AI summaryJoint Strategic Committee approved a £1,272,193 package to redevelop Eastbrook Manor Community Centre, including an £841,143 Youth Investment Fund grant, naming Community People as the new operator for completion by September 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedYIF grant accepted, new tenant approved
Money£1,272,193 total virementCombined capital budget created
What happens nextConstruction from March 2026Site works begin, completion September 2026
Who it affectsEastbrook residents and usersYoung people 11-18 and community groups
What was decided
The committee accepted the £841,143 Youth Investment Fund grant and approved the creation of a capital programme budget for the scheme. Report P7, P55
Members agreed £431,050 from the existing capital programme for Eastbrook Manor, including £140,000 ring fenced for car park improvements. Report P8, P60
The committee approved Community People as the new operator and delegated authority to the Service Director for Place & Economy to sign the lease in line with agreed Heads of Terms. Report P10, P22, P45
Why
Eastbrook Manor Community Centre is in need of redevelopment, with tired buildings, an unsafe former MUGA and a wider national lack of youth provision identified by DCMS in 2022. Report 3.1, P13, P14
Three risks around the operating tenant, delivery deadlines and project scope have been mitigated, including appointing Community People as new tenant and securing a deadline extension. Report P22
Combining the YIF capital grant with existing council capital allows economies of scale and broader site improvements including car park, fencing and landscaping. Report P4, P23, P33, P36
What happens next
The Service Director for Place & Economy, with the Cabinet Member for Regeneration and Economy, will sign the grant agreement, award the construction contract and complete legal paperwork, subject to compliant procurement. Report P9, P51
Construction delivery is set for March 2026 with capital completion and Community People taking up operation both expected in September 2026. Report P27, P40
Youth provision will run for three years from grant agreement signature, and the grant will be monitored for up to ten years. Report P29, P40, P49
The money
£841,143 Youth Investment Fund capital grant Report P7, P55, P61
£50,000 Youth Investment Fund revenue, passported to new tenant Report P28, P30, P63
£291,050 Eastbrook Community Centre External Area Refurbishment from capital programme Report P32, P59
£140,000 Eastbrook Community Centre Car Park Resurfacing (currently named Fishersgate Car Park Resurfacing) Report P35, P60
£431,050 Total council capital programme allocation, includes £140,000 car park Report P8
£1,272,193 Total virement into new combined capital budget; the report also states £1,272,143 at paragraph 8.4 Report P58, P62
Options considered
Chosen: Accept YIF grant and combine with capital programme. Allows economies of scale and broader site improvements Report P4, P7, P23
Chosen: Approve Community People as new operator. Removes council from direct operation, secures FRI lease, mitigates tenant risk Report P10, P22, P45
Chosen: Delegate authority to Service Director for Place & Economy for contracts and lease. Enables timely procurement within the tight YIF timescales Report P9, P51
Implications
Financial: Combined Eastbrook Community Centre capital budget created by virement; any underspend on the car park project is to be returned to the capital programme. Report P37, P58, P62
Legal: Decisions rely on Section 111 Local Government Act 1972, Section 3 Local Government Act 1999 and s1 Local Government (Contracts) Act 1997; procurement must follow Contract Standing Orders and the Procurement Act 2023. Report 9.1, 9.2, 9.3, 9.4
Equalities: Enhanced facility will serve disability, elderly and community groups alongside the 11-18 youth cohort. Report P76, 2.2
Climate: Scheme will return green space to Fishersgate Recreational Ground, support biodiversity and use environmentally friendly methods and products in the capital works. Report P44, P82
Risk: GFA must be monitored for up to ten years; failure to deliver within the grant window could put funding at risk, and resource shortages may require externalisation. Report P49, P51
Staffing: Handing operation to Community People under an FRI lease releases council resources, while revenue funding supports youth work staff via the new tenant. Report P30, P45, P50
Other: Officers expect the youth interventions to act as a driver to reduce youth-related crime in and around Adur. Report P78
Who and where
Young people aged 11-18 in Eastbrook and wider Adur, including Southwick Report P14, P46, P48
Eastbrook Ward residents and Community People as the new operator Report 3.1, P22, P45
Existing community centre user groups, including disability, elderly and wider community groups Report P76
Local youth groups and businesses engaged in shaping the project Report P53
Timeline
January 2026: Internal governance confirmed Report P40
February 2026: Grant Funding Agreement and JCT signed and returned to funder Report P27, P40
5.00pm on 17 February 2026: Call-in deadline for the decision
March 2026: Delivery phase begins Report P40
September 2026: Community People operating out of Eastbrook Manor Community Centre and capital completion Report P40, P45
September 2026 to September 2029: Youth provision active using new MMC buildings Report P29, P40
Up to ten years from GFA: Grant funding agreement monitoring period Report P49
Plain English for the jargon
YIF: Youth Investment Fund, a DCMS capital and revenue fund for youth facilities
DCMS: Department for Culture, Media and Sport, the government department behind the YIF
MMC: Modern Method of Construction, used here for the two new modular buildings
GFA: Grant Funding Agreement between the council and the YIF funder
JCT: Joint Contracts Tribunal standard construction contract
EMCC: Eastbrook Manor Community Centre, the subject of this investment
MUGA: Multi Use Games Area, the former disused court being redeveloped
FRI lease: Full Repairing and Insuring lease, where the tenant takes on repair and insurance duties
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/103/25-26
Resolved
That acceptance of the Youth Investment Funding be authorised, and an increased total grant receipt of £841,143 to deliver the scheme as outlined in this paper, and approve the creation of a budget in the capital programme. 2. That it be agreed that £431,050 of the assigned capital programme (which includes £140,000 ring fenced for car park improvements) to Eastbrook Manor Community Centre to be used to deliver supplementary improvements to the centre as outlined in this paper 3. That authority be delegated to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to sign and complete the grant agreement and award the contract and complete the necessary legal documentation for the construction of the new buildings, and associated capital works, and the awarding of youth services contracts, subject to the outcome of compliant procurement processes and ensuring the work is within the approved budget. 4. That the successful bidder to operate the Eastbrook Manor Community Centre be approved and authority be delegated to the Service Director for Place & Economy authority to complete a lease in accordance with agreed Heads of Terms Call In: The call-in deadline for decisions will be 5.00pm on 17 February 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1 The purpose of this report is to update Members on the successful award from the Youth Investment Fund (YIF) for Eastbrook Manor Community Centre and provide rationale on the developments since the last report in December 2023.
1.2 To confirm the funding to be awarded from YIF and outline the project in the context of the capital and revenue implications. Both elements will serve to provide interventions for young people within the local community and across Adur.
1.3 In securing the YIF funding, outline the opportunity to combine existing capital funding (from the capital programme) to further enhance Eastbrook Manor through economies of scale.
1.4 To provide assurance that previous risks have been mitigated over the last 12 - 24 months to enable the delivery of this scheme to progress. And, as one of those mitigations, confirm the outcome of the Expression of Interest (EOI) process in seeking a new tenant for Eastbrook Manor Community Centre.
Recommendations
The Joint Strategic Committee is recommended to:
2.1. Authorise acceptance of the Youth Investment Funding, and an increased total grant receipt of £841,143 to deliver the scheme as outlined in this paper, and approve the creation of a budget in the capital programme.
2.2. To agree to £431,050 of the assigned capital programme (which includes £140,000 ring fenced for car park improvements) to Eastbrook Manor Community Centre to be used to deliver supplementary improvements to the centre as outlined in this paper.
2.3. Delegate authority to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to sign and complete the grant agreement and award the contract and complete the necessary legal documentation for the construction of the new buildings, and associated capital works, and the awarding of youth services contracts, subject to the outcome of compliant procurement processes and ensuring the work is within the approved budget.
2.4. Approve the successful bidder to operate the Eastbrook Manor Community Centre and delegate to the Service Director for Place & Economy authority to complete a lease in accordance with agreed Heads of Terms.
3. Background
3.1A vibrant hub in the heart of Eastbrook Ward, Eastbrook Manor Community Centre (EMCC) is the catalyst for community activity, support and opportunity for all. Currently operated by Adur District Council (ADC) with strategic input from a voluntary Community Centre Management Advisory Group, the centre provides classes, workshops, support services, educational services, community events, creative arts and social opportunities in an area scarce of community facilities. 3.2 The Centre excels in creating a safe space for the local community. However, it is in desperate need of support, both to continue and expand the current provision offered by the centre, whilst also developing the existing infrastructure.
3.3 With tired buildings on the periphery of the site, a disused and unsafe former MUGA, the site is in significant need of redevelopment to bring these areas back into use for the benefit of the community. Whilst the more significant need for EMCC and place is evidenced in national statistics around health and wellbeing, green space and youth provision.
3.4 In 2022, DCMS identified the lack in youth provisions nationally and created an opportunity for funding (totalling £368m over 3 years) eligible to places across England to expand and improve local youth facilities and their services. The aim of the YIF fund is to create 300 sustainable facilities that represent value for money, are environmentally sustainable and provide positive activities for young people aged 11-18.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.