That the allocation of £5m from the previously approved Adur Homes Investment Programme budget for a ‘Whole Blocks’ repairs project be approved, covering ten existing Adur Homes blocks in phase 1, to include site investigations and professional fees; 2. That the multidisciplinary consultants be appointed to provide pre-contract services, site investigations and cost advice; 3. To commit to the principle of the repair and improvement of Adur Homes properties using a phased approach and Whole Block contracts, with one Principal Contractor where necessary. 4. That it be noted that the phase 1 blocks have been identified on the basis of existing, historic information and investigations, however the production of new building conditions surveys may identify further urgent works in other properties. Call In: The call-in deadline for decisions will be 5.00pm on 20 December 2024
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1As part of our Adur Homes Improvement Plan, officers have been developing a maintenance programme, which is a critical part of providing residents with decent homes.
1.2Ten existing Adur Homes blocks have been identified as requiring essential and urgent repairs.
1.3The Councils are asked to approve a contract with a main contractor to carry out multiple and varied repairs to the ten blocks.
1.4Following surveys carried out at Warren Court in Lancing, The ‘RAFA’ blocks and Aston House in Shoreham, essential repairs and remedial work is required across these blocks. For efficiency it is proposed that all the work is instructed under one contract with a Principal Contractor who will manage the subcontract packages of work, the sequencing and programming, together with the necessary resident liaison. 2. Recommendations
2.1Approve the allocation of £5m from the previously approved Adur Homes Investment Programme budget for a ‘Whole Blocks’ repairs project, covering ten existing Adur Homes blocks in phase 1, to include site investigations and professional fees.
2.2To appoint the multidisciplinary consultants to provide pre-contract services, site investigations and cost advice.
2.3To commit to the principle of the repair and improvement of Adur Homes properties using a phased approach and Whole Block contracts, with one Principal Contractor where necessary.
2.4To note that the phase 1 blocks have been identified on the basis of existing, historic information and investigations, however the production of new building conditions surveys may identify further urgent works in other properties.
3. Context
Adur Homes Investment Programme
3.1In November 2022, following the death of two-year-old Awaab Ishak in a damp and mouldy flat in Rochdale, the Government ordered Councils to check their housing stock. A subsequent review was undertaken into Adur Homes’ stock.
3.2Following this review, In February 2023 Adur District Council (ADC or ‘the Council’) referred itself to the Regulator of Social Housing (the Regulator), following the completion of its review. Since this time, ADC has been providing regular reports to the Regulator on the progress of the Adur Homes Improvement Programme, which also includes the investment in homes
3.3As a result of this, the team has been developing an investment programme for Adur Homes to cover the works required to maintain and improve our housing. As such, the overall Capital budget has been set at £19.3m for 2024/25 financial year and forecast for the next two years at £9m per year for 25/26 and 26/27 respectively.
3.4Budgets for the Adur Homes Investment Programme have been agreed for this financial year and forecast for the next two financial years. 3.5. Capital budgets have been identified for improvements to safety, security, accessibility and compliance with the Decent Homes standards, over the next three years.
4. Warren Court - Structural Reports
4.1Warren Court consists of four, three storey blocks, and is located on Sompting Road, close to Lancing railway station.
4.2In May 2020 ADC appointed Philip Goacher Associates, Structural Engineers to undertake a structural survey on the condition of existing communal walkways and private balconies, and their railings.
4.3The report provided by Philip Goacher Associates, issued in July 2020 identified numerous building defects as summarised below.
4.4In February 2024 ADC re-appointed Philip Goacher Associates to re-inspect the properties.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.