City of York Council

Active Travel – Ostman Road People Street

Approved Executive 7 papers

Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 15 November 2022. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

i. Approved Option 1 to note the outcome of the feasibility work for the ‘People Streets at Ostman Road’ scheme laid out in this report and decide to seek further funding before proceeding to implementation. Seek Active Travel grant funding support at the next round of bidding. Progress with detailed design work on ‘Design Option 1’ described in the attach Feasibility report, in advance of receiving additional funding. Reason: Progressing this scheme through detailed design will result in a ‘ shelfready ’ scheme that will be more likely to attract future funding, thereby increasing the chances of delivery on the ground. i. Approved Option 1 to note the outcome of the feasibility work for the ‘People Streets at Ostman Road’ scheme laid out in this report and decide to seek further funding before proceeding to implementation. Seek Active Travel grant funding support at the next round of bidding. Progress with detailed design work on ‘Design Option 1’ described in the attach Feasibility report, in advance of receiving additional funding. Reason: Progressing this scheme through detailed design will result in a ‘ shelfready ’ scheme that will be more likely to attract future funding, thereby increasing the chances of delivery on the ground.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 11 pages

Summary

1. 3 preliminary designs that offer pedestrians and cyclists a more appealing, safer environment by which to access Carr Infants and Junior schools have been generated.

2. A decision is required to take this scheme through to Detailed Design, while further funding support is being sought.

Recommendations

The Executive Member is asked to:

3. Approve Option 1 – Approve the progression of the proposed design option presented in Annex A through to detailed design. Incorporate this work into a future bid for additional scheme funding.

4. Reason:

Progressing this scheme through detailed design will result in a ‘shelf- ready’ scheme that will be more likely to attract future funding, thereby increasing the chances of delivery on the ground.

Background

5. The Active Travel Programme aims to improve the amenity and safety of active travel forms such as walking and cycling, promoting the adoption of healthier, more environmentally friendly travel.

6. In 2020, Sustrans carried out a one day trial in which temporary build- outs were placed outside Carr Junior school during peak times to discourage parents from parking outside schools and make the roads safer for children. The trial was popular amongst parents and residents interviewed, and was deemed a success. In response to the Sustrans trial’s success, the Active Travel Programme launched this scheme.

7. In the February 2022 Executive Member Decision Session, the Executive Member for Transport approved the Project Outline for this scheme (Background Paper 1).

8. Feasibility work has been completed and a summary report can be found in Annex I.

9. This report concludes that none of the proposed options are affordable within current budgets, however the recommendation is to seek additional grant funding at the next round of Active Travel funding to allow the scheme to progress to delivery. To achieve this, it is preferable to have a ‘shelf-ready’ scheme, which is more likely to attract funding than a proposal at the preliminary design stage.

10. To strengthen the bid for funding and to not further delay implementation, officers seek approval to progress the lowest cost design option, presented in Annex A, through Detailed Design.

Consultation

11. An electronic consultation has been carried out with local ward councillors for Acomb and external stakeholders. Targeted external stakeholders included residents and businesses on and in the immediate vicinity of Ostman Road, and parents and staff affiliated with Carr Infant and Junior Schools.

12. Refer to Annex G for a summary of the consultation responses received.

13. The majority of respondents (53%) used the street to drop off and collect children from school. Cars were the most prevalent mode of transport used by respondents (43%), with walking the second most common mode (39%) and cycling third (12%).

14. Asked about the conditions for pedestrians and cyclists, the responses indicated that the current provision is not good. Most respondents agreed that action needed to be taken to improve pedestrian safety and amenity on Ostman Road. 15. The purpose of this scheme is to encourage people to walk and cycle to school by improving conditions. 40% of respondents said they would walk / cycle instead of driving if conditions improved. 36% of respondents were undecided on this question, and 25% of respondents indicated they would not change modes even if conditions were improved.

16. This feedback suggests that there is a real possibility of influencing people’s behaviour and that there is a level of support for interventions to re-prioritise the roadspace. There were however several concerns relating to how that would be achieved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Active Travel: Ostman Road People StreetReport 11 pages DownloadRead as text
PDF
Prelim Design Option 1Appendix A 1 pages Download
PDF
Prelim Design Option 2Appendix B 1 pages Download
PDF
Prelim Design Option 3Appendix C 1 pages Download
PDF
CLoS Audit AssessmentAppendix D 1 pages Download
PDF
JAT ProposedAppendix E 1 pages Download
PDF
View item 37. as HTML 71 KBReport 71 KB Copy on its way

At this meeting

Whole meeting
35MinutesApproved
37Active Travel – Ostman Road People StreetThis decision
38Buttacre Lane Condition ReportDeferred

On this subject at York

Search all
  1. Active Travel – Ostman Road People StreetThis decision
  2. Active Travel Crossing Request Evaluation and Prioritisation Methodology (10:27am)Approved
  3. Active Travel Programme - Badger Hill Scheme (10:27am)Approved
  4. Active Travel Programme UpdateNoted
  5. Active Travel Programme – Hospital Fields Road SchemeApproved
  6. Active Travel Programme – Project ProgressApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies