Medway Cabinet awarded a £25.9 million substance misuse contract to The Forward Trust and approved over £8.1 million in school capital funding, including £5 million for Danecourt SEND secondary. It also agreed a repairs contract worth up to £9 million and noted forecast overspends of £4.2 million on interest and £290,000 on fostering placements.
What the committee will consider, in order, with every paper attached to its item. Council Plan Performance Monitoring Report and Strategic Risk Summary – Quarter 1 2026/27 is the main business.
A period of 20 minutes is set aside for questions received.
Decision: 118/2026 The Cabinet approved the reallocation of the £612,713 underspend from the Rivermead project to the Danecourt Secondary project, as set out in paragraph 9.8 of the report. 119/2026 The Cabinet recommended to Council the addition of £5 million from the 2026/27 High Needs Capital Allocation to the Danecourt secondary project, as set out in paragraph 9.4 of the report. 120/2026 The Cabinet recommended to Council the addition of £400,000 from the 2026/27 High Needs Capital Allocation to the... Decision page
Decision: The Cabinet noted the comments made by the Children and Young People Overview and Scrutiny Committee, as set out in the addendum report. The Cabinet noted the contents of the Annual Fostering Report 2025–2026 and the Annual Private Fostering Report for 2025–2026, attached at Appendices 1 and 2 to the report respectively. Reasons: The National Minimum Standards for Fostering (2011) require that Fostering Agencies report the activity of the fostering service to its governing bodies. Decision page
Decision: The Cabinet noted the comments made by the Children and Young People Overview and Scrutiny Committee, as set out in the addendum report. The Cabinet noted the annual report as set out at Appendix 1, which outlined the activity that had taken place across Adoption Partnership South East between April 2025 - March 2026. Reasons: Statutory guidance requires adoption agencies to report on adoption agency activity in the previous year. Decision page
Decision: The Cabinet noted the comments of the Audit Committee, as set out in section 7 of the report. The Cabinet noted the treasury management report 2026/27 quarter 1. Reasons: In accordance with the Chartered Institute of Public Finance Accountancy’s (CIPFA) Code of Practice for Treasury Management, there should be a report on treasury every quarter. Decision page
Decision: The Cabinet noted the Quarter 1 2026/27 progress of the performance indicators used to monitor progress of the Council’s priorities, as set out in Appendix 1 to the report. 128/2026 The Cabinet agreed the Strategic Risk Summary, as set out in Appendix 2 to the report. Reasons: Regular monitoring of performance and risks by management and Members is best practice and ensures achievement of corporate objectives. Decision page
Decision: 129/2026 The Cabinet agreed to the commencement of the procurement of a repairs and maintenance contract for general fund Temporary Accommodation, LA Hostel and One Medway Lettings for Housing Needs. This included One Medway - Inspiring Change LA Hostels, HRA work as required and MDC properties in Medway; also, to include requirement for the contractor to fulfil requirements for the Sanctuary Scheme. Reasons: The recommendation for procuring this service has been made as it is the most... Decision page
Decision: 130/2026 The Cabinet agreed to award the contract to Morgan Sindall as they had been evaluated as the most economically advantageous against the consultants control option and award criteria as per the evaluation spreadsheet contained within 3.1 of the Exempt Appendix. Reasons: The construction company has identified significant savings that can be achieved in financial and lead times. This is evidenced in their proposals and is achieved via the following: Supply chain efficiencies, economies... Decision page
Decision: 131/2026 The Cabinet agreed to award the contract to The Forward Trust, as they had been evaluated as the most advantageous against the Council’s award criteria as per the evaluation spreadsheet attached at Exempt Appendix 2 to the report. Decision page
Item 10 is where most of this meeting's papers sit: 3 papers, about 19 MB.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 26 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 4 August 2026. 8 of its items lead into this meeting; 6 items are new. Point at any item to follow a thread. Procedural items are left out.
Activity of the HRA Governance Group, Private Sector Licensing (Additional & Selective Licensing Schemes), Provision for Gypsy and Traveller Accommodation, Climate Change Action Plan 2025-2028: Year 1 (January - December 2025) Update and 6 more do not return this time.
See the 4 August meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Medway, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.