That the Joint Strategic Committee 1. noted the contents of the CBRE report set out at Appendix A; 2. agreed the work programme set out in paragraph Section 5 to procure a development partner for the site; 3. authorised the Head of Major Projects and Investments to continue with the Project as outlined and to enter into contracts for consultancy or advisory appointments which were necessary to progress the development, the costs of which would be met from the approved budget. Call In: The call-in deadline for this decision will be 5.00pm on 11 December 2020.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose ● To update members on recent progress on bringing forward Grafton Car Park for development and to set out a programme of work for 2021.
Recommendations
2.1To note the contents of the CBRE report set out at Appendix A
2.2To agree to the work programme set out in paragraph Section 5 to procure a development partner for the site.
2.3To authorise the Head of Major Projects and Investments to continue with the Project as outlined in this Report and to enter into contracts for consultancy or advisory appointments which are necessary to progress the development, the costs of which will be met from the approved budget? 3. Background & Context
3.1The redevelopment of the Grafton Car Park site is a key commitment contained within Platforms for our Places Going Further and an identified Area of Change in the Worthing Core Strategy (2010) and Emerging Worthing Local Plan.
3.2Due to its location, development of the site is a dual opportunity. Successful development will allow us to remove an existing unattractive property which is an unwelcome part of our seafront; provide modern commercial space to rejuvenate the western end of Montague Street; and will enable the delivery of new homes in a town centre location supporting the town centre economy over the long term. Furthermore, condition surveys of the existing multi-storey car park have established that the lifetime of the existing structure is coming to its end and there is therefore a financial and safety element that requires the project to make progress. Progress is therefore a necessity.
3.3Development of the site involves resolving a complex and complicated set of impediments and barriers that have historically prevented the site from coming forward. These issues are summarised in section 3 of the report . In the past the lack of understanding, knowledge, and early resolution of these issues have meant that nascent partnerships or sales of the site have failed. The focus of the development strategy over the last 18 months has been resolving these issues sufficiently to allow the marketing of the site to be successful.
3.4Along with the normal development issues that are common to most sites such as design, viability, access, and neighbour amenity issues, Grafton Car Park has a number of site specific challenges that need to be resolved to allow it to come forward. These include achieving vacant possession and dealing with the financial impact of this, title, access, rights to light, party wall issues, and right of access to adjoining properties.
3.4Learning from previous experience on this site, the approach of the Major Projects & Investment Team, has been to work proactively to understand and resolve as many of these issues as far as possible before going to secure a development partner for the site. The Council has commissioned the development arm of national property consultancy CBRE to work alongside officers to resolve each of these issues. Following an initial review in 2019, a programme of work was agreed which has been undertaken over the last year. A summary of progress against each of the key issues is contained in the Development Implementation and Delivery Options Report set out in Appendix A. Sufficient progress has now been made in understanding or addressing these issues to ensure that any process to attract a developer would have a chance of success, and allows us to move to the next phase of the project.
4. Development Delivery Approach
4.1Developing this fuller understanding of the challenges has informed our delivery strategy and approach for the site. A key aspect of CBRE’s commission was to provide advice on how best to successfully bring forward the development. Five options were considered:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.