Adur District Council / Worthing Borough Council
Joint Strategic Committee, Wednesday 17 July 2024 at 6.30pm

Construction Contract Award - Victoria Road, Worthing

Noted Committee 1 paper

Joint Strategic Committee noted this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemJSC/18/24-25

Resolved

1) That the updated financial modelling undertaken by the Delivery team following fixed fee tender returns and grant receipt be noted, and it be further noted the viability of the Victoria Road scheme as a spend to save initiative. 2) That the final costs of the scheme of £3,497,457 (to include professional fees, construction and contingency) funded through Prudential borrowing and central government grant be approved. 3) That the award of the Main Works contract to Sunninghill Construction Company Ltd following the competitive tendering process undertaken earlier this year be approved. Call In: The call-in deadline for the decisions will be 5.00pm on 29 July 2024
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose

1.1The Victoria Road Housing Scheme and its budget was originally approved at Worthing JSC on 7 June 2022. Planning permission for the scheme was granted in April 2023 and demolition of the vacant Air Cadet portacabins took place in July 2023, funded by a grant from the Brownfield Land Release Fund, in preparation for the site’s future redevelopment.

1.2Since then, the project has been awarded grant funding from Homes England of £770,000 and the Development Team has invited tenders from contractors to deliver the scheme. The viability of the project has also been reassessed following this tender exercise.

1.3In accordance with the recommendation contained in para 2.5 of the original report, this report has been prepared in order for the Committee to review the final costs and viability of the scheme, approve the virement of Homes England grant into the scheme’s budget, and approve the appointment of the preferred contractor to deliver the Main Works package. 2. Recommendations 2.1 To note the updated financial modelling undertaken by the Delivery team following fixed fee tender returns and grant receipt, and to note the viability of the Victoria Road scheme as a spend to save initiative. 2.2 To approve the final costs of the scheme of £3,497,457 (to include professional fees, construction and contingency) funded through Prudential borrowing and central government grant. 2.3 To approve the award of the Main Works contract to Sunninghill Construction Company Ltd following the competitive tendering process undertaken earlier this year.

3. Context

3.120-22 Victoria Road in Worthing is owned by Worthing Borough Council and was a former Air Cadet Headquarters comprising two small single storey portacabins with hardstanding on a 0.3 acre site. The site has been empty since May 2022, when the South East Reserve Forces & Cadet Association vacated their premises and handed it back to the Council, due to their declining membership.

3.2The principle of the site being developed into Temporary Accommodation (TA) was accepted by Joint Strategic Committee in June 2022, when Members approved this as the Preferred Option. The decision taken at that time was informed by a comprehensive analysis of temporary housing demand and costs, and guided by the Council’s housing delivery targets. Since then, the demand for TA has increased by 233% from 215 households in April 2021, to 502 households in April 2024, which, alongside the increasing costs of alternatives, makes the argument for scheme delivery even stronger.

3.3Following the scheme’s budget approval by Members in June 2022, ECE Architects were appointed to progress the design from feasibility stage through to the submission of a planning application (RIBA Stages 1-3). The scheme of 11 one and two bedroom flats was granted planning permission in April 2023 and has been specifically designed by ECE to target the Passivhaus standard, a whole-building approach to delivering high levels of comfort for occupants using very little energy for heating and cooling. The key drivers for the Council in adopting Passivhaus design principles were: ● Addressing the climate emergency – Passivhaus buildings are likely to consume around 80% less energy for heating ● Excellent thermal comfort in both summer and winter ● Improved indoor air quality (IAQ) ● Lower maintenance costs

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Construction Contract Award: Victoria Road, WorthingAgenda 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxChair, present
CB
Councillor Caroline BaxterWorthing Member, absent
ÖB
Councillor Ödül BozkurtWorthing Member, absent
RG
Councillor Rita GarnerWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
JH
Councillor Jude HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present

All 13 on the meeting page

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies