i. Noted and accepted the changes recommended by the Yorkshire Purchasing Organisation Management Committee. ii. The Executive agreed to delegated authority to the Director of Governance to sign an updated Management Agreement on behalf of the Council of the City of York, noting that all Member Authorities of Yorkshire Purchasing Organisation must also agree before the revisions take effect. iii. The Executive agreed to delegate contracting authority to the functional role of Managing Director of Yorkshire Purchasing Organisation. Reason: YPO has operated as a Joint Committee since its inception in 1974 and under the governance structure in the current Management Agreement since 2010. The governance of the arrangements needs to be updated to ensure that the governance of YPO Management Committee remains up to date and fit for purpose. i. Noted and accepted the changes recommended by the Yorkshire Purchasing Organisation Management Committee. ii. The Executive agreed to delegated authority to the Director of Governance to sign an updated Management Agreement on behalf of the Council of the City of York, noting that all Member Authorities of Yorkshire Purchasing Organisation must also agree before the revisions take effect. iii. The Executive agreed to delegate contracting authority to the functional role of Managing Director of Yorkshire Purchasing Organisation. Reason: YPO has operated as a Joint Committee since its inception in 1974 and under the governance structure in the current Management Agreement since 2010. The governance of the arrangements needs to be updated to ensure that the governance of YPO Management Committee remains up to date and fit for purpose.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting: Executive Meeting date: 9th May 2024 Report of: Bryn Roberts Director of Governance & Monitoring Officer
Debbie Mitchell Chief Finance Officer
Dan Moynihan Deputy Monitoring Officer & Senior Lawyer Portfolio of: Cllr Katie Lomas Executive Member for Finance, Performance, Major Projects, Human Rights, Equality, and Inclusion
Decision Report: Update to Joint Committee Governance Arrangements for the Yorkshire Purchasing Organisation (“YPO”) Subject of Report 1. This report is to seek approval from Executive to sign a revised Management Agreement which sets out the governance arrangements for the YPO Joint Management Committee following a review of governance and recommendations for approval from the YPO Management Committee.
Benefits and Challenges 2. Continued participation in YPO helps CYC to combine its purchasing power with other local authorities to maximise economies of scale and ensure value for money.
Policy Basis for Decision
Page 1 of 12 3. In December 2022, Full Council approved a 10-Year Plan, known as “York 2032”, and 10-Year Strategies. The Council Plan 2023- 2027 was approved by Full Council in September 2023, and contributes to delivery of the 10-Year Strategies. The Council Plan has four core commitments, that define the outcomes the council will deliver over the current administrative term:
Affordability; Environment; Equalities and Human Rights; and Health Inequalities.
The proposals within this report are consistent with these four key pledges as follows:
a) Affordability: Through its continued participation in YPO, CYC combines its purchasing power with other local authorities to maximise economies of scale and ensure value for money.
b) Health Inequalities: Overall, good local government financial governance plays a crucial role in promoting public health by ensuring that resources are allocated efficiently, these efforts contribute to creating healthier and more resilient communities.
Financial Strategy Implications 4. The recommended option has no financial implications. As one of the founder members of YPO, CYC combines its purchasing power with other local authorities to maximise economies of scale and ensure value for money. The continuation of this arrangement will support CYC in meeting the financial challenges ahead.
Recommendation and Reasons 5. It is recommended that the Executive:
a) To note, consider and accept the changes recommended by the Yorkshire Purchasing Organisation Management Committee.
Page 2 of 12 b) To delegate authority to the Director of Governance to sign an updated Management Agreement on behalf of the Council of the City of York, noting that all Member Authorities of Yorkshire Purchasing Organisation must also agree before the revisions take effect.
c) To delegate contracting authority to the functional role of Managing Director of Yorkshire Purchasing Organisation.
6. Reasons:
a) YPO has operated as a Joint Committee since its inception in 1974 and under the governance structure in the current Management Agreement since 2010. The governance of the arrangements needs to be updated to ensure that the governance of YPO Management Committee remains up to date and fit for purpose.
Background 7. YPO has operated as a Joint Committee since its inception in 1974 and under the governance structure in the current Management Agreement since 2010.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.