Financial Performance 2023/24 - Capital and Projects Outturn

Noted Committee 1 paper

Joint Strategic Committee noted this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemJSC/10/24-25

Resolved

Decision 1) That the outturn position for 2023/24 be noted 2) That it be recommend that Adur District Council at its Council meeting on 18th July 2024: a. Note the overall capital final outturn for 2023/24. b. Agree the net carry over of General Fund Capital underspends for Adur District Council as detailed in paragraphs 5.4. c. Approve the financing of the Adur District Council 2023/24 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.1, 5.2 and 5.3 d. Approve the carry forward of Council resources underspends to fund an increased contingency as reviewed in 5.6 and summarised in paragraph 5.7. 3) To recommend that Worthing Borough Council at its Council meeting on 23rd July 2024: a. Note the overall capital final outturn for 2023/24. b. Agree the net carry over of General Fund Capital underspends for Worthing Borough Council as detailed in paragraph 5.11. c. Approve the financing of the Worthing Borough Council 2023/24 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.8, 5.9 and 5.10 d. Approve the carry forward of Council resources underspends to fund budget pressures as detailed paragraph 4.5.2 and reviewed in 5.13 with a summary in paragraph 5.14. 4) That the release of funding for schemes which had been added to the programme following cabinet approval in February 2024 and do not require the use of capital resources as detailed in 5.16 and 5.17 be approved 5) That the amendment to the Worthing Borough Council 2024/25 capital programme be approved, as set out in section 5.18 of the report. To include the budget for Colonnade House to match the grant funding and the correction to the requirement of funding from prudential borrowing. Call In: The call-in deadline for the decisions will be 5.00pm on 29 July 2024. There are no call-ins for recommendations to Council
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose

1.1This report outlines the financial monitoring position for the end of the 2023/24 financial year for capital schemes included in the capital programmes of the Joint Strategic Committee, Adur District Council and Worthing Borough Council.

1.2Information is also provided in respect of capital receipts for the 2 constituent authorities.

1.3The following appendices have been attached to this report:

Appendix 1: Adur District Council Outturn Summary Appendix 2: Worthing Borough Council Outturn Summary Appendix 3: Adur District Council Capital Receipts Appendix 4: Worthing Borough Council Capital Receipts

Recommendations

2.1The Joint Strategic Committee is asked:

i) Note the outturn position for 2023/24 ii) To recommend that Adur District Council at its Council meeting on 18th July 2024: (a) To note the overall capital final outturn for 2023/24. (b) Agree the net carry over of General Fund Capital underspends for Adur District Council as detailed in paragraphs 5.4. (c) Approve the financing of the Adur District Council 2023/24 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.1, 5.2 and 5.3 (d) Approve the carry forward of Council resources underspends to fund an increased contingency as reviewed in 5.6 and summarised in paragraph 5.7.

iii) To recommend that Worthing Borough Council at its Council meeting on 23rd July 2024: (a) Note the overall capital final outturn for 2023/24. (b) Agree the net carry over of General Fund Capital underspends for Worthing Borough Council as detailed in paragraph 5.11. (c) Approve the financing of the Worthing Borough Council 2023/24 Capital Investment Programme, including the use of capital receipts as set out in paragraphs 5.8, 5.9 and 5.10 (d) Approve the carry forward of Council resources underspends to fund budget pressures as detailed paragraph 4.5.2 and reviewed in 5.13 with a summary in paragraph 5.14.

iii) To approve the release of funding for schemes which have been added to the programme following cabinet approval in February 2024 and do not require the use of capital resources as detailed in 5.16 and 5.17.

iiii) To approve the amendment to the Worthing Borough Council 2024/25 capital programme as set out in section 5.18 of the report. To include the budget for Colonnade House to match the grant funding and the correction to the requirement of funding from prudential borrowing.

3. CONTEXT

3.1The monitoring of capital budgets has been reported to the Joint Strategic Committee sub-commitees three times during the year.

3.2In accordance with the Councils’ Capital Strategy, the Joint Capital Working Group oversees the development, implementation and progress of both Councils’ Capital Investment Programmes. 3.3 Full summaries of the outturn of all the schemes in the 2023/24 Capital Investment Programmes are available from the Councils’ Intranet and highlight:

Schemes not progressing satisfactorily or where there are Red financial issues Schemes where progress is being closely monitored Amber Schemes progressing well Green Schemes where progress is beyond officers’ control # Schemes with financial issues £ Schemes where progress has improved ⇧ Schemes where progress has deteriorated ⇩

4. 2023/24 Outturn

4.1Overall performance against the programme can be summarised as follows:

Capital Outturn - Summary of Progress: Adur Worthing Status

Schemes where the Councils have experienced significant challenges or where Red financial issues have been identified - 1

Schemes where progress is being closely 3 10 Amber monitored Schemes progressing well 60 81 Schemes completed Green 19 17 Total Schemes: 82 109

4.2Successes in the 2023/24 programme

4.2.1 A number of significant schemes have been delivered this year, with real and visible impact across our area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Performance 2023/24: Capital and Projects OutturnReport 944 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxChair, present
CB
Councillor Caroline BaxterWorthing Member, absent
ÖB
Councillor Ödül BozkurtWorthing Member, absent
RG
Councillor Rita GarnerWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
JH
Councillor Jude HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Financial Performance 2023/24 - Capital and Projects OutturnThis decision
  2. Financial Performance 2025/26 - Revenue outturnNoted
  3. Financial Performance 2025/26 - Capital and Projects OutturnNoted
  4. Financial Performance 2024/25 - Revenue outturnNoted
  5. Financial Performance 2024/25 - Capital and Projects OutturnNoted
  6. Financial Performance 2023/24 - Revenue OutturnApproved

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open