Adur District Council / Worthing Borough Council
Joint Strategic Committee, Wednesday 17 July 2024 at 6.30pm

Albion Street Update

Noted Committee 1 paper

Joint Strategic Committee noted this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemJSC/17/24-25

Resolved

1) That the anticipated net increase in costs, and that the impact on scheme viability is that it still achieves the necessary financial targets be noted. 2) To approve the virement of an additional budget of £994,411 to enable the project at Albion Street to be completed. To vire £841,050 from existing budgets for the small sites programme, not currently committed to schemes. The remaining £153,361 is to be vired from capital budgets remaining from projected underspends for sites; Wilmot Road, Daniel Close and Gravelly Crescent. 3) That authority be delegated to the Director For Housing and Communities to enter into all necessary contracts and associated legal documentation to enable the project to progress through the remaining construction phase to completion Call In: The call-in deadline for the decisions will be 5.00pm on 29 July 2024
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose 1.1. The report sets out the latest position on the Albion Street new build project and seeks approval of additional funds to support its delivery.

1.2The main contractor became insolvent in August 2023 and a completion contract is underway however the cost to complete is higher than anticipated and an additional budget is required to complete the work.

1.3The report sets out the background to the project, the latest position on costs and likely completion programme and sets out the financial implications for the Council.

Recommendations

2.1To note the anticipated net increase in costs, and that the impact on scheme viability is that it still achieves the necessary financial targets.

2.2To approve an additional budget of £994,411 to enable the project at Albion Street to be completed. 2.3. To delegate authority to the Director For Housing and Communities to enter into all necessary contracts and associated legal documentation to enable the project to progress through the remaining construction phase to completion

3. Context

3.1The contract for the construction of the 49 flats for affordable rented housing was terminated in September 2023 following the insolvency of the main contractor, Westridge Construction. Although work on the buildings was around 90% complete at this point, there is substantial work left to do to complete cladding, balconies and external works, as well as completing the internal fit out and mechanical and electrical installations. Deterioration of the building as a result of leaks and spread of condensation while the buildings have been vacant has exacerbated the position.

3.2The cost to complete the buildings will substantially exceed the originally approved scheme budget and has increased since the initial assessment of what is required due the extent of defective and incomplete work now identified.

3.3Now that a fuller assessment of the work required to complete the project has been undertaken, it is clear that an additional budget of £994,411 is required to complete the project in addition to that already approved.

4. Issues for Consideration

4.1Project Background

4.1.1. The Albion Street project will provide 49 affordable rented flats in 2 blocks funded through a mix of Homes England funding, Right to Buy receipts, S106 contributions and capitalised rental income.

4.1.2. The building contract was let to Westridge Construction following a competitive tender process, and work started on site in March 2021. The project was delayed by Covid restrictions, together with bad weather and drainage connection issues, and there was overall slow progress from the contractor who encountered a range of technical problems delivering this complex building. Part of the delay was considered to be ‘no fault’ due to a range of factors including poor weather, Covid impacts and delays by statutory authorities, and an extension time was granted to December 2022. This means that no damages applied to that period. However damages for late completion were being deducted from payments at the point the contract was terminated.

4.1.3. Westridge had planned to complete the project in October 2023 however it was doubtful this would be achieved. They became insolvent in August 2023 and the building contract was terminated on 28th September 2023.

4.1.4. A report was considered by the Adur Joint Strategic Sub-Committee on 1st February 2024 which set out the initial assessment of the position with the plan for procurement of a completion contract, and included an assessment of costs to complete. Members approved the virement of a budget of £1.776m of which it was anticipated £998k would be claimed from insurers under an insolvency bond leaving a net figure of £778,000.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Albion Street UpdateAgenda 190 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxChair, present
CB
Councillor Caroline BaxterWorthing Member, absent
ÖB
Councillor Ödül BozkurtWorthing Member, absent
RG
Councillor Rita GarnerWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
JH
Councillor Jude HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Albion Street UpdateThis decision
  2. Albion Street Housing Scheme Update ReportApproved
  3. Adur Homes - Albion Street UpdateNoted
  4. Approval of budget to complete Albion Street housing developmentApproved
  5. Adur Homes Development Programme - Albion Street and Cecil Norris HouseAgreed

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies