Adur Homes Whole Block Repairs - Phase 1

Approved Committee 1 paper

Joint Strategic Committee approved this item on Tuesday 10 December 2024. Below is the council's own wording, with the papers it was decided on.

ItemJSC/61/24-25

Resolved

That the allocation of £5m from the previously approved Adur Homes Investment Programme budget for a ‘Whole Blocks’ repairs project be approved, covering ten existing Adur Homes blocks in phase 1, to include site investigations and professional fees; 2. That the multidisciplinary consultants be appointed to provide pre-contract services, site investigations and cost advice; 3. To commit to the principle of the repair and improvement of Adur Homes properties using a phased approach and Whole Block contracts, with one Principal Contractor where necessary. 4. That it be noted that the phase 1 blocks have been identified on the basis of existing, historic information and investigations, however the production of new building conditions surveys may identify further urgent works in other properties. Call In: The call-in deadline for decisions will be 5.00pm on 20 December 2024
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose

1.1As part of our Adur Homes Improvement Plan, officers have been developing a maintenance programme, which is a critical part of providing residents with decent homes.

1.2Ten existing Adur Homes blocks have been identified as requiring essential and urgent repairs.

1.3The Councils are asked to approve a contract with a main contractor to carry out multiple and varied repairs to the ten blocks.

1.4Following surveys carried out at Warren Court in Lancing, The ‘RAFA’ blocks and Aston House in Shoreham, essential repairs and remedial work is required across these blocks. For efficiency it is proposed that all the work is instructed under one contract with a Principal Contractor who will manage the subcontract packages of work, the sequencing and programming, together with the necessary resident liaison. 2. Recommendations

2.1Approve the allocation of £5m from the previously approved Adur Homes Investment Programme budget for a ‘Whole Blocks’ repairs project, covering ten existing Adur Homes blocks in phase 1, to include site investigations and professional fees.

2.2To appoint the multidisciplinary consultants to provide pre-contract services, site investigations and cost advice.

2.3To commit to the principle of the repair and improvement of Adur Homes properties using a phased approach and Whole Block contracts, with one Principal Contractor where necessary.

2.4To note that the phase 1 blocks have been identified on the basis of existing, historic information and investigations, however the production of new building conditions surveys may identify further urgent works in other properties.

3. Context

Adur Homes Investment Programme

3.1In November 2022, following the death of two-year-old Awaab Ishak in a damp and mouldy flat in Rochdale, the Government ordered Councils to check their housing stock. A subsequent review was undertaken into Adur Homes’ stock.

3.2Following this review, In February 2023 Adur District Council (ADC or ‘the Council’) referred itself to the Regulator of Social Housing (the Regulator), following the completion of its review. Since this time, ADC has been providing regular reports to the Regulator on the progress of the Adur Homes Improvement Programme, which also includes the investment in homes

3.3As a result of this, the team has been developing an investment programme for Adur Homes to cover the works required to maintain and improve our housing. As such, the overall Capital budget has been set at £19.3m for 2024/25 financial year and forecast for the next two years at £9m per year for 25/26 and 26/27 respectively.

3.4Budgets for the Adur Homes Investment Programme have been agreed for this financial year and forecast for the next two financial years. 3.5. Capital budgets have been identified for improvements to safety, security, accessibility and compliance with the Decent Homes standards, over the next three years.

4. Warren Court - Structural Reports

4.1Warren Court consists of four, three storey blocks, and is located on Sompting Road, close to Lancing railway station.

4.2In May 2020 ADC appointed Philip Goacher Associates, Structural Engineers to undertake a structural survey on the condition of existing communal walkways and private balconies, and their railings.

4.3The report provided by Philip Goacher Associates, issued in July 2020 identified numerous building defects as summarised below.

4.4In February 2024 ADC re-appointed Philip Goacher Associates to re-inspect the properties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Adur Homes Whole Block Repairs: Phase 1Report 209 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, absent
DF
Councillor Dom FordWorthing Member, absent
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Adur Homes Whole Block Repairs - Phase 1This decision
  2. Adur Homes Improvement Plan and Homes England AuditNoted
  3. Adur Homes Improvement Plan Phase TwoNoted
  4. Adur Homes - Albion Street UpdateNoted
  5. Adur Homes Readiness for Awaabs Law UpdateNoted
  6. Adur Homes UpdateNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies