MoneyCapital shortfall of £82,541Plus £1.629m full year revenue cost for 2026/27
What happens nextFood waste collections start September 2026Roll-out to begin after summer school holidays
Who it affectsNot stated
What was decided
The Committee noted the progress with implementing Simpler Recycling, in particular the planning for food waste collections. Report P5
The Committee noted the unavoidable delay to food waste collections, attributed to the late notice of government funding and longer than usual vehicle delivery times. Report P6, P70, P87
Why
The Government set out new domestic and non-domestic waste collection requirements under the Environment Act 2021 and Simpler Recycling, requiring weekly food waste collections from all domestic properties by March 2026. Report P2, P10
The councils face high demand for specialist food waste vehicles nationally, meaning the first eight 7.5 tonne vehicles ordered in June 2025 will not arrive until June or July 2026, and revenue funding was only confirmed in December 2025. Report P69, P85, P87
What happens next
Design of food waste collection rounds in January and February 2026, two further vehicles ordered, caddies received and recruitment campaign run between February and May 2026. Report P91, P92, P93
First vehicles delivered and communications signed off in June to July 2026, staff training and caddy distribution in August 2026, with collections starting in September 2026. Report P94, P95, P96, P97, P98, P99
The money
£940,117 Adur District Council Extended Producer Responsibility funding for 2025/26 Report P25
£961,808 Adur District Council Extended Producer Responsibility funding for 2026/27 Report P25
£1,790,800 Worthing Borough Council Extended Producer Responsibility funding for 2025/26 Report P26
£1,832,119 Worthing Borough Council Extended Producer Responsibility funding for 2026/27 Report P26
£507,870 DEFRA Capital Grant for Adur Report P62
£875,810 DEFRA Capital Grant for Worthing Report P62
£108,756 DEFRA Capital top up for Adur Report P63
£118,455 DEFRA Capital top up for Worthing Report P63
£211,625 DEFRA Implementation Grant for Adur Report P64
£296,598 DEFRA Implementation Grant for Worthing Report P64
£1,693,252 Total projected capital expenditure on food waste vehicles and caddies Report P74
£1,610,711 Total DEFRA Capital Grant received Report P75
£82,541 Capital shortfall met from the agreed capital programmes of both councils Report P76, P77
£507,863 Total implementation grant for project costs such as communications, training, caddy delivery Report P82, P111
£1,629,263 Projected full year revenue cost of the food waste service for 2026/27 Report P85, P108
Options considered
Chosen: 1-2-2 model: weekly food waste, two weekly refuse and two weekly recycling collections. Resolved by the Committee in July 2024 and confirmed again in this report Report P16, P56, P57
Rejected: 1-2-3 model: weekly food, fortnightly recycling and three weekly residual waste. Committee resolved in July 2024 to progress with the 1-2-2 model Report P56
Rejected: Move to single stream recycling collections. TEEP assessment concluded it is technically feasible but not economically viable Report P45
Rejected: Roll out food waste collections by the statutory March 2026 deadline. Not possible due to vehicle delivery times and late confirmation of revenue funding Report P87
Implications
Financial: The food waste service is estimated to cost £1.629m per year in revenue from 2026/27, with no ring-fenced government funding for ongoing costs. The MTFS is being updated to cover the full cost. Report P85, P108, P109
Financial: Capital expenditure of £1.693m exceeds the £1.611m DEFRA capital grant by £82,541, which is being met from the existing capital programmes of both councils. Report P74, P75, P76, P77, P110
Legal: The councils have a statutory duty under the Environment Act 2021 to provide weekly food waste collections from all domestic properties, but the roll-out will be after the March 2026 deadline. Report P10, P87, 7.1
Legal: Grant funding must be spent in line with the funding agreement and in a way that is compliant with the Subsidy Control Act 2022.
Equalities: The new service will offer assisted collections on the same basis as refuse and recycling services. Report P124
Climate: Food waste collections are expected to increase recycling rates by 5% to 7% and remove putrescible waste from the residual stream. The new fleet will run on hydrotreated vegetable oil. Report P69, P122, P131
Staffing: The new service is expected to employ 10 crews of three staff, providing up to 30 new jobs, with apprenticeships forming part of the recruitment campaign. Report P60, P80, P119
Risk: Future Extended Producer Responsibility funding levels are not guaranteed and are expected to fall as industry responds to incentives to reduce packaging. Markets for flexible plastics collected from 2027 remain uncertain. Report P28, P54
Who and where
Residents of Adur and Worthing who will receive weekly food waste collections starting from September 2026 Report P57, P88
Households in blocks of flats, who will use communal 140 litre food waste bins Report P58
1,760 active commercial customers, with 756 already recycling and 174 using the food waste service Report P41
Larger businesses already required to recycle, and micro businesses which will be required from 2027 Report P40
Existing 20,588 garden waste subscribers, whose service will continue unchanged Report P49
Up to 30 new collection crew staff to be recruited Report P60, P119
Timeline
2024: Initial reports to Joint Strategic Committee on Simpler Recycling and food waste Report P3, P11
July 2024: Committee agreed phased roll out using the 1-2-2 model and delegated procurement authority Report P15, P16, P56
June 2025: Orders placed for 8 food waste collection vehicles Report P69
December 2025: DEFRA confirmed food waste revenue funding is incorporated into the annual financial settlement Report P65, P85
January 2026: Design of food waste collection rounds begins Report P90, P91
March 2026: Statutory deadline for food waste collections that will not be met Report P10, P87
February to May 2026: Two further vehicles ordered, caddies received, recruitment campaign and round design work Report P92, P93
June to July 2026: First 8 food waste vehicles delivered and communications finalised Report P69, P94, P95
August 2026: Letters to households, staff training and caddy distribution Report P96, P97
September 2026: Food waste collections begin rolling out to properties Report P88, P98, P99
October 2027: National Deposit Return Scheme due to launch Report P30
2027: Micro businesses must comply with Simpler Recycling and flexible plastics collections begin Report P40, P52
Plain English for the jargon
Simpler Recycling: Government policy under the Environment Act 2021 setting consistent recycling requirements for households and businesses across the UK, including weekly food waste collections from all domestic properties.
1-2-2 model: Weekly food waste collection, two weekly refuse collection and two weekly recycling collection.
Extended Producer Responsibility (EPR): A scheme that charges businesses with over £1m turnover that supply over 25 tonnes of packaging to the UK, to fund the cost of collecting and processing packaging waste.
Deposit Return Scheme (DRS): A national scheme launching in October 2027 where consumers pay a refundable deposit on single use drinks containers which is returned when the container is taken back to a designated point.
TEEP assessment: A Technical, Economical, Environmental and Practical assessment, used here to judge whether co-mingled recycling collections should move to single stream recycling.
DEFRA: The UK Government Department for Environment, Food and Rural Affairs, which is providing the new burdens funding for food waste collections.
HVO: Hydrotreated vegetable oil, a renewable diesel substitute which the new food waste vehicles will run on.
MRF: Materials Recycling Facility, operated by Biffa on behalf of West Sussex County Council, where recycling is sorted for onward processing.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/99/25-26
Resolved
That the progress with the implementation of the requirements under Simpler Recycling be noted, particularly planning for the implementation of food waste collections 2. That the unavoidable delay with the implementation of food waste collections as a result of the late notice of government funding and the extended delivery time for new vehicles be noted. Call In: The call-in deadline for decisions will be 5.00pm on 17 February 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The Government set out changes to domestic and non-domestic waste collections under the Simpler Recycling scheme in line with the Environment Act 2021.
1.2. This report builds on reports previously presented to this Committee in February 2024 and July 2024 and provides an update on progress made towards implementing the requirements under Simpler Recycling, which notably include weekly domestic food waste collections.
2. Recommendations
2.1. That the Committee notes the progress with the implementation of the requirements under Simpler Recycling, particularly planning for the implementation of food waste collections
2.2. That the Committee notes the unavoidable delay with the implementation of food waste collections as a result of the late notice of government funding and the extended delivery time for new vehicles.
3. Background
3.1. The Government adopted the current Waste and Resource Strategy in 2018. Key policies in the strategy include:
● Consistent recycling for households and businesses across the UK, with the intention of boosting recycling rates. ● A Deposit Return Scheme (DRS) for plastic and metal drinks containers to drive high recycling rates, to incentivise recycling and to bring positive behaviours into public consciousness. ● Packaging Extended Producer Responsibility (EPR) to move the cost of dealing with household packaging waste from taxpayers and councils to the packaging producers.
3.2. The Environment Act 2021 is the vehicle for the implementation of the key strategy policies which will significantly reform local authority waste and recycling services. The most significant change is the requirement to provide food waste collections from all domestic properties by March 2026.
3.3. This Committee has received reports on how the requirements of the Act will impact service delivery in February 2024 and in July 2024 and this report provides a further update, now the funding situation has been clarified.
3.4. A key risk associated with the roll out of the new domestic food waste collection service is resourcing. The service requires:
● Capital funding for new vehicles and food waste containers; ● Funding to cover implementation costs including communications, caddy distribution, project management costs etc. ● Revenue funding to cover the day to day running costs including staffing, fuel and vehicle maintenance.
3.5. At the time of the July 2024 report levels of capital funding had been announced by DEFRA but there was no information on funding to cover implementation costs or revenue costs, other than a commitment to cover ‘reasonable costs’ with new burdens funding. 3.6. Due to the financial pressures the councils were under then, and still face now, the Committee resolved that the service could only be rolled out to the extent that the additional funding permitted whenever that was announced by DEFRA. A working assumption was made that DEFRA would fund 75% of the costs, and the roll out of the service would be phased to fit within the available budget envelope.
3.7. The recommendations agreed by this Committee in the July 2024 meeting are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.