(i) That the revision to the Active Travel Programme proposed in Option 1 in the report, with the prioritisation of Phase 1 projects as set out in Annex 2, be approved. Reason: To ensure that the Active Travel Programme is affordable, achievable and effective. (ii) That approval be given to award the contract for Principal Designer services relating to a number of schemes on the Active Travel Programme, and that authority be delegated to the Director of Environment, Transport and Planning and the Chief Finance Officer, in consultation with the Director of Governance or his delegated officers, to take such steps as are necessary to award and enter into the resulting contracts (Option 3). Reason: To enable progress to be made on the ‘City Centre North South Cycle Route’ and ‘University East-West Campus Link’ schemes. (i) That the revision to the Active Travel Programme proposed in Option 1 in the report, with the prioritisation of Phase 1 projects as set out in Annex 2, be approved. Reason: To ensure that the Active Travel Programme is affordable, achievable and effective. (ii) That approval be given to award the contract for Principal Designer services relating to a number of schemes on the Active Travel Programme, and that authority be delegated to the Director of Environment, Transport and Planning and the Chief Finance Officer, in consultation with the Director of Governance or his delegated officers, to take such steps as are necessary to award and enter into the resulting contracts (Option 3). Reason: To enable progress to be made on the ‘City Centre North South Cycle Route’ and ‘University East-West Campus Link’ schemes.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The Active Travel Programme is an ambitious programme of projects to improve York’s walking and cycling infrastructure with an estimated total cost of up to £36m. The programme aims to make cycling and walking in the city more attractive and to encourage modal shift from vehicle travel to more active modes as per the Councils Local Transport Plan.
2. The intended outcomes of the programme will contribute to the city’s carbon reduction targets, improve health and wellbeing through facilitating more active lifestyles and support the local economy through facilitating safe and affordable journeys to work.
3. The programme will make a key contribution to delivering the Local Cycling and Walking Infrastructure Plan (LCWIP - which is currently being developed for approval early 2023) and also supports the Council’s key objective of ‘Getting Around Sustainably’, and responds to the governments walking and cycling strategy, “Gear Change”.
4. The programme will be delivered in phases, drawing in more funding as it becomes available from Government grants, regional funding and section 106 funding from new developments, CIL.
5. Capital funding for the first phase of the programme totals £2.1m. This is comprised of two awards of Department of Transport funding (£527k and £350k) and council capital Council capital investment of £1.2m, and £200k of contributions from LTP funding sources. This is alongside the £1.4m Transforming Cities project currently underway on Tadcaster Road. 6. The approach to dealing with this deficit has been to progress each scheme as far as is possible to strengthen their chances at future funding rounds. However, given the funding currently available, determination of which schemes should progress is required and an element of phasing of projects is required.
7. Projects proposed as the first phase focus on a combination of high priority projects that improve obvious ‘missing links’ and pinch points in the existing strategic walking and cycling network and the progression of some larger projects through project design stages to take advantage of further funding opportunities.
8. This report details the work to be implemented in Phase 1 of the programme, alongside the design-ready schemes which will be priorities for future funding bids. Further schemes may be added to later stages of the programme following the consultation and approval of the LCWIP.
9. This report will prioritise funding for ‘Phase 1’ of the programme, whilst the remaining schemes will be delivered when further funding becomes available, under ‘Phase 2’.
10. This report sets out the rationale in prioritising the schemes identified in Phase 1 and seeks Executive approval for the proposed programme.
11. Additionally, this report seeks a decision to award a contract for services relating to a number of schemes on the programme (option 3).
Recommendations
12. The Executive is asked to:
1) Approve the revision to the Active Travel Programme proposed in Option 1 of this report, with the prioritisation of Phase 1 projects as per Annex 2.
Reason: To ensure that the Active Travel Programme is affordable and achievable and effective.
2) Approve the award of the contract for Principal Designer services relating to a number of schemes on the Active Travel Programme and delegate to the Director of Environment, Transport and Planning and the Chief Finance Officer (in consultation with the Director of Governance or their delegated officers) the authority to take such steps as are necessary to award and enter into the resulting contracts (Option 3).
Reason: To enable progress on the ‘City Centre North South Cycle Route’ and ‘University East-West Campus Link’ schemes.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.