes.

7. All funding bids required an assessment of risk and contingency to ensure all eventualities could be covered following the completion of a full business case. The project currently has a valuation of £5.8m, the final value to be awarded to the project will be confirmed following the projects development phase as detailed above.

8. The project has been developed with involvement from a number of key partners including JBA Consulting, Environment Agency, University of York, Yorkshire Dales Rivers Trust, Yorkshire Dales National Park and a range of other river catchment based partnerships.

9. The project seeks to work with landowners and those at flood risk across the River Swale, Ure and Nidd catchments upstream of the City of York and form links to develop an understanding and agreement of how changes to upstream land management can benefit at risk communities downstream. This is an ambitious project that has not previously been carried out on this scale. The project will work with the varying catchment partnerships and the good work that has already been carried out to embed catchment-sensitive farming ideals and directly link those who have the means to home upstream flood prevention measures with those who benefit from reduced flood risk downstream. The linkage would be both financial and social, providing reward and recognition for the upstream parties and engendering an understanding and sense of ownership of the measures by those who benefit downstream.

10. The project will develop a bespoke and detailed science base to identify storage and natural flood management opportunities down to a local scale, producing a ‘shopping list’ of potential measures and identifying the downstream locations that would benefit from this work. Engagement of beneficiaries in urban areas will identify ways in which they can support and contribute to the delivery of such measures, and this is expected to be supported through local policy and financial incentives and inform national policy and future programmes of investment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Innovative Flood Resilience ProgrammeReport 8 pages DownloadRead as text
PDF
View item 20. as HTML 59 KBReport 59 KB Copy on its way

At this meeting

Whole meeting

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies