Resolved
That the report be noted. Reason: To inform the development and delivery of Carbon Negative Challenge Fund projects.
Corporate Services, Climate Change and Scrutiny Management Committee noted this item on Monday 14 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. Reason: To inform the development and delivery of Carbon Negative Challenge Fund projects.
1. City of York Council was awarded £2.9m from the Combined Authority Net Zero Fund to deliver projects that contributed to the decarbonisation of the region. The funding was awarded in November 2023 for both project development and project delivery. Projects were required to complete delivery and expenditure by 31 March 2025.
2. This report provides an update to the previous paper presented to Corporate Services, Climate Change and Scrutiny Management Committee in December 2023; summarising the status, benefits, challenges and lessons learnt from each of the projects, to inform future funding applications and project development and delivery.
Background 3. As part of York & North Yorkshire’s devolution arrangements, a £7m Net Zero Fund was established in 2023 to enable the development and delivery of projects that would contribute to decarbonisation across the region. 4. The fund would support both development (revenue) and delivery (capital) projects, with funding allocated through a competitive application process.
5. An internal review and prioritisation process resulted in City of York Council submitting applications for 14 projects, totalling over £5m in grant funding ask for York. These projects are summarised in Table 1. Fund Project Title Description Development Grimston Bar Solar Feasibility study for potential ground-mounted Scheme solar PV scheme Development Onshore Wind Feasibility study for potential wind turbine north (Wigginton) of Wigginton Development Garden Village Design assessment of lowest carbon, lowest Decarbonisation cost approach to decarbonise the development Plan Development York Sport Club Heat Decarbonisation Plans for community Energy Savings sport facilities Development Harewood Whin Planning application and full business case for Green Energy Park potential 28MW Green Energy Park project Development Post Occupancy Approach to monitoring ‘as built’ versus ‘as Monitoring modelled’ energy performance of CYC’s housing delivery programme Delivery CYC Lighting LED replacement at CYC office buildings, Upgrades schools and sheltered accommodation Delivery HyperHub 4 Fourth EV charging hyperhub in the south of the city Delivery Alex Lyon & Replacement of fossil fuel heating system with Honeysuckle House low carbon communal system heat decarbonisation Delivery Every Mouthful Comprehensive approach to reducing food Matters York loss and improving redistribution Delivery LED Street Lighting LED replacement of remaining streetlamps Delivery York Central – Environmental improvement to commercial Commercial use units at York Central Delivery Coney Street Environmental improvement to commercial environmental uplift units and public realm at Coney Street Delivery HRA Energy Installation of battery storage and heat-pumps Efficiency Upgrades at CYC properties with Solar Table 1: Projects submitted by CYC to the Net Zero Fund
6. Following independent assessment, City of York Council was awarded £2.9m from the Net Zero Fund in November 2023, for the following projects: Development Harewood Whin Green Energy Park - £243,500 Renewable generation Feasibility study: North Wigginton - £50,000 Renewable generation Feasibility study: Grimston Bar - £50,000
Delivery Renewable Heating upgrades: Alex Lyon & Honeysuckle House - £1,895,000 LED Conversion: Streetlighting - £352,282 LED Conversion: Commercial - £354,000 7. On award of funding in November 2023, projects were required to be completed by end of March 2025. Subsequently, some projects have applied for extensions from the Combined Authority to the end of June 2025 – this is noted below where relevant. Project Updates
Project Harewood Whin Green Energy Park
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Net Zero Fund: Project Update (5.37 pm)Report | 13 pages | DownloadRead as text |
PDF |
View item 64. as HTML 109 KBReport | 109 KB | Copy on its way |
Follow Corporate Services, Climate Change and Scrutiny Management Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 May 2025 | Minutes (5.33 pm)That the minutes of the last meetings held on 10 March 2025 and 14 April 2025 were approved as a correct record. | Approved | Open |
| 12 May 2025 | Pre-Decision Scrutiny: Equity, Diversity and, Inclusion and Strategy (5.40 pm)That further work on the Equity, Diversity and, Inclusion and Strategy be undertaken to take into account Member comm... | Decided | Open |
| 12 May 2025 | Monitoring and Tracking of Approved Council Motions (6.55 pm)That the report be noted and the Chair and Vice-Chair to determine which Motions can be closed and removed from the t... | Noted | Open |
| 12 May 2025 | Schedule of Petitions (7.10 pm)i. That the report be noted and that ii. Further information be requested from officers in relation to petition 232 a... | Noted | Open |
| 12 May 2025 | Preparing for proposed changes to long-term sickness and disability benefits, Task and Finish Group Review (7.25 pm)i. That the Terms of Reference be agreed. ii. Membership of the group should consist of 2 x Labour, 2 x Liberal Democ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.