Parks Investment Fund - progress report (4:45pm)

Noted Executive 6 papers

AI summaryCity of York Council's Executive unanimously paused work on the Bachelor Hill Tenant Road steps and approved play area tree planting with White Rose Forest. Funding changes were noted for the 500k Parks Investment Fund, and reserve schemes cannot proceed in the current programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress and funding changes noted; reserve schemes cannot proceed.
Money500kBackground approval; current adjustments are in Annex 1.
What happens nextPlant trees, pause scheme 19With White Rose Forest; no reserve schemes in this programme.
Who it affectsParks, play areas, green spacesTree planting covers play areas and immediate surrounding green spaces.

What was decided

City of York Council's Executive unanimously noted significant progress on the approved programme and benefits already beginning. It noted the funding adjustments for each scheme set out in Annex 1.

The Executive noted findings from the PIF play area consultation, which were already being used to inform play area requirements.

It paused further work on scheme 19, Bachelor Hill Tenant Road steps. It approved a tree planting programme for the Council's play areas and immediate surrounding green spaces with White Rose Forest, and noted that no reserve schemes could progress in the current programme.

Why

Further work on scheme 19 was paused to ensure that the programme being delivered meets the expected outcomes.

The consultation information supports the expected outcomes and shares York's knowledge while promoting inclusive and accessible play to interested parties and partners.

Tree planting was intended to enhance the local environment and green space enjoyment and contribute to the Council's tree planting ambitions. Reserve schemes could not progress because the scale of expenditure required was outside what was currently available.

What happens next

Deliver the approved tree planting programme across the Council's play areas and immediate surrounding green spaces with White Rose Forest.

Continue using the PIF play area consultation findings to inform play area requirements.

Keep further work on scheme 19 paused and do not progress reserve schemes during the current programme.

The money

  • 500k Parks Investment Fund scheme approval Report P1

Options considered

  • Chosen: Pause further work on scheme 19 Bachelor Hill Tenant Road steps. To ensure that the programme being delivered meets the expected outcomes.
  • Chosen: Approve tree planting for the Council's play areas and immediate surrounding green spaces with White Rose Forest. To enhance the local environment and green space enjoyment and contribute to the Council's tree planting ambitions.
  • Rejected: Progress reserve schemes within the current programme. The scale of expenditure required is outside the scope of what is currently available.

Implications

  • Financial: Funding adjustments for each scheme were noted in Annex 1.
  • Financial: No reserve scheme can progress in the current programme because the expenditure required is outside the currently available scope.
  • Climate: Tree planting is intended to enhance the local environment, support green space enjoyment and contribute to the Council's tree planting ambitions.
  • Equalities: The Council intends to share York's knowledge and promote inclusive and accessible play to interested parties and partners.
  • Risk: Further work on scheme 19 is paused to ensure that the programme meets the expected outcomes.
  • Other: PIF play area consultation findings were already being used to inform play area requirements.
  • Other: Significant progress on the approved programme had begun to bring benefits.

Who and where

  • People using the Council's play areas and immediate surrounding green spaces
  • Interested parties and partners involved in inclusive and accessible play
  • People benefiting from the approved programme of work
  • White Rose Forest, as tree planting collaborator

Timeline

  • 7 October 2025: An earlier Executive meeting approved the 500k Parks Investment Fund scheme. Report P1
  • 2026-10-06: City of York Council's Executive noted progress, paused scheme 19 and approved tree planting.

Plain English for the jargon

  • PIF: Parks Improvement Fund
  • IMD: Indices of Multiple Deprivation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item41

Resolved

Resolved (unanimously) that Executive: i. Noted that significant progress had been made on the approved programme of work and the benefits this had already started to bring. ii. Noted the adjustments to funding for each scheme as set out in Annex 1. iii. Paused further work on scheme 19 Bachelor Hill Tenant Road steps. Reasons: To ensure that the programme being delivered meets the expected outcomes. iv. Noted the findings from the PIF play area consultation and that this information was already being used to inform play area requirements. Reason: To ensure that the programme being delivered meets the expected outcomes and to share York’s knowledge and promote the value of inclusive and accessible play to a wide range of interested parties and partners. v. Approved a tree planting programme for the Council’s play areas and immediate surrounding green spaces in collaboration with White Rose Forest. Reason: To both enhance the local environment and use enjoyment of the green spaces, and to contribute to the Councils tree planting ambitions. vi. Noted that it was not possible to progress any of the reserve schemes within the current programme. Reason: The scale of expenditure required is outside the scope of what is currently available
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Meeting: Executive Meeting date: 6 October 2026 Report of: Dave Atkinson, Director of Environmental and Regulatory Services Portfolio of: Councillor Jenny Kent, Executive Member for Environment and Climate Emergency

Parks Investment Fund – progress report Subject of Report

1. In October 2025 Executive approved a major investment programme into the Councils parks, play areas and green spaces - PIF for short. The programme consisted of 19 approved schemes and a further 5 possible schemes which required additional investigation to establish cost and feasibility.

2. Executive is now being provided with an update on the programme and asked to:

a) Note that significant progress has been made on the approved programme of work and the benefits this has already started to bring. b) Note the adjustments to individual scheme funding. c) Pause any further work on scheme 19 Bachelor Hill Tenant Road steps. d) Note the findings from the PIF play area consultation and that this information is already being used to inform play area requirements. e) Approve a tree planting programme for the Councils play areas and immediate surrounding green spaces in collaboration with White Rose Forest. f) Note that it is not possible to progress any of the reserve schemes within the current programme.

These decisions will allow officers to complete the delivery of the work programme Benefits and Challenges

3. The benefits and challenges to this programme of investment are the same as those previously reported to Executive in October 2025 and include:

 Improving our communities and ensure that residents can enjoy accessible parks, play areas, and green spaces fit for all.  Supporting our Pride in Place values - of community wellbeing, encouraging more people of all ages and abilities to spend time outdoors.  Accessible and sustainable outdoor environments that enhance biodiversity, wellbeing, and social inclusion.  Encourage our communities to help with the ongoing and future involvement in York’s green spaces

4. The biggest challenge that was identified in October 2025 was capacity within the current workforce to deliver this greatly expanded investment programme. This problem was addressed through the appointment of project manager who will be in place until 30 April 2027.

Policy Basis for Decision

5. The programme of work supports two of the Council’s Core commitments:

Equalities and Human Rights - Equality of opportunity. We will create opportunities for all, providing equal opportunity and balancing the human rights of everyone to ensure residents and visitors alike can benefit from the city and its strengths.

Health - Health and wellbeing - We will improve health and wellbeing and reduce health inequalities. Scheme selection

6. To define the work programme weighted criteria was used in order of significance:

 First - Indices of Multiple Deprivation (IMD) levels. Those green spaces and play areas in higher IMD areas the greater the need for investment

 Second - Investment into play areas. Play areas with older equipment score higher

 Third - Key infrastructure - the poorer the condition of the asset the greater the score

 Fourth equal - projects

o which support the expansion and retention of Green Flag Award standard. o Projects which have or have the potential for 3rd party funding contributions.

Programme of work

7. Application of the above criteria established a programme of work

Site Scheme features

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 8: Parks Investment Fund: progress report: Annex 1Appendix 245 KB Download
PDF
Item 8: Parks Investment Fund: progress report: Annex 2Appendix 262 KB Download
PDF
Parks Investment Fund: progress report (4:45pm)Report 490 KB DownloadRead as text
PDF
View as HTML (41./2) 94 KBAppendix 94 KB Copy on its way
PDF
View as HTML (41./3) 61 KBAppendix 61 KB Copy on its way
PDF
View item 41. as HTML 112 KBReport 112 KB Copy on its way

At this meeting

Whole meeting

Who was there

9 of 9 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneCommittee Member, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbVice-Chair, present
DM
Councillor Dave MerrettCommittee Member, present
AP
Councillor Anna PerrettCommittee Member, present

On this subject at York

Search all
  1. Parks Investment Fund - progress report (4:45pm)This decision
  2. £500k Parks Investment Fund – Scheme ApprovalAgreed
  3. Parks Investment Fund (17:40)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open