That the implementation of this project, using the approach summarised in the report, be approved. Reason: To enable the delivery of the York and North Yorkshire Catchment Flood Management project. That the implementation of this project, using the approach summarised in the report, be approved. Reason: To enable the delivery of the York and North Yorkshire Catchment Flood Management project.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The City of York Council (the “Council”) has developed an exciting strategic approach to manage flood risk across a river catchment scale. This innovative programme of work will contribute to the solution of long term, sustainable, flood risk management in our city.
2. We are leading the co-development of natural flood risk management opportunities with a wide variety of partners that will increase flood resilience across North Yorkshire and York and support a wide range of wider climate, environmental, social and economic benefits. This initiative will expand our flood risk management activities beyond our administrative boundaries and represents the biggest, and most ambitious, change to our flood risk management strategies ever seen.
3. The Council’s Executive approved (24th June 2021) the development of a business case to deliver approved funding from the Government’s Flood and Coastal Resilience Innovation Programme.
4. The business case was developed in line with guidance from the Department for Environment, Food and Rural Affairs (“DEFRA”) and the Environment Agency and was submitted on 29th April 2022. This report summarises the proposed approach to the 5 year project (until 31st March 2027) as set out in the business case.
5. Members are recommended to approve the implementation of this project as requested in Paragraph 6 of this report. Recommendations
6. The Executive is asked to approve the implementation of this project using the approach summarised in this report.
Reason: To enable the delivery of the York and North Yorkshire Catchment Flood Management project.
Background
7. The Council developed a proposal for the Government’s Flood and Coastal Resilience Innovation Programme, which was approved for funding by Defra on 26th March 2021. Since that time, the Council has received development funding to further develop the business case and facilitate the recruitment of a project manager. An approved business case is needed to draw down further project funding.
8. The business case has been prepared following guidance provided by the Environment Agency, and sets out the strategic, economic, commercial, financial and management case for the project in line with the aims of the Flood and Coastal Resilience Innovation Programme.
9. The project aims to offset the impacts of climate change in York and smaller communities across North Yorkshire by initiating long-term change across the river catchment. The project will work with partners to deliver a programme of investment in natural flood management (“NFM”) measures which will increase the resilience of small communities across North Yorkshire. Innovative catchment-scale modelling will show how this work and wider delivery of such measures has the potential to cumulatively benefit downstream communities, including the city of York. The project will engage with catchment partners and communities to build capacity to implement NFM and raise awareness of how water connects their communities. Financing models will be investigated with the aim of developing a self-sustaining forward pipeline of NFM investment opportunities that enables a long-term legacy.
10. The total project value in the business case is £5.9m, including contingency of £1.3m.
11. The business case has been developed with involvement from a number of key partners including North Yorkshire County Council, University of York, Yorkshire Dales Rivers Trust, Yorkshire Dales National Park, Environment Agency and JBA Consulting. These partners are committed to the project and are instrumental to its successful delivery.
Consultation
12. The initial project proposal was developed in collaboration with partners and further consultation has been carried out as the business case has been developed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.