Week 3524 to 30 August 20267 decisions
Medway Council: the week24 to 30 August 2026 · 2 meetings · 7 decisions
Week 35

Medway's Planning Committee refused outline plans for up to 100 homes on greenfield land at Buckland Road and Higham Road, Cliffe, and an HMO conversion at 4 Barnsole Road, Gillingham, but approved 16 dwellings on Longhill Avenue subject to Section 106 contributions. Cabinet approved a £612,713 reallocation from the Rivermead project to Danecourt Secondary and recommended adding £5 million, £400,000 and £220,000 from the 2026/27 High Needs Capital Allocation to three school projects. Cabinet also awarded the Danecourt pre-construction contract to Morgan Sindall and agreed to start procuring a repairs and maintenance contract covering temporary accommodation and hostels.

7decisions
approved in contracts
0deferred
2meetings next week

Decided

26 Aug
Land at Buckland Road and Higham Road Cliffe

The Planning Committee refused outline planning permission for up to 100 residential dwellings on land at Buckland Road and Higham Road, Cliffe, citing conflict with the development plan's spatial strategy.

Refused
25 Aug
School Place Planning Strategy annual review

Cabinet approved reallocating £612,713 from the Rivermead project to Danecourt Secondary, and recommended adding £5 million, £400,000 and £220,000 from the 2026/27 High Needs Capital Allocation to three school projects.

Approved
26 Aug
4 Barnsole Road Gillingham HMO

The Planning Committee refused a change of use at 4 Barnsole Road, Gillingham, from a dwellinghouse to a six-bedroom HMO, citing undersized bedrooms and poor outlook.

Refused
26 Aug
Longhill Avenue 16 dwellings construction

The Planning Committee approved construction of 16 dwellings on Longhill Avenue, subject to a Section 106 agreement securing contributions including £58,213.60 for green space and £101,664.68 for education.

Approved
25 Aug
Repairs and maintenance contract procurement

Cabinet agreed to start procuring a repairs and maintenance contract covering general fund Temporary Accommodation, One Medway Lettings and Inspiring Change LA Hostels, including the Sanctuary Scheme.

Agreed
25 Aug
Danecourt pre-construction contract award

Cabinet agreed to award the Danecourt Secondary pre-construction and design development contract to Morgan Sindall, citing identified savings in cost and lead times.