1) That the anticipated net increase in costs, and that the impact on scheme viability is that it still achieves the necessary financial targets be noted. 2) To approve the virement of an additional budget of £994,411 to enable the project at Albion Street to be completed. To vire £841,050 from existing budgets for the small sites programme, not currently committed to schemes. The remaining £153,361 is to be vired from capital budgets remaining from projected underspends for sites; Wilmot Road, Daniel Close and Gravelly Crescent. 3) That authority be delegated to the Director For Housing and Communities to enter into all necessary contracts and associated legal documentation to enable the project to progress through the remaining construction phase to completion Call In: The call-in deadline for the decisions will be 5.00pm on 29 July 2024
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose 1.1. The report sets out the latest position on the Albion Street new build project and seeks approval of additional funds to support its delivery.
1.2The main contractor became insolvent in August 2023 and a completion contract is underway however the cost to complete is higher than anticipated and an additional budget is required to complete the work.
1.3The report sets out the background to the project, the latest position on costs and likely completion programme and sets out the financial implications for the Council.
Recommendations
2.1To note the anticipated net increase in costs, and that the impact on scheme viability is that it still achieves the necessary financial targets.
2.2To approve an additional budget of £994,411 to enable the project at Albion Street to be completed. 2.3. To delegate authority to the Director For Housing and Communities to enter into all necessary contracts and associated legal documentation to enable the project to progress through the remaining construction phase to completion
3. Context
3.1The contract for the construction of the 49 flats for affordable rented housing was terminated in September 2023 following the insolvency of the main contractor, Westridge Construction. Although work on the buildings was around 90% complete at this point, there is substantial work left to do to complete cladding, balconies and external works, as well as completing the internal fit out and mechanical and electrical installations. Deterioration of the building as a result of leaks and spread of condensation while the buildings have been vacant has exacerbated the position.
3.2The cost to complete the buildings will substantially exceed the originally approved scheme budget and has increased since the initial assessment of what is required due the extent of defective and incomplete work now identified.
3.3Now that a fuller assessment of the work required to complete the project has been undertaken, it is clear that an additional budget of £994,411 is required to complete the project in addition to that already approved.
4. Issues for Consideration
4.1Project Background
4.1.1. The Albion Street project will provide 49 affordable rented flats in 2 blocks funded through a mix of Homes England funding, Right to Buy receipts, S106 contributions and capitalised rental income.
4.1.2. The building contract was let to Westridge Construction following a competitive tender process, and work started on site in March 2021. The project was delayed by Covid restrictions, together with bad weather and drainage connection issues, and there was overall slow progress from the contractor who encountered a range of technical problems delivering this complex building. Part of the delay was considered to be ‘no fault’ due to a range of factors including poor weather, Covid impacts and delays by statutory authorities, and an extension time was granted to December 2022. This means that no damages applied to that period. However damages for late completion were being deducted from payments at the point the contract was terminated.
4.1.3. Westridge had planned to complete the project in October 2023 however it was doubtful this would be achieved. They became insolvent in August 2023 and the building contract was terminated on 28th September 2023.
4.1.4. A report was considered by the Adur Joint Strategic Sub-Committee on 1st February 2024 which set out the initial assessment of the position with the plan for procurement of a completion contract, and included an assessment of costs to complete. Members approved the virement of a budget of £1.776m of which it was anticipated £998k would be claimed from insurers under an insolvency bond leaving a net figure of £778,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.