Resolved

i. Approved the Project Outline for the ‘ City Centre Cycle Parking Improvements ’ scheme attached in Annex 1. Proceed to undertake Feasibility work to understand costs, timescales, outline designs and consultation feedback to inform a further decision prior to implementation. Reason: To provide clarity on the objectives and scope of the proposed scheme. ii. Approved the Project Outline for the ‘People Streets at Clifton Green Primary School’ scheme attached in Annex 2. Proceed to undertake Feasibility work to understand costs, timescales, outline designs and consultation feedback to inform a further decision prior to implementation. Reason: To provide clarity on the objectives and scope of the proposed scheme. iii. Approved the Project Outline for the ‘People Streets at Badger Hill Primary School’ scheme attached in Annex 3. Proceed to undertake Feasibility work to understand costs, timescales, outline designs and consultation feedback to inform a further decision prior to implementation. Reason: To provide clarity on the objectives and scope of the proposed scheme. iv. Agreed to make the Experimental Traffic Regulation Order relating to Navigation Road cycle scheme permanent. Reason: To successfully conclude the Navigation Road trial scheme. v. Confirmed that the proposals presented for the City Centre Bridges scheme align with the approved Project Outline, and decide to proceed with consultation, detailed design and implementation. Reason: To support progress towards implementation of a solution. vi. That officers work with the Department for Transport and Sustrans to use the existing funding to explore the feasibility of a new bridge for pedestrians and cyclists on the A1237. For officers to consider whether in the longer term if active travel provision could be considered as part of the Outer Ring Road works. For officers to explore shorter term options to improve safety are to be explored through the separate Safety Scheme Review process within the Transport Capital Programme. Reason: To consider options to create a safe crossing on the A1237. vii. That officers explore with the Department for Transport and Sustrans the possibility of undertaking feasibility work for a smaller scheme. Reason: To consider options for an affordable scheme to be undertaken. viii. Noted the outcome of the feasibility work for the ‘People Streets at Ostman Road’ scheme laid out in section 125 and decide to seek further funding before proceeding to implementation. Seek Active Travel grant funding support at the next round of bidding. However, do not progress with detailed design work on Design Option 1 presented within Annex 8. Reason: Feasibility work indicates that whilst a practically achievable scheme has been identified, there is currently insufficient budget to deliver the scheme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 30 pages

Summary

1. This report presents updated information on the progress of the Active Travel Programme, including recommendations for decisions relating to individual projects within the programme.

2. The Executive Member is asked to approve the addition of 3 new schemes to the programme following the news of a partially successful grant funding bid to the Department for Transport.

3. An update on the overall programme timescales and budget is included, with a proposal on how to manage the available funds.

4. The report recommends that the Navigation Road Experimental Traffic Regulation Order is made permanent, following a trial period and the outcome of a consultation process.

5. Feasibility work is presented for the City Centre Bridges scheme and the report recommends a decision is made to proceed to consultation, detailed design and implementation.

6. An update is provided for the A1237 Active Travel scheme, with the outcome of the feasibility work indicating that the project as it currently stands is not viable. The report explores the reasoning behind this outcome and proposes to reassign the available resources to other projects within the programme. Further safety-focussed work is proposed to be pursued through a separate programme.

7. Similarly, the Heslington to Wheldrake path scheme has progressed to a later stage of feasibility, with the outcome strongly suggesting that the objectives cannot be achieved within the available budget. A recommendation is made to reassign the available resources to other projects within the programme and progress the existing feasibility through the upcoming LCWIP work (Local Cycling and Walking Infrastructure Plan).

8. Feasibility work has been completed for the People Streets at Ostman Road scheme. This report highlights the key outcomes of this work and makes a recommendation on the next steps for the scheme.

Recommendations

9. The Executive Member is asked to:

1) Approve the Project Outline for the ‘City Centre Cycle Parking Improvements’ scheme attached in Annex 1.

Proceed to undertake Feasibility work to understand costs, timescales, outline designs and consultation feedback to inform a further decision prior to implementation. (Option 1)

Reason: To provide clarity on the objectives and scope of the proposed scheme.

2) Approve the Project Outline for the ‘People Streets at Clifton Green Primary School’ scheme attached in Annex 2.

Proceed to undertake Feasibility work to understand costs, timescales, outline designs and consultation feedback to inform a further decision prior to implementation. (Option 1)

Reason: To provide clarity on the objectives and scope of the proposed scheme.

3) Approve the Project Outline for the ‘People Streets at Badger Hill Primary School’ scheme attached in Annex 3.

Proceed to undertake Feasibility work to understand costs, timescales, outline designs and consultation feedback to inform a further decision prior to implementation. (Option 1)

Reason: To provide clarity on the objectives and scope of the proposed scheme. 4) Decide to make the Experimental Traffic Regulation Order relating to Navigation Road cycle scheme permanent. (Option 3)

Reason: To successfully conclude the Navigation Road trial scheme.

5) Confirm that the proposals presented for the City Centre Bridges scheme align with the approved Project Outline, and decide to proceed with consultation, detailed design and implementation. (Option 5)

Reason: To support progress towards implementation of a solution.

6) Support the approach to managing the programme budget laid out in Section 75 of this report. Note the programme budget summary attached in Annex 5. (Option 6)

Reason: To ensure an appropriate balance is reached between obtaining value for money and the expeditious delivery of schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Active Travel ProgrammeReport 30 pages DownloadRead as text
PDF
Background Paper 1: EATF T2 ApplicationReport 11 pages Download
PDF
Background Paper 2: ATF T3 Bid August 2021Report 236 KB Download
PDF
Background Paper 3: Project Outline: City Centre Bridges: v2.0 16022022Report 4 pages Download
PDF
Background Paper 4: Project Outline: Wheldrake to Heslington: v1.0 02022022Report 5 pages Download
PDF
Background Paper 5: Project Outline: A1237 section over the River Ouse: v1.0 03022022Report 4 pages Download
PDF
View as HTML (15./4) 30 KBReport 30 KB Copy on its way
PDF
View as HTML (15./5) 38 KBReport 38 KB Copy on its way
PDF
View as HTML (15./6) 31 KBReport 31 KB Copy on its way
PDF
View item 15. as HTML 169 KBReport 169 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Active Travel ProgrammeThis decision
  2. Active Travel Crossing Request Evaluation and Prioritisation Methodology (10:27am)Approved
  3. Active Travel Programme - Badger Hill Scheme (10:27am)Approved
  4. Active Travel Programme UpdateNoted
  5. Active Travel Programme – Hospital Fields Road SchemeApproved
  6. Active Travel Programme – Project ProgressApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies