Executive, Thursday 16 March 2023 at 5.30pm

Clifton Green Primary - Re-organisation and Security

Approved Executive 4 papers

Executive approved this item on Thursday 16 March 2023. Below is the council's own wording, with the papers it was decided on.

Item104

Resolved

(i) That Option 3 be approved; that is, to re-organise internal rooms and spaces and address safeguarding and security issues that affect the external areas within the school site. (ii) That approval be given to submit planning application for the scheme. (iii) That approval be given to undertake a procurement process to secure a contractor to carry out the works, and that authority be delegated to the Corporate Director of Children and Education (in consultation with the Executive Member for Children, Young People and Education, the Chief Finance Officer and the Director of Governance or their delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contract, subject to the winning bid being within the budget set out in paragraph 17 of the report. Reasons: a) To ensure that the use of the rooms and spaces within Clifton Green Primary are suitable and sufficient to meet the needs of children, to reduce the number of pupils that need to access other specialist provision around the city, and to improve the security and safeguarding of pupils and others using the site. b) This work supports the outcomes of the Inclusion Review which will provide more suitable provision in mainstream settings for neurodiverse children and for those with a primary need of SEMH (Social and Emotional Mental Health. (i) That Option 3 be approved; that is, to re-organise internal rooms and spaces and address safeguarding and security issues that affect the external areas within the school site. (ii) That approval be given to submit planning application for the scheme. (iii) That approval be given to undertake a procurement process to secure a contractor to carry out the works, and that authority be delegated to the Corporate Director of Children and Education (in consultation with the Executive Member for Children, Young People and Education, the Chief Finance Officer and the Director of Governance or their delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contract, subject to the winning bid being within the budget set out in paragraph 17 of the report. Reasons: a) To ensure that the use of the rooms and spaces within Clifton Green Primary are suitable and sufficient to meet the needs of children, to reduce the number of pupils that need to access other specialist provision around the city, and to improve the security and safeguarding of pupils and others using the site. b) This work supports the outcomes of the Inclusion Review which will provide more suitable provision in mainstream settings for neurodiverse children and for those with a primary need of SEMH (Social and Emotional Mental Health.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 8 pages

Summary

1. This report provides details about a proposed capital scheme for Clifton Green Primary School to re-organise the site to develop the provision to support better outcomes for children with SEND. Recommendations

Executive is asked to:

a. approve option 3 outlined in this report, that is to re-organise internal rooms and spaces and address safeguarding and security issues that affect the external areas within the school site. b. agree to a planning application to be submitted for the scheme.

c. approve the carrying out of a procurement process to procure a contractor to carry out the works and to delegate to the Corporate Director of Children and Education (in consultation with the Executive Member for Children, Young People and Education, the Chief Finance Officer and the Director of Governance or their delegated officers) the authority to take such steps as are necessary to procure, award and enter into the resulting contract. subject to the winning bid being within the budget set out in paragraph 17 of this report.

2. Reason: This will ensure that the use of the rooms and spaces within Clifton Green Primary are suitable and sufficient to meet the needs of children and will reduce the number of pupils that need to access other specialist provision around the city. It will also ensure that the security and safeguarding of pupils and others using the site is improved. This work supports the outcomes of the Inclusion Review which will provide more suitable provision in mainstream settings for neurodiverse children and for those with a primary need of SEMH (Social and Emotional Mental Health).

Background

3. The school recently received a ‘good’ Ofsted Inspection and is ambitious, wanting to continue its improvement journey by securing the recent ‘good’ Ofsted judgement and possibly ‘outstanding’ in the future as it will be better able to meet the needs of children with SEND if the school spaces are adapted to support their learning.

4. Academic data shows that too many children are leaving at the end of key stage assessment points below the age-related expectations.

5. Clifton Green Primary faces an increasing number of significant challenges that exacerbate the ability to help pupils reach this expectation due to teaching and intervention areas that are inaccessible, cannot be used or incorrectly located around the school building. Clifton Green Primary serves one of the most disadvantaged wards in York. The 2019 English indices of deprivation (2019) show that the school is located in amongst the 20% most deprived neighbourhoods in the country. The neighbourhood data shows that the school is within the 10% most deprived areas in the country when factoring in the areas of education, skills and training.

6. Over 13% of Clifton Green pupils speak English as an additional language which is higher than the Local Authority’s city-wide average of 8.9%.

7. The number of children with Social, Emotional and Mental Health (SEMH) needs is routinely high but this has noticeably increased due to the impact of the pandemic and the cost-of-living crisis. This requires enhanced pastoral provision and spaces for children to regulate their emotions and process their experiences on a 1:1 and small group basis.

8. The Rapid Improvement Group made specific reference to the organisation of school space where there is a lack of intervention space, intervention spaces in the right places to support year groups and children with SEN. A review of the use of the building was requested and following several meetings with the Head teacher they proposed a re-organisation of space to allow rooms, Early Years, KS1 and KS2 groups and room adjacencies work more logically within the confines of the area of the school building.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Clifton Green Primary: EIAAppendix A 13 pages Download
PDF
Clifton Green Primary: Re-organisation and SecurityReport 8 pages DownloadRead as text
PDF
View as HTML (104./2) 98 KBAppendix 98 KB Copy on its way
PDF
View item 104. as HTML 55 KBReport 55 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Clifton Green Primary - Re-organisation and SecurityThis decision
  2. Clifton Green Primary School Kingsway North York YO30 6JA [23/02271/GRG3] (7:16 pm)Approved
  3. The Determination of a Section 35(3)(a) Application by Old Grey Mare Ltd for Variation of a Premises Licence in respect of The Old Grey Mare, Clifton Green, York, YO30 6LH (CYC-9044)Approved
  4. Consideration of representations received to the advertised Residents Priority Parking scheme for Clifton Dale and Clifton GreenAgreed
  5. Hotel Noir Ltd, 3 - 5 Clifton Green [19/00108/FULM]Approved
  6. Called-in Item: Water End/Clifton Green Junction: Options for Reinstating a Separate Left Turn Traffic Lane on the Water End ApproachDecided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies