Resolved (unanimously): That Executive 1) Approves £4m of BSIP1 funding and £250k of allocated YNYCA Bus Grant funding to deliver Park and Ride site improvements as outlined in Annex A. Reason: To modernise old facilities for existing and future Park and Ride users and to attract more passengers to use Park and Ride services. 2) Delegates authority to the Director of City Development (in consultation with the Director of Governance and the Head of Procurement) to implement the proposed Park and Ride site Infrastructure improvements and to carry out any required procurement processes and to take such steps as are necessary to procure, award and enter into the resulting contracts. Reason: To ensure expedient delivery of the projects. 3) Delegates authority to the Director of City Development (in consultation with the Chief Finance Officer and the Director of Governance) to explore and implement further income opportunities associated with Park and Ride including setting fees for overnight parking. Reason: To further support the financial viability of Park and Ride provision. 4) Delegates authority to the Director of City Development (in consultation with the Director of Governance and the Head of Procurement) to agree an extension to the existing Park and Ride contract and any associated leases, of not more than two years duration, and to take such steps as are necessary to enter into the resulting variation and extension agreement and lease extensions. Reason: To provide continuation of service and to enable the results of the York and North Yorkshire Combined Authority bus network review to be incorporated into the new Park and Ride contract.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting: Executive Meeting date: 7 October 2025 Report of: Director of City Development Portfolio of: Councillor Kate Ravilious, Executive Member for Transport
Decision Report: Park and Ride: Site Improvements and New Bus Service Contract Subject of Report 1. The report presents two connected projects for approval: firstly, a range of infrastructure improvements to five Park and Ride sites to be funded through Bus Service Improvement Plan (BSIP) grant. Secondly a two-year extension to the contract for the operation of Park and Ride bus services is proposed to enable continuity of service until wider conversations with the York and North Yorkshire Combined Authority (YNYCA) are concluded.
2. A range of infrastructure changes are required to replace and refresh existing aging site facilities, improve security and offer a more dynamic Park and Ride product. An extension to the contract for the operation of the bus services is essential to ensure continuity of the service and to enable the Council to reduce congestion in the city.
Benefits and Challenges 3. Maintaining a fresh and attractive Park and Ride product is essential for reducing car trips into York City Centre. Whilst Poppleton Bar and Askham Bar are relatively new sites with modern facilities, Rawcliffe Bar and Grimston Bar in particular were constructed in the mid 1990’s and are in need of more substantial updating. The current buildings at Grimston Bar housing the staff and toilet facilities are in poor repair, are not located next to the bus stop, do not have sufficient space for optimal toilet facilities and would benefit from replacement. Rawcliffe Bar suffers from antisocial behaviour and the current layout of the building does not offer quality facilities for passengers.
4. A key element of the BSIP work was to turn the Park and Ride sites into integrated transport hubs and to enable more trips where more than just a bus journey may be required. The proposed infrastructure changes include improving cycle parking provision for both Park and Cycle and those who cycle to the P&R site then take the bus into the city centre, car club bays, micromobility parking and coach (National Express and Flixbus) stops at Askham Bar.
5. Site security is also an issue at Monks Cross where the building has regularly been a target for antisocial behaviour. This situation has resulted in the toilets being closed when the site supervisor leaves and passengers having to use other toilet facilities in the vicinity which is not desirable.
6. A wide range of improvements can be made to improve the accessibility at the Park and Ride sites. From improving the dimensions of accessible parking bays, to introducing the first Changing Places facilities at Park and Ride sites the infrastructure funding will enable more people to comfortably use the service.
7. Overnight Parking at two Park and Ride sites will enable more people to use the service and can reduce the number of vehicles arriving into York Centre looking for a parking space. This can reduce congestion, particularly on Friday afternoons where bus operating conditions are challenging. Visitors arriving for a long weekend will be able to park overnight at Rawcliffe Bar or Askham Bar in a dedicated area with 24/7 access and use the bus to get into the centre, then pick their vehicle up on the day of their departure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.