City of York Council
Executive, Thursday 12 October 2023 at 5.30pm

Capital Projects 2024/25 (19:48)

Approved Executive 4 papers

Executive approved this item on Thursday 12 October 2023. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

i. Approved the £3,000,000 budget for capital maintenance works planned for 2024/25. Reason: To complete the annual programme of maintenance works within the maintained school estate, dealing with the most urgent issues for 2024/25. ii. Approved the budget of £1,400,000 to build additional classrooms to accommodate a growth in pupil places at St Oswald’s CE VC Primary. Reason: To accommodate the demand for mainstream school pupil places. iii. Approved the budget of £1,100,000 to build additional classrooms to accommodate the demand SEN pupil places at Hob Moor Oaks Community Primary Academy. Reason: To accommodate the demand for special school pupil places for those children with complex special educational needs. iv. Approved the budget of £1,100,000 to refurbish the science labs at Huntington Secondary School. Reason: To resolve health and safety issues within the existing science labs that mean teachers are unable to deliver the full science curriculum. This will ensure these labs are future-proofed for existing pupil numbers prior to the increased pupil numbers expected from planned housing developments. v. Approved the £600,000 budget to create outdoor learning areas at Danesgate Community Pupil Referral Unit. Reason: To accommodate the increased demand for alternative teaching spaces for pupils with Social and Emotional Mental Health (“SEMH”). vi. Agreed to delegate approval of expenditure on individual schemes to the Corporate Director of Children’s Services and Education (or his delegated officers). Reason: To ensure efficient spend and that decisions are made in a timely manner on individual schemes throughout the life of the capital programme. vii. Agreed to delegate authority to the Corporate Director of Children’s Services and Education (or his delegated officers), in consultation with the Director of Governance (or his delegated officers), to determine the provisions of any new works contracts necessary for the delivery of the Education Capital Programme, 2024/25, and to award and conclude each of these contracts following the appropriate competitive tendering processes. Reason: This ensure compliance with LA’s Contract Procedure Rules and its obligations under Public Procurement Law, as well as enable the Education Capital Programme, 2024/25 to be delivered on time. i. Approved the £3,000,000 budget for capital maintenance works planned for 2024/25. Reason: To complete the annual programme of maintenance works within the maintained school estate, dealing with the most urgent issues for 2024/25. ii. Approved the budget of £1,400,000 to build additional classrooms to accommodate a growth in pupil places at St Oswald’s CE VC Primary. Reason: To accommodate the demand for mainstream school pupil places. iii. Approved the budget of £1,100,000 to build additional classrooms to accommodate the demand SEN pupil places at Hob Moor Oaks Community Primary Academy. Reason: To accommodate the demand for special school pupil places for those children with complex special educational needs. iv. Approved the budget of £1,100,000 to refurbish the science labs at Huntington Secondary School. Reason: To resolve health and safety issues within the existing science labs that mean teachers are unable to deliver the full science curriculum. This will ensure these labs are future-proofed for existing pupil numbers prior to the increased pupil numbers expected from planned housing developments. v. Approved the £600,000 budget to create outdoor learning areas at Danesgate Community Pupil Referral Unit. Reason: To accommodate the increased demand for alternative teaching spaces for pupils with Social and Emotional Mental Health (“SEMH”). vi. Agreed to delegate approval of expenditure on individual schemes to the Corporate Director of Children’s Services and Education (or his delegated officers). Reason: To ensure efficient spend and that decisions are made in a timely manner on individual schemes throughout the life of the capital programme. vii. Agreed to delegate authority to the Corporate Director of Children’s Services and Education (or his delegated officers), in consultation with the Director of Governance (or his delegated officers), to determine the provisions of any new works contracts necessary for the delivery of the Education Capital Programme, 2024/25, and to award and conclude each of these contracts following the appropriate competitive tendering processes. Reason: This ensure compliance with LA’s Contract Procedure Rules and its obligations under Public Procurement Law, as well as enable the Education Capital Programme, 2024/25 to be delivered on time.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 19 pages

Meeting: Executive Meeting date: 12/10/2023 Report of: Report of the Corporate Director, Children’s Services and Education Portfolio of: Executive Member for Children, Young People and Education, Councillor Bob Webb

Decision Report: Capital Projects 2024/25 - Children, Young People and Education Subject of Report 1. To approve the overall budget of £7,200,000 to enable the schemes in the Education Capital Programme, 2024/25 (the “Programme”) to take place.

2. To maintain the Local Authority (“LA”) School Building Estate.

3. To create enough pupil places and Special Educational Needs (“SEN”) pupil places at St Oswald’s CE VC Primary and Hob Moor Oaks Community Primary Academy.

4. To create SEN outdoor learning areas at Danesgate Community Pupil Referral Unit.

5. To refurbish the science labs at Huntington Secondary School.

6. Without these works, the LA School Building Estate could face severe risks in its ability to function and the LA sufficiency duty under section 14 of the Education Act 1996 would not be met.

Benefits and Challenges

Page 1 of 19 Pros:

7. Keeping abreast of the condition works needed at LA maintained schools will ensure Best Value under its Best Value Duty set out in Section 3 of the Local Government Act 1999 (as amended by s137 of the Local Government & Public Involvement in Health Act 2007).

8. The LA’s sufficiency duty under section 14 of the Education Act 1996 to provide pupil places and SEN pupil places will not be breached.

Cons:

9. Not keeping abreast of the works needed to the declining condition of the School Building Estate will mean:

 Greater maintenance costs in each year where works do not take place.

 The LA failing in its sufficiency duty to provide enough pupil places.

10. The LA failing in its sufficiency duty to provide SEN pupil places.

Policy Basis for Decision 11. The council’s commitment to provide access to high quality education and skills for all is consistent with the 10-Year Plan (York 2032), which sets out a vision for the city and five priorities. The priority Skills and Education sets an ambition that “all ages will have access to learning throughout their lives to equip them with the skills to success commercially, socially, locally and nationally”.

12. This report responds to the Council Plan 2023-2027 - One York for all, which sets a vision for the Council that over the next four years we will “establish the conditions that would make the city of York a healthier, fairer, more affordable, more sustainable and more accessible place, where everyone feels valued, creating more regional opportunities to help today’s residents and benefit future generations.”

13. The report aligns to the below policy priorities in the Council Plan: a. Health Generating City

Page 2 of 19 b. High quality skills and learning for all c. Sustainable accessible transport for all d. Cutting Carbon, enhancing the environment for our future

Cutting Carbon, protecting the environment 14. Reducing carbon emissions through the delivery of the capital maintenance schemes by for example:

a. insulating roofs, b. replacing lead single glazed windows for double glazed efficient windows, and c. refurbishing kitchens and science labs with sustainable, modern equipment, d. that saves both time and energy. e. Replacing old wiring and heating mains pipework.

15. New builds will be created to the most current building specifications.

16. Better tinted windows mean less solar gain, so rooms and corridors are not affected by extreme temperatures during hot summers and cold winters.

Sustainable accessible transport for all 17. By expanding at three (3) school sites (St Oswald’s for mainstream pupils and Hob Moor Oaks Community Primary Academy and Danesgate Community Pupil Referral Unit for SEN pupils), the LA will prevent increased transport journeys and costs around the city.

Health Generating city

18. Better teaching environments are created when roofs are not leaking and heating is more temperate and more efficient.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Projects 2024/25 (19:48)Report 19 pages DownloadRead as text
PDF
EIA: Capital Projects 2024-25Report 12 pages Download
PDF
View as HTML (42./2) 102 KBReport 102 KB Copy on its way
PDF
View item 42. as HTML 141 KBReport 141 KB Copy on its way

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies