The Joint Strategic Committee i ) noted the outturn position for 2018/19, ii) recommended that Adur District Council at its Council meeting on 18 July 2019: a. Note the overall capital final outturn for 2018/19. b. Agree the net carry over of General Fund Capital underspends for Adur District Council as detailed in paragraph 5.4. c. Approve the financing of the Adur District Council 2018/19 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.1 and 5.2. d. Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. and summarised in paragraph 5.6. e. Approve the use of capital receipts to fund redundancy costs associated with the Environmental Services restructure and the resulting Capital Flexibilities Strategy as detailed in paragraph 5.3. iii) recommended that Worthing Borough Council at its Council meeting on 23 July 2019: a. Note the overall capital final outturn for 2018/19. b. Agree the net carry over of General Fund Capital underspends for Worthing Borough Council as detailed in paragraph 5.10. c. Approve the financing of the Worthing Borough Council 2018/19 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.7 and 5.8. d. Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. And to fund a contingency budget as detailed in paragraph 5.13 and summarised in paragraph 5.14. e. Approve the use of capital receipts to fund redundancy costs associated with the Environmental Services restructure and the resulting Capital Flexibilities Strategy as detailed in paragraph 5.9.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report outlines the financial monitoring position for the end of the 2018/19 financial year for capital schemes included in the capital programmes of the Joint Strategic Committee, Adur District Council and Worthing Borough Council.
1.2Information is also provided in respect of capital receipts for the 2 constituent authorities.
1.3The following appendices have been attached to this report:
Appendix 1: Adur District Council Outturn Summary Appendix 2: Worthing Borough Council Outturn Summary Appendix 3: Adur District Council Sale Proceeds Appendix 4: Worthing Borough Council Sale Proceeds
Recommendations
2.1The Joint Strategic Committee is asked:
i) Note the outturn position for 2018/19 ii) To recommend that Adur District Council at its Council meeting on 18th July 2019: (a) Note the overall capital final outturn for 2018/19. (b) Agree the net carry over of General Fund Capital underspends for Adur District Council as detailed in paragraph 5.4. (c) Approve the financing of the Adur District Council 2018/19 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.1 and 5.2. (d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. and summarised in paragraph 5.6. (e) Approve the use of capital receipts to fund redundancy costs associated with the Environmental Services restructure and the resulting Capital Flexibilities Strategy as detailed in paragraph 5.3.
iii) To recommend that Worthing Borough Council at its Council meeting on 23rd July 2019: (a) Note the overall capital final outturn for 2018/19. (b) Agree the net carry over of General Fund Capital underspends for Worthing Borough Council as detailed in paragraph 5.10. (c) Approve the financing of the Worthing Borough Council 2018/19 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.7 and 5.8. (d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed in paragraph 4.2.2. And to fund a contingency budget as detailed in paragraph 5.13 and summarised in paragraph 5.14. (e) Approve the use of capital receipts to fund redundancy costs associated with the Environmental Services restructure and the resulting Capital Flexibilities Strategy as detailed in paragraph 5.9.
3. CONTEXT
3.1The monitoring of capital budgets has been reported to the Joint Strategic Committee three times during the year.
3.2In accordance with the Councils’ Capital Strategy, the Joint Capital Working Group oversees the development, implementation and progress of both Councils’ Capital Investment Programmes. 3.3 Full summaries of the outturn of all the schemes in the 2018/19 Capital Investment Programmes are available from the Councils’ Joint Intranet and highlight:
Schemes not progressing satisfactorily or where there are Red financial issues Schemes where progress is being closely monitored Amber Schemes progressing well Green Schemes where progress is beyond officers’ control ◘ Schemes with financial issues £ Schemes where progress has improved ⇧ Schemes where progress has deteriorated ⇩
4. 2018/19 Outturn
4.1Overall performance against the programme can be summarised as follows:
Capital Outturn - Summary of Progress: Adur Worthing Status
Schemes where the Councils have experienced significant challenges or where 6 4 Red financial issues have been identified Schemes where progress is being closely 21 24 Amber monitored Schemes progressing well 12 18 Schemes completed Green 18 19 Total Schemes: 57 65
4.2Successes and challenges in the 2018/19 programme
4.2.1 There has been a number of significant schemes delivered this year, with real and visible impact across our area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.