That the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 7.2.1 and appendix 2 be noted; 2. That the Kingston Beach urgent virement be approved retrospectively as requested in 7.11; 3. That the virement of grant funding to Splashpoint GSHP project be approved as requested in 7.2.2; 4. That as at 6.3.1 that financial decisions in relation to Worthing Pier be considered as part of another report; 5. That the budget amendments to both the Adur District Council and Worthing Borough Council 2024/25 capital programmes detailed in appendix 3 be approved following the programme review referenced in sections 4.2, 4.3 and 4.4 of the report Call In: The call-in deadline for decisions will be 5.00pm on 20 December 2024
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report updates the Committee on the progress made on the delivery of the 2024/25 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme includes schemes which support the delivery of services by the Joint Services Committee.
1.2Included within the report is information about the prudential indicators which provide a link between the Councils’ revenue budget and capital budget. Quarterly monitoring of these indicators is a requirement of the prudential code.
1.2The following appendices have been attached to this report:
Appendix 1: Capital Monitoring Summary for Both Councils Appendix 2: Reprofiled Budgets for Worthing Borough Council Appendix 3: Programme Review for Both Councils 2. RECOMMENDATIONS
2.1The Joint Strategic Committee is asked to:
i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 7.2.1 and appendix 2.
ii) To approve Kingston Beach urgent virement retrospectively as requested in 7.11
iii) To approve the virement of grant funding to Splashpoint GSHP project as requested in 7.2.2
iv) To note, as at 6.3.1 that financial decisions in relation to Worthing Pier are to be considered in a separate report to this committee.
v) To approve the budget amendments to both the Adur District Council and Worthing Borough Council 2024/25 capital programmes detailed in appendix 3 following the programme review referenced in sections 4.2, 4.3 and 4.4 of the report.
3. CONTEXT
3.1In accordance with the Council’s Capital Strategy, the Capital Working Group oversees the implementation and progress of the Council’s capital investment programmes. The Capital Working Group also ensures that capital schemes are approved within financial regulations.
3.2The Capital Working Group monitors the programme’s progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Council’s control. Moving forward a Major Projects Board will have oversight of the capital programme and a new budget management group for assets has been established to review capital expenditure requests before commitment to spend.
3.3Full summaries of the progress of all the schemes in the 2024/25 Capital Investment Programmes are prepared each quarter.
3.4Financial Regulations require officers to report each project on completion.
4. Progression of the 2024/25 Capital Programme’s - Quarter 2
4.1This section of the report looks into the progression of the programme and highlights the current overview of the projects currently underway. By tracking this trajectory we can highlight issues with projects and be aware of schemes which require further support and monitoring. This information is supplied by project managers monthly, following updates on their expenditure from finance colleagues. Number of Percentage Adur District Council schemes % Schemes which have completed 5 6% Schemes which are progressing satisfactorily 73 88% Schemes where progress is being closely monitored 4 4.8% Schemes with significant challenges or financial issues 1 1.2%
Number of Percentage Worthing Borough Council schemes % Schemes which have completed 6 5.6% Schemes which are progressing satisfactorily 97 90.7% Schemes where progress is being closely monitored 3 2.8% Schemes with significant challenges or financial issues 1 0.9%
A summary of the financial movements of the 2024/25 Capital Investment Programme is attached as Appendix 1 to this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.