Housing Delivery Programme Delivery Strategy

Approved Executive 7 papers

AI summaryYork Executive approves long-term Housing Delivery Programme strategy, appointing a Strategic Delivery Partner for an initial phase of five sites aiming to deliver over 315 affordable homes over approximately 10 years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedLong-term Strategic Delivery Partner approach for HDP
MoneynullNo overall budget figure given in the papers
What happens nextProcurement under wayStrategic Delivery Partner procurement Autumn 2026 to Spring 2027
Who it affectsAll WardsCouncil-owned sites across the city

What was decided

The Executive approved the Delivery Strategy, including an initial phase of five sites: Ordnance Lane, Castle Mills, Willow House, Lowfield Plot A and Manor School, via a long-term Strategic Delivery Partner and client-side multidisciplinary team. Report P33

Members agreed the Strategy may, subject to future Executive approvals, support additional HDP sites and wider strategic sites, including One Public Estate and major brownfield regeneration schemes. Report P34, P8

Members approved replacing the Passivhaus-certification requirement with the Homes England Healthy Homes Standard and alignment with the Future Homes Standard, with possible enhancements such as AECB. Report P40, P15, P16

Why

Officers said a recent procurement for 101 homes at Ordnance Lane failed to attract a contract award, reflecting weak market appetite driven by inflation, supply chain fragility, contractor risk aversion, scheme complexity and Passivhaus requirements. Report P45, P30, P15

A long-term Strategic Delivery Partner is intended to secure pace, scale, value for money, programme-wide efficiencies and a city-focused Social Value Plan, while keeping site-by-site business cases and Executive control over major construction contracts. Report P6, P9, P12, P18, P23

Similar strategic delivery partnerships have been used by Hull City Council and Cambridge City Council, and the approach is supported by Public Health and aligned with the Council Plan priority to increase affordable housing supply. Report P19, P25, P89

What happens next

Preliminary Market Engagement runs in Spring 2026, followed by procurement of the client-side multidisciplinary team in Spring to Summer 2026, and procurement of the Strategic Delivery Partner from Autumn 2026 to Spring 2027. Report P66

Early site mobilisation and preparation is planned to begin at Ordnance Lane and Willow House in Spring 2027, with a separate demolition contract for the southern part of Willow House to start in the next few months. Report P7, P55, P66

Further contract awards to the Partner are expected from Summer 2027 onwards on a site-by-site basis, each subject to an updated business case coming back to Executive before any major construction contract is entered into. Report P34, P66

The money

  • over 315 new affordable homes Indicative total for the initial five-site phase of the Partnership, subject to planning and viability Report P7

Options considered

  • Chosen: Procure a single Strategic Delivery Partner covering a programme of sites. Aims to deliver at pace and scale with reduced risk to the Council, stronger competition, supply chain engagement, and clearer governance; similar to approaches used by Hull and Cambridge. Report P61, P62, P19
  • Rejected: Continue site-by-site procurement and delivery. Creates repeated procurement cycles, duplicated costs and limits ability to deliver HDP and wider strategic sites at pace and scale; reduces pipeline certainty for the market. Report P67, P68, P69
  • Rejected: Dispose of initial phase sites to Registered Providers. Could transfer delivery and financial risk and generate capital receipts, but would limit HRA rental income, reduce long-term housing assets under Council ownership, and may not secure 100% affordable outcomes on viability-challenged sites. Report P70, P71

Implications

  • Financial: Schemes must remain viable within the HRA 30-year Business Plan or General Fund; funding will use a blend of HRA borrowing, grant, Section 106 monies and Right to Buy receipts, with possible Partner financing of commercial or homes for sale subject to Executive approval. Report P27, P29, P73
  • Legal: Procurement must comply with the Council's Financial Regulations, Contract Procedure Rules, the Procurement Act 2023 and the Public Contract Regulations 2015; grant funding must comply with the Subsidy Control Act 2022; disposal of HRA and General Fund land must follow statutory requirements and General Consent Order limits. Report P35, P39, P79, P80, P82, P83
  • Equalities: A Human Rights and Equality Assessment (Annex B) supports the proposals, with a review due within 3 years; the Council must have due regard to its Public Sector Equality Duty under section 149 of the Equality Act 2010. Report P97, P98, P99
  • Climate: Moving away from Passivhaus certification may reduce overall environmental performance, but Homes England Healthy Homes Standard with EPC A where achievable, Whole Life Carbon Assessment and Future Homes Standard alignment maintain a low-carbon approach; enhancements such as AECB are being considered. Report P16, P91, P92, P93
  • Risk: Key risks include single Partner dependency, viability and market conditions, funding and affordability, procurement risk, programme slippage and Partner financial standing; mitigations include site-by-site contract awards, break clauses, performance security, separate business cases, and phased delivery. Report P23, P106, P107, P108, P109, P110, P111
  • Staffing: The report states there are no HR implications contained within it. Report P77
  • Other: Compulsory Purchase Order powers under sections 226(1)(a) and 226(1A) of the Town and Country Planning Act 1990 are noted and further reports may come back if needed. Report P41, P85

Who and where

  • Households in need of affordable housing in York, including social rent and shared ownership tenants Report P7, P18, P96
  • Council tenants and applicants on the housing register, including those needing supported housing at Lowfield Plot A Report P5
  • Construction market, supply chain, local skills and apprenticeship providers through a city-focused Social Value Plan Report P9, P18
  • Registered Providers being considered for separate disposals of sites including Woolnough House, 68 Centre, Clifton Without Junior School, Lowfield Plot B, Morrell House and The Glen Report P58
  • Wider public sector partners such as NHS, Ministry of Defence and York and North Yorkshire Combined Authority for future One Public Estate and regeneration opportunities Report P8, P26
  • All wards of the City of York Council area Report P112

Timeline

  • 14 April 2026: Executive approves the Housing Delivery Programme Delivery Strategy Report P2
  • Spring 2026: Preliminary Market Engagement with housebuilders and contractors Report P66
  • Next few months: Demolition of buildings at Willow House is expected to start, in readiness for the Partner to build new homes Report P7, P55
  • Spring to Summer 2026: Procurement of client-side multidisciplinary professional team Report P66
  • Autumn 2026 to Spring 2027: Procurement of the Strategic Delivery Partner Report P66
  • Spring 2027: Early site mobilisation and preparation activity commences at Ordnance Lane and Willow House Report P66
  • Summer 2027 onwards: Further contract awards to the Partner on a site-by-site basis, subject to Executive approvals Report P66
  • Approximately 10 years, with potential 5-year extensions: Anticipated length of the Partnership, subject to partner performance and Executive approvals on a site-by-site or group basis Report P10

Plain English for the jargon

  • HDP: Housing Delivery Programme, the Council's programme for building new council and affordable homes
  • HRA: Housing Revenue Account, the ring-fenced account that funds council housing
  • RPs: Registered Providers, social housing landlords such as housing associations
  • YNYCA: York and North Yorkshire Combined Authority
  • Passivhaus: A rigorous German energy-efficiency standard for buildings requiring very high levels of insulation and airtightness
  • EPC A: The top Energy Performance Certificate rating, indicating the lowest expected energy running costs
  • CPO: Compulsory Purchase Order, a legal power to acquire land without the owner's consent, with Secretary of State authorisation
  • AECB: Association for Environment Conscious Building, a recognised approach to building energy performance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item225

Resolved

Resolved (unanimously): That Executive a) Approves the Delivery Strategy for the HDP, including an initial phase of five sites (Ordnance Lane, Castle Mills, Willow House, Lowfield Plot A and Manor School), via the appointment of a long-term Strategic Delivery Partner and client-side multidisciplinary professional team. b) Agrees that the Delivery Strategy, subject to future Executive approvals, may be used to support the delivery of additional sites in the HDP, as well as strategic sites that may come forward through the Council’s wider asset programmes and One Public Estate partnership work, including major public ? sector land opportunities and significant brownfield regeneration schemes. c) Approves that prior to entering into any major construction contract in the HDP, a business case will be brought back to Executive for approval. d) Agrees to delegate authority to the Director of Housing and Communities and/or the Director of City Development (as appropriate based on the site) (in consultation with the Director of Finance and the Director of Governance) to take such steps that are necessary to procure and appoint the Strategic Delivery Partner, multidisciplinary professional team, and demolition of buildings at Willow House, and to determine the provisions of and enter into the resulting contracts (including any and all partnership agreements, pre-construction services agreements and early / minor / enabling / demolition works contracts) and any other necessary legal documentation (including any and all planning agreements and/or highways/land agreements as required; however, for the sake of clarity this delegation is not for any requirements of either the Local Planning and/or Highways Authority), and the provisions of any subsequent modifications and/or extensions thereto, in accordance with the Council’s Financial Regulations set out in Appendices 10 and 10a of the Constitution (the “Finance Regs”), the Contract Procedure Rules set out in Appendix 11 of the Constitution (the “CPRs”) and (where applicable) the Procurement Act 2023 (the “Procurement Act”) and the Public Contract Regulations 2015 (the “PCRs”), within approved budgets and subject to the availability of funding. e) Agrees to delegate authority to the Director of Housing and Communities and/or the Director of City Development (as appropriate based on the site) (in consultation with the Directors of Governance and Finance) to agree and enter into any land assembly, access, highways, easement, wayleave, title regularisation, or minor freehold/leasehold disposal necessary to deliver individual schemes (and the provisions of any subsequent modifications and/or extensions thereto), where consistent with an Executive ? approved business case and statutory requirements. f) Agrees to delegate authority to the Director of Housing and Communities and/or the Director of City Development (as appropriate based on the site) to negotiate and enter into any Section 106, Section 278, Section 38, utilities, adoption, estate management, collaboration or development agreements required to implement schemes (and the provisions of any subsequent modifications and/or extensions thereto), following Executive approval of the relevant business case. g) Agrees to delegate authority to the Director of Housing and Communities and/or the Director of City Development (as appropriate based on the site) (in consultation with the Director ...
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

y

Meeting: Executive Meeting date: 14 April 2026 Report of: Pauline Stuchfield, Director of Housing and Communities Garry Taylor, Director of City Development Portfolio of: Councillor Michael Pavlovic, Executive Member for Housing, Planning and Safer Communities

Decision Report: Housing Delivery Programme Delivery Strategy Subject of Report

1. City of York Council has built a strong, proven track record of delivering high-quality homes and placemaking. Through the Housing Delivery Programme (HDP), the Council has successfully delivered new homes at Lowfield Green, Duncombe Square and Burnholme Green. The Council has also completed refurbishment and retrofit at Bell Farm, redevelopment of Marjorie Waite Court, Lincoln Court and a refurbishment of Glen Lodge.

2. The Council has, over recent years, committed to delivering 100% affordable homes on a number of Council-owned sites and is actively progressing this commitment. This includes demolishing buildings at Ordnance Lane and securing a new planning permission; developing a new business case for Castle Mills; submitting a planning application for Willow House and advancing regeneration proposals for Walmgate; and bringing forward proposals for supported housing at Lowfield Plot A. The Council has also developed a programme to improve and expand Gypsy and Traveller accommodation in the city. The Council has secured significant external grant funding to help unlock delivery. Each of these proposals has been shaped through extensive engagement with local communities and stakeholders to ensure they meet York’s housing needs. The Council also continues to work in partnership with Registered Providers (RPs) to bring forward delivery of 100% affordable housing on smaller Council sites.

3. To unlock the next phase of delivery, develop at pace and scale, and with reduced risk to the Council - this report seeks approval for a new long-term Delivery Strategy. The Strategy proposes appointing a Strategic Delivery Partner (such as a housebuilder or contractor) to deliver new build housing within the HDP pipeline. This partnership approach is designed to accelerate delivery and strengthen resilience in challenging market conditions, while also supporting wider ambitions across the public estate, including opportunities linked to One Public Estate, health-estate renewal and neighbourhood-based regeneration.

4. Through this Partnership, the Council will aim to deliver over 315 new affordable homes (subject to planning and viability) across an initial phase of five Council-owned sites: Ordnance Lane, Willow House, Lowfield Plot A, Castle Mills and Manor School. Ordnance Lane and Willow House are anticipated to start on site with early site mobilisation and preparation activity shortly after contracts are agreed. Demolition work at Willow House is expected to start over the next few months, in readiness for the Strategic Delivery Partner to build the new homes.

5. The Delivery Strategy has also been designed as a flexible vehicle for future growth, capable of supporting the delivery of additional sites in the HDP, as well as major strategic sites that may come forward through wider Council asset programmes or One Public Estate partnership work. This includes complex public sector or brownfield regeneration opportunities involving NHS, Ministry of Defence or other public landholdings. The proposed governance and delegations ensure that (subject to future Executive decisions) the Partnership can enable faster, more coordinated delivery across the wider public sector estate, contributing to citywide ambitions for new homes, regeneration, health facilities, community spaces and placemaking. The scale and scope of delivery achieved through the Partnership will be subject to governance, viability, market appetite and prevailing market conditions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Delivery Programme Delivery StrategyReport 597 KB DownloadRead as text
PDF
Item 9: Housing Delivery Programme Delivery Strategy: Annex AAppendix 527 KB Download
PDF
Item 9: Housing Delivery Programme Delivery Strategy: Annex BAppendix 700 KB Download
PDF
Item 9: Housing Delivery Programme Delivery Strategy: Annex CAppendix 329 KB Download
PDF
View as HTML (225./3) 181 KBAppendix 181 KB Copy on its way
PDF
View as HTML (225./4) 43 KBAppendix 43 KB Copy on its way
PDF
View item 225. as HTML 172 KBReport 172 KB Copy on its way

At this meeting

Whole meeting

Who was there

8 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneVice-Chair, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbCommittee Member, present

On this subject at York

Search all
  1. Housing Delivery Programme Delivery StrategyThis decision
  2. Preparation for Potential Use of Compulsory Purchase Powers at Willow House to Support the Delivery of Affordable Housing (5:49pm)Noted
  3. Called-in Item: Housing Delivery Programme Delivery StrategyAgreed
  4. Delivering More Affordable Housing in York – Update on the Housing Delivery ProgrammeApproved
  5. Delivery of supported affordable housing at Lowfield Plot A (17:05)Approved
  6. Update on the Housing Delivery Programme including making strategic use of land assets (17:32)Agreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open